Court dismissed contractor's claim for full payment due to valid retention money and insolvency defense under Civil Code.
Legislator summary
AI generatedThe court dismissed the contractor's appeal to recover the full contract price, upholding the first-instance judgment that retained funds were legally justified. The contractor argued for full payment, while the construction company claimed the contract price was reduced by 5% due to its insolvency and the resulting inability to provide guarantees. The court ruled that the retention clause was a valid business practice to mitigate risks associated with the contractor's insolvency proceedings. Consequently, the court held that the contractor's right to demand full payment was barred by the statutory right to withhold performance when the creditor fails to fulfill reciprocal obligations.
Legislator headnote
AI generatedCivil Code Art. 6.46 para. 2; Contract Law Art. 6.46 para. 2: A creditor may suspend performance if the debtor fails to fulfill reciprocal obligations, and a contractual retention clause is valid when the debtor's insolvency creates a legitimate risk to the creditor's interests.
Keywords
AI generatedCited Legislation
AI generatedFull text
CivilinÄ byla NrCivilinÄ byla Nr.2A-1216-656/2014Proceso Nr. 2-68-3-24027-2013-0    Procesinio sprendimo kategorijos: 52.1., 52.3.;121.21. (S) VILNIAUS APYGARDOS TEISMAS                                                    N U T A R T I S                                                                 2014 m. balandžio 18 d.Vilnius              Vilniaus apygardos teismo Civilinių bylų skyriaus teisÄjų kolegija, susidedanti iÅ¡ kolegijos pirmininko ir praneÅ¡Äjo Andriaus Ignoto, teisÄjų Astos RadzeviÄienÄs ir Aldonos TilindienÄs, raÅ¡ytinio proceso apeliacine tvarka iÅ¡nagrinÄjo ieÅ¡kovo BUAB âLT Rangaâ, bankroto administratorius UAB âTigestaâ, apeliacinį skundÄ dÄl Vilniaus miesto apylinkÄs teismo 2013 m. lapkriÄio 14 d. sprendimo civilinÄje byloje pagal ieÅ¡kovo ieÅ¡kinį dÄl skolos priteisimo iÅ¡ atsakovo UAB âMerko statybaâ,              Kolegija, iÅ¡nagrinÄjusi bylÄ ,              n u s t a t Ä :                                                                 I.GinÄo esmÄ IeÅ¡kovas kreipÄsi į teismÄ praÅ¡ydamas iÅ¡ atsakovo priteisti 32 686,33 Lt skolÄ ir 6 procentų metines palÅ«kanas nuo priteistos sumos nuo bylos iÅ¡kÄlimo teisme iki teismo sprendimo visiÅ¡ko įvykdymo.
IeÅ¡kovas nurodÄ, kad Vilniaus apygardos teismo 2012 m. rugsÄjo 4 d. nutartimi civilinÄje byloje Nr. B2-4975-12) UAB âLT Rangaâ iÅ¡kelta bankroto byla administratoriumi paskiriant UAB âTigestaâ. Atsakovas UAB âMerko statybaâ su UAB âŽarestaâ (dabar - BUAB âLT Rangaâ) 2010-11-19 sudarÄ Statybos rangos sutartį Nr. 6117B-W0011 (toliau â Sutartis), pagal kuriÄ ieÅ¡kovas turÄjo atlikti statybos darbus objekte Secondary civil CCGP Project in Lithuanian Power Plant (9LPP).
Pagal Sutarties2011-02-22 PapildymÄ Nr. l Sutarties kaina su PVM sudaro 52 9957,38Lt, o darbų pabaiga 2011-04-15. IeÅ¡kovo bankroto administratorius, vykdydamas LR įmonių bankroto įstatymo 11 str. 3 d. 23 p. nuostatÄ , patikrino sandorius bei įgaliotam asmeniui perduotus ieÅ¡kovo buhalterinÄs atskaitomybÄs dokumentus ir nustatÄ, kad atsakovas UAB âMerko statybaâ už paslaugas pagal sutartį yra skolingas ieÅ¡kovui. Visi tarpiniai atliktų darbų aktai buvo pasiraÅ¡yti ir tai liudija, kad už visus atliktus darbus, iÅ¡skyrus 32 686,33 Lt atsakovo sulaikytÄ sumÄ , sumokÄta.
