Portuguese court dismisses contractor's claim for new work due to procedural error in contract formation.

Case Number 030598
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Administrative Court dismissed the contractor's action against the Municipal Council of Lourinhã regarding a construction project. The court determined that the work in question was not new, as the contractor had not been provided with necessary processes and projects, but rather the work was simply not included in the global price. Consequently, the plaintiff's request for contract terms adjustment was incompatible with the established facts, leading to the rejection of the cause of action.

Legislator headnote

Official

EMPREITADA DE OBRAS PÚBLICAS OBRA NOVA ERRO NA FORMA DE PROCESSO ACÇÃO CAUSA DE PEDIR IMPROCEDÊNCIA MANIFESTA

Keywords

AI generated
public works contractor new work determination contract formation error procedural incompatibility global price fixation dismissal of action administrative contract

Cited Legislation

AI generated
DL 488/71 de 1969/02/19 Art. 2 n.º 1
CCIV.66 Art. 247
CCIV.66 Art. 251

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[AREA TEMATICA 1] DIR ADM CONT - CONTRATO.

[LEGISLACAO NACIONAL] DL 48871 DE 1969/02/19 ART2 N1. CCIV66 ART247 ART251.

[ANO DA PUBLICACAO] 92

[DATA DE ENTRADA] 03/24/1992

[Nº CONVENCIONAL] JSTA00035851

[Nº DO DOCUMENTO] SA119920625030598

[OBJECTO] SENT TAC LISBOA.

[PRIVACIDADE] 01

[RECORRENTE] ANDRELO-SOC DE CONSTRUÇÕES LDA

[RECORRIDO 1] CM DA LOURINHÃ

[URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/5CF2AF90BC10198B802568FC0038AC9A?OpenDocument

SUMÁRIO

I - Se determinada obra foi prevista pelo empreiteiro na fixação do preço global da empreitada para constituição da Casa da Justiça da Lourinhã, uma de duas: a obra é nova ou apenas não foi considerada por ao empreiteiro não terem sido facultados os "processos" e "projectos", de onde aqueles constavam.

II - Tratando-se de obra nova, não era a acção proposta a idónea, pois o objecto da mesma é fixar os termos e amplitude do contrato celebrado.

III - Não sendo obra nova, então a causa de pedir - (erro da Ara., por lhe terem sido ocultados elementos decisivos para a formação da sua vontade).

IV - É incompatível com o aludido pedido, pois aquele apenas justificava pedido de anulação do referido contrato de empreitada.

V - Consequência é, pois, a improcedência da acção.