Portuguese court dismisses contractor's claim for contract termination due to incomplete expropriations when work was completed and penalties applied.

Case Number 000984
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Administrative Court dismissed the contractor's appeal against a penalty imposed for exceeding the construction deadline of a public road project. Although expropriations for the required land were not fully completed at the time of the final handover, the court found the contractor had signed the handover document without objection, requested and received two extensions, and had already deducted work corresponding to the unexpropriated land. Consequently, the court ruled that the statutory defenses regarding non-performance and unjustified delays were inoperant due to the lack of evidence supporting the contractor's claims.

Legislator headnote

Official

CONTRATO ADMINISTRATIVO EMPREITADA DE OBRAS PUBLICAS PRAZO DE EXECUÇÃO DE EMPREITADA MULTA PODER DISCRICIONARIO EXPROPRIAÇÃO POR UTILIDADE PUBLICA EXCEPTIO NON ADIMPLETI CONTRATUS AUTO DE CONSIGNAÇÃO

Keywords

AI generated
administrative contract public works execution penalty for delay incomplete expropriation non-performance defense handover document contractual termination

Cited Legislation

AI generated
Decreto n. 4667 de 14 de Julho de 1918, artigos 7 e 9
Código Civil, artigo 677

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[AREA TEMATICA 1] DIR ADM GER. DIR ADM ECON - EXPRO UTIL PUBL. DIR ADM CONT - CONTRATO.

[LEGISLACAO NACIONAL] CCIV867 ART677. D 1906/05/09. D 4667 ART7 PARUNICO ART12 ART9.

[1ª PAG. DE PUBLICACAO DO ACORDAO] 0

[ANO DA PUBLICACAO] 1961

[DATA DE ENTRADA] 05/24/1957

[Nº CONVENCIONAL] JSTA00000379

[Nº DO DOCUMENTO] SAP19580724000984

[Nº DO VOLUME] X

[OBJECTO] AC 1 SECÇÃO PROC4928.

[PAGINA] 9

[PRIVACIDADE] 1

[RECORRENTE] PINTO , MANUEL

[RECORRIDO 1] MINOP - JUNTA AUTONOMA DE ESTRADAS

[URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/62BCAC6BDDFFAA65802568FC0037FFB0?OpenDocument

SUMÁRIO

Se a consignação da empreitada de construção de uma estrada - lance de Minde a Fatima - tiver sido feita como total, embora sem estarem concluidas as expropriações dos terrenos para ela necessarios, e legal a aplicação de uma multa quando se haja excedido o respectivo prazo de construção e aquela esteja prevista no contrato violado.

Favorecem a aplicação da multa as circunstancias verificadas de o auto de consignação ter sido assinado pelo empreiteiro sem oposição, de haver este solicitado duas prorrogações de prazo, que lhe foram concedidas, e ainda de terem sido descontados os trabalhos que corresponderiam ao terreno não expropriado.

E, pois, inoperante a invocação do disposto nos artigos 7 e 9 do Decreto n. 4667, de 14 de Julho de

1918, e bem assim do artigo 677 do Codigo Civil, não se verificando tambem o ambiente juridico para aplicação da invocada exceptio non adimpleti contractus por falta de prova quanto a pagamentos injustificadamente retardados.