Atsakovas netinkamai aiÅ¡kina Sutarties nuostatas dÄl sulaikymo teisÄs.             Atsakovas praÅ¡Ä ieÅ¡kinį atmesti ir nurodÄ, jog rangos sutartimi ieÅ¡kovas įsipareigojo ne tik atlikti sutartus statybos darbus, bet ir prisiÄmÄ eilÄ kitų įsipareigojimų, kurių tinkamas atlikimas yra prielaida reikalauti sumokÄti visÄ sutartimi Å¡alių sutartÄ kainÄ . Å alių sutarta Sutarties kaina atspindi ieÅ¡kovo prisiimtų įsipareigojimų visumÄ , nes atsakovui yra svarbu ne tik atliekami darbai ir jų kiekis, bet ir kita su atliktais darbais gaunama nauda (tinkamai parengta iÅ¡pildomoji dokumentacija, atliktų darbų aktai, garantiniai įsipareigojimai, jų realizavimo galimybÄs).
Å alys, be darbų atlikimo papildomai susitardamos dÄl konkreÄių garantinio laikotarpio užtikrinimo priemonių, atitinkamai nustatÄ ir Sutarties kainÄ , nes ieÅ¡kovas, žinodamas apie savo pareigÄ pateikti draudimo bendrovÄs garantijÄ , iÅ¡pildomÄ jÄ dokumentacijÄ , jų kaÅ¡tus įskaiÄiuoja į savo pasiÅ«lymo kainÄ ir tai atsispindi galutinÄje Sutarties kainoje. FaktinÄ Sutarties kaina, atsižvelgiant į Å¡alių pasiraÅ¡ytos statybos rangos Sutarties papildymÄ Nr.2 bei ieÅ¡kovo atliktų darbų kiekį , yra 653.726, 67 Lt, o atsakovas sulaikÄ 32.686,33 Lt, t.y. lygiai 5 proc.; todÄl atsakovas teisÄtai ir pagrįstai naudojosi Sutarties bendrosios dalies 9.7 punkte numatyta pinigų sulaikymo teise.
IeÅ¡kovas, bÅ«damas atsakingas už tinkamÄ visų darbų atlikimÄ (įskaitant visos su darbais susijusios dokumentacijos parengimÄ ir perdavimÄ ), darbų iki galo neatliko, Galutinio perdavimo akto neparengÄ ir darbų atsakovui neperdavÄ, todÄl ieÅ¡kovas neįgijo teisÄs į visų pagal sutartį prisiimtų įsipareigojimų apmokÄjimÄ . Sutartiesbendrosios dalies 9.10 punkte numatytas juridinis faktas, dÄl kurio Sutartieskaina mažÄja 5 procentais, įvyko 2012-09-04, todÄl atsakovas teisÄtai ir pagrįstai naudojasi CK 6.58 str. numatytomis teisÄmis.
                                       II. Teismo sprendimo esmÄ Vilniaus miesto apylinkÄs teismas 2013 m. lapkriÄio 14 d. sprendimu ieÅ¡kinį atmetÄ. Teismas nustatÄ, kad ieÅ¡kovas ginÄija sulaikytos 5 procentų dydžio sumos nuo darbų kainos, kas sudaro 32 686,33 Lt dydžio sumÄ , pagrindÄ ir teigia, jog atsakovas netinkamai aiÅ¡kino Å¡alių pasiraÅ¡ytos SutartiessÄ lygas ir be teisÄto pagrindo negrÄ Å¾ina ieÅ¡kovui sulaikytos skolos už atliktus darbus sumos.
