Court dismisses tender claim for insufficient reference period duration in public procurement combination.
Legislator summary
AI generatedThe court rejected the tender combination's request to be awarded a public participation contract after the municipality invalidated their bid due to a missing reference project. The municipality awarded the contract to a competitor because the combination's sole reference project failed to meet the mandatory 12-month duration requirement within the three-year lookback period. Consequently, the court ruled that the combination's arguments regarding the reference's content were irrelevant and dismissed their vordering entirely.
Legislator headnote
AI generatedPublic Procurement Act; Tender Directive: Where a tender requirement specifies a minimum duration for reference projects, a combination of bidders must collectively satisfy this duration requirement; failure to meet the statutory time limit renders the combination ineligible regardless of other reference qualities.