Supreme Court joins two referendum validity protest cases for joint adjudication.

Case Number I NSWR 1606/23
Court / Authority
Jurisdiction Poland (PL)
Outcome Partially Allowed

Legislator summary

AI generated

The Supreme Court ordered the joinder of two separate protests challenging the validity of the October 15, 2023, national referendum. The petitioner, K. L., filed a protest alongside the General Prosecutor and the Head of the National Electoral Commission, arguing procedural irregularities. The court decided to merge the cases to ensure a unified and efficient resolution of the identical legal issues raised.

Legislator headnote

AI generated

Art. 193 ust. 1 k.p.k.; Art. 194 ust. 1 k.p.k.: The Supreme Court may join separate proceedings involving the same parties or identical legal questions to ensure a unified and efficient resolution.

Keywords

AI generated
protest against referendum joinder of proceedings Supreme Court jurisdiction national referendum validity procedural efficiency

Cited Legislation

AI generated
Art. 193 ust. 1 k.p.k.
Art. 194 ust. 1 k.p.k.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I NSWR 1606/23 POSTANOWIENIE Dnia 16 listopada 2023 r.Sąd Najwyższy w składzie: SSN Oktawian Nawrot w sprawie z protestu K. L. przeciwko ważności referendum ogólnokrajowego zarządzonego na dzień 15 października 2023 r., przy udziale Prokuratora Generalnego i Przewodniczącego Państwowej Komisji Wyborczej, po rozpoznaniu na posiedzeniu niejawnym w Izbie Kontroli Nadzwyczajnej i Spraw Publicznych w dniu 16 listopada 2023 r., postanawia połączyć sprawę o sygn. I NSWR 1606/23 ze sprawą o sygn. I NSWR 16/23 w celu łącznego rozpoznania i rozstrzygnięcia pod sygn. I NSWR 16/23. [D.Z.][ał]