Teismas nurodÄ, kad rangovas privalo darbus pagal užsakovo nustatytas sÄ lygas atlikti laiku ir tinkamai. Pareiga atlikti darbus tinkamai reiÅ¡kia, kad darbai turi atitikti SutartiessÄ lygas, statybos rangos Sutartiesatveju â norminių statybos dokumentų reikalavimus. Å alys sutartyje susitarÄ, kad sulaikytų sumų grÄ Å¾inimas siejamas su Galutinio perdavimo akto pasiraÅ¡ymu bei įsipareigojimo pateikti garantinio laikotarpio prievolių užtikrinimÄ Ä¯vykdymu. Vadinasi, atsakovo prievolÄ sumokÄti sulaikytas pagal sutartį sumas atsiranda tik po to, kai ieÅ¡kovas įvykdo savo prieÅ¡prieÅ¡ines prievoles pagal sutartį: atlieka visus įsipareigojimus, reikalingus Galutinio perdavimo akto pasiraÅ¡ymui bei pateikia garantinio laikotarpio prievolių užtikrinimÄ .
Å i mokÄtinų sumų sulaikymo teisÄ yra savarankiÅ¡ka ir negali bÅ«ti sutapatinama su garantinio laikotarpio prievolių užtikrinimo priemonÄs alternatyva, nes Å¡ių savarankiÅ¡kų teisių pradžios ir pabaigos terminai yra skirtingi, jos turi skirtingus pagrindus prasidÄti ar pasibaigti bei jų realizavimo tvarka irgi skiriasi. Kaip buvo numatyta Sutarties bendrosios dalies 8.5 punkte - ieÅ¡kovas privalÄjo garantinio laikotarpio prievolių užtikrinimÄ pateikti per 14 dienų nuo Galutinio perdavimo akto pasiraÅ¡ymo.
Atsakovas, turÄjÄs pareigÄ Ä¯vykdyti prievolÄ pirmas, jÄ Ä¯vykdÄ apmokÄdamas 95 procentus atliktų darbų kainos, todÄl ieÅ¡kovas savo ruožtu taip pat turÄjo vykdyti kitus sutartinius įsipareigojimus ir perduoti atsakovui iÅ¡pildomosios dokumentacijos grafinÄ dalį, pateikti garantinio laikotarpio prievolių užtikrinimÄ . Teismas sutinka su atsakovo argumentu, kad Å¡alių pasiraÅ¡ytas skolų suderinimo aktas nereiÅ¡kia, kad atsakovas pripažino sulaikytÄ 5 procentų dydžio nuo visos Sutartieskainos sumÄ kaip jo nesumokÄtÄ skolÄ už ieÅ¡kovo rangos sutartimi prisiimtų įsipareigojimų įvykdymÄ .
SistemiÅ¡kai aiÅ¡kinant užsakovo mokÄtinų sumų sulaikymo teisÄ, sulaikymo sutartinÄs sÄ lygos tikslas yra užtikrinti užsakovo nuostolių padengimÄ rangovo netinkamų prievolių vykdymo atveju. NagrinÄjamo ginÄo atveju užsakovo ir rangovo pasiraÅ¡ytoje sutartyje buvo sulygta, kad tais atvejais, kai užsakovas yra pasinaudojÄs teise sulaikyti 5 procentų dydžio rangovui mokÄtinÄ sumÄ , o rangovui yra keliama bankroto byla, teismo nutarties dÄl bankroto bylos iÅ¡kÄlimo rangovui priÄmimas yra juridinis faktas, kuriam įvykus Sutarties kaina be atskiro Å¡alių susitarimo yra sumažinama Sutarties pecialiosios dalies 7.2 punkte nurodyta suma, kas konkreÄiu ginÄo atveju sudaro 5 procentus ir yra lygi 32 868,33 Lt.
Vadinasi, užsakovas (atsakovas) ir rangovas (ieÅ¡kovas) sutartyje buvo numatÄ prevencinÄ sÄ lygÄ , pagal kuriÄ iÅ¡ esmÄs rangovas įsipareigojo užsakovui savo statybų verslo veiklÄ vykdyti taip, kad bÅ«tų iÅ¡vengta bankroto ar restruktÅ«rizavimo, kadangi rangovo bankroto ar restruktÅ«rizavimo atveju neabejotinai apsunkinamas rangos Sutarties tÄstinių įsipareigojimų, tokių kaip garantinÄ priežiÅ«ra ir kt., vykdymas. Teismas konstatavo, kad atsakovas teisÄtai pasinaudojo savigynos priemonÄmis - prievolÄs vykdymo sustabdymu.
