Contract for public works engineer terminates only upon completion of works or specific statutory grounds.

Case Number 005823
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The court upheld the validity of a contract between a public works contractor and an engineer for fiscal supervision. The engineer argued for contract termination, but the authority contended the agreement remains valid until project completion. The court ruled that the contract persists throughout the execution period unless a specific statutory cause for extinction exists.

Legislator headnote

Official

EMPREITADA DE OBRAS PUBLICAS ENGENHEIRO PRESTAÇÃO DE SERVIÇOS FISCAL TECNICO DE OBRAS RESCISÃO DE CONTRATO MOTIVO DETERMINANTE

Keywords

AI generated
public works engineer contract duration fiscal supervision contract termination statutory extinction administrative contract project completion

Cited Legislation

AI generated
D. 34107 de 1944/11/13, art. 2, alíneas b, e, h, i; art. 3

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[AREA TEMATICA 1] DIR ADM GER. [AREA TEMATICA 2] DIR TRAB. [LEGISLACAO NACIONAL] D 34107 DE 1944/11/13 ART2 B - E H I ART3. [ANO DA PUBLICACAO] 1964 [Nº CONVENCIONAL] JSTA00025092 [Nº DO DOCUMENTO] SA119610414005823 [Nº DO VOLUME] XXVII [OBJECTO] DESP SSE DO FOMENTO ULTRAMARINO DE 1959/09/14. [PAGINA] 31 [PRIVACIDADE] 01 [RECORRENTE] MACHADO , HENRIQUE [RECORRIDO 1] SSE DO FOMENTO ULTRAMARINO [URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/95366D8F62D7AF11802568FC00378FAA?OpenDocument

SUMÁRIO

Contratado um engenheiro para fiscalização de determinadas obras, o seu contrato perdura por todo o tempo de execução das referidas obras, a não ser que haja outro motivo para a sua extinção.