Court orders ProRail to award contract to Dura Vermeer and pays €1M penalty for breach of tender rules.
Legislator summary
AI generatedThe court ordered ProRail to award the 'SAAL' infrastructure project to Dura Vermeer and imposed a €1 million penalty for failing to follow tender procedures. Dura Vermeer argued that ProRail's selection process violated the 2012 Tendering Act and its specific regulations, while ProRail contended it retained discretion to re-evaluate the award. The court found ProRail's actions unlawful, granting the primary claim and rejecting ProRail's defense that it could unilaterally change the decision.
Legislator headnote
AI generatedAanbestedingswet 2012; Aanbestedingsreglement Nutssectoren 2013: The contracting authority must strictly adhere to tender regulations and cannot unilaterally alter the award decision without legal grounds, making such breaches actionable for damages and specific performance.