Pagal CK 6.46 str. 2 d. skolininkas turi teisÄ sustabdyti prievolÄs vykdymÄ , kai kreditorius nevykdo savo prieÅ¡prieÅ¡inÄs pareigos, jeigu skolininko ir kreditoriaus prieÅ¡prieÅ¡inÄs pareigos susijusios taip, kad galima pateisinti prievolÄs vykdymo sustabdymÄ . CK 6.58 str. l d. taip pat nustatyta, kad jeigu sutartinÄs prievolÄs įvykdymas yra prieÅ¡prieÅ¡inis, o prievolÄs Å¡alis, kuri pirma turi atlikti veiksmus prievolei vykdyti, prievolÄs nevykdo arba yra aiÅ¡ku, jog nustatytu terminu jo neįvykdys, kita prievolÄs Å¡alis turi teisÄ sustabdyti prieÅ¡prieÅ¡inį savo prievolÄs vykdymÄ arba apskritai atsisakyti ir vykdyti, apie tai praneÅ¡ti kitai Å¡aliai ir pareikalauti atlyginti nuostolius.
Pagal CK 6.58 str. 3 d., jeigu sutartinÄ prievolÄ viena jos Å¡alis įvykdÄ nevisiÅ¡kai, kita prievolÄs Å¡alis turi teisÄ sustabdyti prieÅ¡prieÅ¡inį savo prievolÄs vykdymÄ arba atsisakyti jÄ Ä¯vykdyti tiek, kiek prievolÄs neįvykdÄ Å¡alis, privalÄjusi jÄ Ä¯vykdyti pirma; kai Å¡alys savo prievoles turi įvykdyti viena paskui kitÄ , tai turinti sutartį įvykdyti vÄliau Å¡alis gali sustabdyti vykdymÄ tol, kol kita Å¡alis neįvykdo savo prievolių. IeÅ¡kovas savo prievolių, prisiimtų statybos rangos sutartimi pilna apimtimi tinkamai neįvykdÄ (neparengÄ ir neperdavÄ iÅ¡pildomosios dokumentacijos, neparengÄ Galutinio perdavimo akto, nepateikÄ garantinio laikotarpio prievolių užtikrinimo), nepateikÄ adekvataus savo prievolÄs įvykdymo užtikrinimo.
IeÅ¡kovas savo prievolÄ turÄjo įvykdyti pirmiau nei atsakovas, o ieÅ¡kovo ir atsakovo prieÅ¡prieÅ¡inÄs pareigos susijusios taip, kad galima pateisinti prievolÄs vykdymo sustabdymÄ , todÄl konstatuotina, kad atsakovas teisÄtai pasinaudojo savigynos priemonÄmis ir bendrÄ Sutarties kainÄ , mokÄtinÄ rangovui, sumažino sulaikyta 5 procentų dydžio suma. AplinkybÄ, kad užsakovas, tikÄtina, siekdamas nevilkinti tolesnių galutinio objekto statybos darbų ir nepažeisti tretiesiems asmenims prisiimtų įsipareigojimų, savo iniciatyva sprendÄ trÅ«kstamų dokumentų pateikimo klausimÄ , nelemia, jog ieÅ¡kovas savaime buvo atleistas nuo ieÅ¡kovo ir rangovo pasiraÅ¡ytoje statybos rangos sutartyje prisiimtų kitų, tiesiogiai susijusių su konkreÄiais statybos darbais, įsipareigojimų vykdymo.
AplinkybÄ, kad atsakovas priÄmÄ tarpinius darbus ir yra pasiraÅ¡ytas statybos užbaigimo aktas, neįrodo, jog visi rangovo atlikti darbai buvo padaryti tinkamai, visi reikalingi dokumentai pateikti. Statybos užbaigimo aktas, neįrodo, kad ieÅ¡kovas pateikÄ trÅ«kstamÄ dokumentacijÄ .                III. Apeliacinio skundo ir atsiliepimo argumentai IeÅ¡kovas pateikÄ apeliacinį skundÄ , kuriuo praÅ¡Ä panaikinti pirmosios instancijos teismo sprendimÄ ir priimti naujÄ sprendimÄ ieÅ¡kinį patenkinti.
