0378/03 AI generated

Municipality cannot claim unapplied daily penalty as compensation for debt when it caused the delay itself.

Case Number 0378/03
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Administrative Court dismissed the Municipality of Castelo de Paiva's request to offset its debt with an unapplied daily penalty clause. The municipality had awarded a construction project to a specialized office, included a penalty for delays, but never applied it despite receiving the completed work. The court found that since the municipality caused the delay through procedural alterations, it could not benefit from the penalty it failed to enforce. Consequently, the court ruled that the municipality cannot use the unapplied penalty to compensate its financial debt.

Legislator headnote

Official

CONCURSO PÚBLICO. AQUISIÇÃO DE SERVIÇOS. ADJUDICAÇÃO. MULTA CONTRATUAL. RECONVENÇÃO.

Keywords

AI generated
public procurement contractual penalty unapplied fine municipal debt contractual delay administrative liability compensation offset

Cited Legislation

AI generated
DL 390/82 de 1982/09/17, Art. 7
DL 390/82 de 1982/09/17, Art. 8
DL 390/82 de 1982/09/17, Art. 9
DL 390/82 de 1982/09/17, Art. 14
DL 390/82 de 1982/09/17, Art. 15
DL 390/82 de 1982/09/17, Art. 16
DL 100/84 de 1984/03/29, Art. 53 n.1 j

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[AREA TEMATICA 1] DIR ADM ECON - AQUISIÇÃO DE BENS E SERVIÇOS.

[LEGISLACAO NACIONAL] DL 390/82 DE 1982/09/17 ART7 ART8 ART9 ART14 ART15 ART16. DL 100/84 DE 1984/03/29 ART53 N1 J.

[DATA DE ENTRADA] 02/18/2003

[Nº CONVENCIONAL] JSTA00059578

[Nº DO DOCUMENTO] SA1200310070378

[OBJECTO] SENT TAC DO PORTO.

[RECORRENTE] MUNICÍPIO DE CASTELO DE PAIVA

[RECORRIDO 1] A...

[URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/9508989942B5DF0E80256DC100494F1F?OpenDocument

SUMÁRIO

I - A Administração Autárquica que adjudicou a elaboração de um projecto de Engenharia a um Gabinete da especialidade e estabeleceu a cláusula de que podia aplicar até ao fim dos trabalhos uma multa diária por atrasos na realização da prestação e não aplicou nenhuma multa, tendo recebido e executado o projecto, não pode obter a compensação do seu débito com a multa que na acção por incumprimento no pagamento veio referir como aplicável, mas que não foi aplicada.

II - A alteração do prazo de realização do projecto por razões imputáveis à adjudicante não deixa de produzir efeitos em sede de responsabilidade civil por cumprimento defeituoso do contrato pelo facto de não ter sido objecto de aprovação ou visto do Tribunal de Contas e, por outro lado, também não estaria sujeita a visto quando não tivesse como efeito a Autarquia assumir encargos financeiros superiores aos aprovados na anterior fiscalização prévia do contrato.