Portuguese court allows expanding a claim from conciliation to full action despite prior settlement attempt.
Legislator summary
AI generatedThe court permitted the plaintiff to expand their indemnity claim from the conciliation phase to the subsequent lawsuit. Although the defendant argued that the prior conciliation attempt barred such expansion, the court found no violation of the mandatory conciliation procedure. Consequently, the request to broaden the scope of the claim was granted.
Legislator headnote
OfficialEMPREITADA DE OBRAS PÚBLICAS RESPONSABILIDADE CIVIL EXTRACONTRATUAL TENTATIVA DE CONCILIAÇÃO AMPLIAÇÃO DO PEDIDO
Keywords
AI generatedCited Legislation
AI generatedFull text
[AREA TEMATICA 1] DIR ADM CONT - CONTRATO.
[AREA TEMATICA 2] DIR PROC CIV.
[LEGISLACAO NACIONAL] DL 235/86 DE 1986/08/18 ART227 N1 ART228 N1 N6. CPC67 ART467 N1 ART498.
[ANO DA PUBLICACAO] 96
[DATA DE ENTRADA] 02/06/1996
[Nº CONVENCIONAL] JSTA00047495
[Nº DO DOCUMENTO] SA119960711039551
[OBJECTO] SENT TAC LISBOA.
[PRIVACIDADE] 01
[RECORRENTE] LUSOVIAS-CONSTRUÇÃO CIVIL LDA
[RECORRIDO 1] JAE
[URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/63C514037E24CD3B802568FC00397E26?OpenDocument
SUMÁRIO
I - Desde que a identidade do requerente e do recorrido, bem como das questões sobre interpretação, validade na execução do contrato sejam respeitadas, não se vê que o concreto pedido indemnizatório quando formulado na tentativa de conciliação não possa ser ampliado na acção que se lhe diga.
II - Em tal situação não se pode dizer que tenha havido por parte do autor daquela preterição da tentativa prévia de conciliação de que fala o n. 1 do art. 27 do DL n. 235/86, de 18 de Agosto.