Apeliacinis skundas grindžiamas Å¡iais argumentais: Teismas nepagrįstai vadovavosi Sutarties Bendrosios dalies 9.7 punktu, pagal kurį sulaikyta suma rangovui turi bÅ«ti sumokÄta per tris dienas nuo rangovo įsipareigojimų, nurodytų Sutarties Bendrosios dalies 8.5 punkte įvykdymo. Teismas nesiremdamas jokia konkreÄia Sutarties nuostata nepagrįstai nusprendÄ kad sulaikytų pinigų grÄ Å¾inimas siejamas su galutinio akto perdavimo pasiraÅ¡ymu ir įsipareigojimo pateikti garantinio laikotarpio prievolių užtikrinimų įvykdymu.
Sutarties Bendrosios dalies 8.5. punkto sÄ lygos įvykdytos ir to nepaneigÄ pirmosios instancijos teismas. Apeliantas įvykdÄ Bendrosios dalies 8.5 punkte numatytÄ savo sutartinÄ prievolÄ, t.y. pateikÄ Sutarties sÄ lygas atitinkanÄiÄ garantinio laikotarpio įsipareigojimų užtikrinimo garantijÄ . Sutarties Bendrosios dalies 9.7 punktas nenumato, kaip teigÄ teismas, kad sulaikyta suma grÄ Å¾inama, kai rangovas atlieka visus įsipareigojimus reikalingus Galutinio perdavimo akto pasiraÅ¡ymui bei pateikia garantinio laikotarpio prievolių užtikrinimÄ .Iki ieÅ¡kovo kreipimosi į teismÄ , atsakovas 2013-02-21 raÅ¡te ieÅ¡kovui nurodÄ, kad 32686,33 Lt sumÄ sulaikÄ vadovaujantis Sutarties Bendrosios dalies 7.2 punktu.
Sulaikymo teise naudojosi, nes nebuvo pateikta garantinio laikotarpio užtikrinimo garantija, taÄiau, pradÄjus bylÄ nagrinÄti teisme, atsakovas nurodÄ, kad nesinaudojo sutartyje numatyta sulaikymo teise, kaip garantinio laikotarpio įsipareigojimų užtikrinimo priemone.Teismas nepagrįstai konstatavo, kad bankroto bylos iÅ¡kÄlimo ieÅ¡kovui faktas sudarÄ galimybÄ atsakovui pasinaudoti Sutarties 9.10 punkte numatytomis teisÄmis. TaÄiau Vilniaus miesto apygardos teismo nutartis dÄl bankroto bylos iÅ¡kÄlimo ieÅ¡kovui įsiteisÄjo nuo Lietuvos apeliacinio teismo 2012-12-20 nutarties priÄmimo, o skolinis atsakovo įsipareigojimas grÄ Å¾inti pinigus atsirado dar 2011 m.
Atsakovas piktybiÅ¡kai sulaikÄ pinigus iki kol ieÅ¡kovui buvo iÅ¡kelta bankroto byla. Teismas netyrÄ aplinkybių, kad ieÅ¡kovas neparengÄ ir neperdavÄ iÅ¡pildomosios dokumentacijos.Atsakovas pažeidÄ CK 6.58 str. nustatytas savigynos taikymo nuostatas, nes ieÅ¡kovo sutartimi prisiimti įsipareigojimai turÄjo bÅ«ti įvykdyti nuo 2011-04-15, o užsakovas sugalvojo taikyti savigynos priemonÄ nuo 2013-02-07 â praÄjus beveik dviem metams. Statybos objektas dar 2012-10-15 priduotas valstybinei komisijai.
