Legislator Case Law & Legislation
ECLI:NL:RBROT:2022:2643 ECLI:NL:RBROT:2022:2643 AI generated

Contractor ordered to pay delay damages and legal fees for construction delays and breach of contract.

Case Number ECLI:NL:RBROT:2022:2643
Court / Authority
Jurisdiction Netherlands (NL)
Decision Date
Outcome Partially Allowed

Legislator summary

AI generated

The court ordered the contractor to pay the plaintiffs €2,179.28 in damages for construction delays and legal fees. The court found the contractor in default from October 2020 and awarded specific delay costs based on third-party invoices, while rejecting claims for expert fees. Although the plaintiff's main claim was partially allowed, the reconvention was dismissed, and the parties were ordered to bear their own litigation costs.

Legislator headnote

AI generated

Articles 6:85, 6:96, and 6:119 of the Civil Code; A contractor is liable for delay damages under Article 6:85, and expert costs under Article 6:96 are only awarded if reasonably necessary and proportionate.

Keywords

AI generated
construction contract delay damages default liability expert fees legal costs breach of contract default interest

Cited Legislation

AI generated
Article 6:85 of the Civil Code
Article 6:96 of the Civil Code
Article 6:119 of the Civil Code
artikel 6:87 lid 1 BW
artikel 7:750 BW
artikel 6:52 BW
artikel 6:262 BW
artikel 7:754 BW
artikel 6:85 BW
artikel 6:119 BW