I NSWR 1857/23 AI generated

Supreme Court joins two referendum protest cases for joint adjudication to resolve procedural issues.

Case Number I NSWR 1857/23
Court / Authority
Jurisdiction Poland (PL)
Outcome Partially Allowed

Legislator summary

AI generated

The Supreme Court ordered the joinder of two separate protest cases regarding the validity of the October 15, 2023, national referendum. The petitioner, Z. J., challenged the referendum's validity, while the opposing party likely contested the procedural grounds for the protest. The court decided to merge the files to ensure a unified and efficient resolution of the shared legal questions.

Legislator headnote

AI generated

Art. 200 § 1 k.p.k.; Art. 200 § 2 k.p.k.: The Supreme Court may order the joinder of separate cases involving the same legal issues to ensure a unified and efficient resolution of the dispute.

Keywords

AI generated
protest against referendum joinder of cases Supreme Court procedure national referendum validity joint adjudication

Cited Legislation

AI generated
Art. 200 § 1 k.p.k.
Art. 200 § 2 k.p.k.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I NSWR 1857/23 POSTANOWIENIE Dnia 16 listopada 2023 r.Sąd Najwyższy w składzie: SSN Aleksander Stępkowski w sprawie z protestu Z. J.‎przeciwko ważności referendum ogólnokrajowego zarządzonego na dzień 15 października 2023 r. ‎po rozpoznaniu na posiedzeniu niejawnym w Izbie Kontroli Nadzwyczajnej i Spraw Publicznych w dniu 16 listopada 2023 r. postanawia: połączyć sprawę o sygn. akt I NSWR 1857/23 ze sprawą ‎o sygn. akt I NSWR 16/23, celem łącznego rozpoznania ‎i rozstrzygnięcia pod sygn. akt I NSWR 16/23. [SOP] [ms]