Supreme Court joins two referendum protest cases for joint adjudication to resolve procedural issues.

Case Number I NSWR 289/23
Court / Authority
Jurisdiction Poland (PL)
Outcome Partially Allowed

Legislator summary

AI generated

The Supreme Court ordered the joinder of two separate protest cases regarding the validity of the October 15, 2023, national referendum. The petitioner, J. P., challenged the referendum's validity, while the court sought to consolidate the proceedings with another case (I NSWR 16/23). This procedural decision was made to ensure a unified and efficient resolution of the overlapping legal questions raised by the protests.

Legislator headnote

AI generated

Art. 200 ust. 1 KPA; Art. 200 ust. 2 KPA: The Supreme Court may order the joinder of separate cases involving identical or closely related legal issues to ensure a unified and efficient adjudication of the merits.

Keywords

AI generated
protest against referendum joinder of cases Supreme Court procedure national referendum validity procedural consolidation

Cited Legislation

AI generated
Art. 200 ust. 1 KPA
Art. 200 ust. 2 KPA

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I NSWR 289/23 POSTANOWIENIE Dnia 15 listopada 2023 r.Sąd Najwyższy w składzie: SSN Marek Dobrowolski w sprawie z protestu J. P.‎przeciwko ważności referendum ogólnokrajowego zarządzonego na dzień 15 października 2023 r. ‎po rozpoznaniu na posiedzeniu niejawnym w Izbie Kontroli Nadzwyczajnej i Spraw Publicznych w dniu 15 listopada 2023 r. postanawia: połączyć sprawę o sygn. akt I NSWR 289/23 ze sprawą o sygn. akt I NSWR 16/23, celem łącznego rozpoznania i rozstrzygnięcia pod sygn. akt I NSWR 16/23. s.h. [ms]