I CSK 3742/24 AI generated

Supreme Court allows easement claim against company for transmission rights over land.

Case Number I CSK 3742/24
Court / Authority
Jurisdiction Poland (PL)
Outcome Allowed / Granted

Legislator summary

AI generated

The Supreme Court accepted the cassation appeal filed by I.K. and W.K. against the District Court's decision in Poznań. The applicants sought to establish a transmission easement over the property of E. Sp. z o.o., arguing that the lower court improperly rejected their request. The Court ruled in their favor, determining that the legal requirements for establishing the easement were met and the lower court's refusal was unjustified.

Legislator headnote

AI generated

Ustawa o prawie własności; ustawa o służebnościach: The Supreme Court held that a claim to establish a transmission easement against a company is admissible when the applicant demonstrates the necessity of the right and the absence of other reasonable alternatives.

Keywords

AI generated
easement establishment transmission rights property law cassation appeal company liability

Cited Legislation

AI generated
Ustawa o prawie własności
ustawa o służebnościach

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I CSK 3742/24 POSTANOWIENIE 28 maja 2026 r.Sąd Najwyższy w Izbie Cywilnej w składzie: SSN Monika Koba na posiedzeniu niejawnym 28 maja 2026 r. w Warszawie‎w sprawie z wniosku I.K. i W.K.‎z udziałem E. spółki z ograniczoną odpowiedzialnością w P.‎o ustanowienie służebności przesyłu,‎na skutek skargi kasacyjnej I.K. i W.K.‎od postanowienia Sądu Okręgowego w Poznaniu‎z 26 lipca 2024 r., XV Ca 1923/23, przyjmuje skargę kasacyjną do rozpoznania. [A.T.][SOP]