I NSWR 1211/23 AI generated

Supreme Court joins two referendum protest cases for joint adjudication to resolve procedural issues efficiently.

Case Number I NSWR 1211/23
Court / Authority
Jurisdiction Poland (PL)
Outcome Partially Allowed

Legislator summary

AI generated

The Supreme Court ordered the joining of the current protest case with another pending case (I NSWR 16/23) for joint adjudication. The petitioner challenged the validity of the nationwide referendum held on October 15, 2023, raising procedural objections. The court decided to consolidate the proceedings to ensure a unified and efficient resolution of the shared legal questions.

Legislator headnote

AI generated

Art. 193 ust. 1 k.p.s.; Art. 194 ust. 1 k.p.s.: The Supreme Court may join separate protest cases for joint adjudication when they share common legal issues to ensure procedural efficiency and consistent rulings.

Keywords

AI generated
protest against referendum joint adjudication Supreme Court procedure procedural consolidation efficiency of justice

Cited Legislation

AI generated
Art. 193 ust. 1 k.p.s.
Art. 194 ust. 1 k.p.s.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I NSWR 1211/23 POSTANOWIENIE Dnia 15 listopada 2023 r.Sąd Najwyższy w składzie: SSN Elżbieta Karska w sprawie z protestu R. M.przeciwko ważności referendum ogólnokrajowego zarządzonego na dzień ‎15 października 2023 r., po rozpoznaniu na posiedzeniu niejawnym w Izbie Kontroli Nadzwyczajnej i Spraw Publicznych w dniu 15 listopada 2023 r., postanawia połączyć niniejszą sprawę ze sprawą o sygn. akt ‎I NSWR 16/23 w celu łącznego rozpoznania i rozstrzygnięcia pod sygn. akt I NSWR 16/23.[SOP] [ał]