Atsakovas neapsisprendÄ, ar jis skolos nemoka vadovaudamasis Sutarties Bendrosios dalies 9.7 punkte numatyta sulaikymo teise, ar atsakovas naudojasi CK 6.58 str. nustatyto savigynos instituto teise. NepagrindÄ, kad 32686,33 Lt suma sudaro faktinius nuostolius.              Atsakovas atsiliepime praÅ¡Ä apeliacinį skundÄ atmesti. Atsiliepimas grindžiamas Å¡iais argumentais:Piniginių sumų sulaikymas pagal Sutarties Bendrosios dalies 9.7 punktÄ ir piniginių sumų sulaikymas kaip garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ (Sutarties Specialiosios dalies 7.2 b punktas) yra dvi savarankiÅ¡kos atsakovo teisių gynimo priemonÄs, kurios yra įgyvendinamos skirtingais Sutarties vykdymo etapais, skirtos užtikrinti skirtingus apelianto įsipareigojimus;
Å¡ių priemonių pradžios ir pabaigos terminai yra skirtingi ir susijÄ taip, kad antroji (t.y. numatytoji Sutarties Specialiosios dalies 7.2 b) punkte) negali prasidÄti kol nepasibaigÄ pirmoji (t.y. numatytoji Sutarties Bendrosios dalies 9.7 punkte).Sutarties Bendrosios dalies 9.7 punkte numatyta atsakovo teisÄ pasibaigtų, kai apeliantas iÅ¡pildytų atitinkamas Bendrosios dalies 9.7 b) punkto ii) papunkÄio sÄ lygas, t.y. po Galutinio akto be iÅ¡lygų pasiraÅ¡ymo pateiktų garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ.
Atkreiptinas dÄmesys į tai, kad 9.7 b) punktas numato, kad turi bÅ«ti iÅ¡pildytos abi sÄ lygos, t.y. ir pasiraÅ¡ytas Galutinis perdavimo aktas, ir pateikta garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ.Apeliantas sulaikytÄ pagal Bendrosios dalies 9.7 punktÄ sumÄ nepagrįstai traktuoja kaip Bendrosios dalies 8.5 punkte numatyto įsipareigojimo įvykdymÄ . Garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ galima pateikti tik po to, kai yra pasiraÅ¡omas Galutinis perdavimo aktas (Sutarties Bendrosios dalies 8.5 punktas), kuris yra siejamas ir garantinio laikotarpio pradžia (Sutarties Specialiosios dalies 7.1 punktas); - Pinigų sulaikymas kaip garantinio laikotarpio įsipareigojimų užtikrinimo alternatyva (Sutarties Specialiosios dalies 7.2 b) punktas) yra siejama bÅ«tent su apelianto pasirinkimu.
Å is pasirinkimas turi bÅ«ti objektyviai iÅ¡reikÅ¡tas ir apie tai informuotas atsakovas (informavimo bÅ«dus ir priemones reglamentuoja Sutarties Bendrosios dalies 13 straipsnio nuostatos). Bet apeliantas niekada nÄra praneÅ¡Äs atsakovui, kad jis pasirinko ir/ar pateikÄ vienÄ ar kitÄ prievolių užtikrinimo priemonÄ - tai rodo, kad apeliantas niekada pats nemanÄ kad yra įvykdÄs savo sutartinius įsipareigojimus tiek, kad galÄtų pateikti garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ.Viso objekto statybos darbų užbaigimo aktas pasiraÅ¡ytas 2012-10-15.
Visas objektas yra itin sudÄtingas ir brangus, kainavÄs 1,3 milijardo litų. Apelianto atliktų darbų dalis yra itin maža, todÄl viso objekto statybos darbų užbaigimo aktas pasiraÅ¡ytas 2012-10-15 negali patvirtinti 2011 metais atsakovo atliktų darbų tinkamumo. Apeliantas neatliko visų darbų (neatliktų darbų likutis â 16101,16 Lt), neparengÄ ir nepateikÄ Galutinio perdavimo akto, todÄl atsakovas darbus užbaigÄ ir iÅ¡pildomÄ jÄ dokumentacijÄ parengÄ savo jÄgomis. I                                       IV.
ApeliacinÄs instancijos teismo argumentai              Bylos nagrinÄjimo apeliacine tvarka ribas sudaro apeliacinio skundo faktinis ir teisinis pagrindas bei absoliuÄių sprendimo negaliojimo pagrindų patikrinimas (CPK 320 str. 1 d.). TeisÄjų kolegija, iÅ¡nagrinÄjusi bylos medžiagÄ , absoliuÄių sprendimo negaliojimo pagrindų, numatytų CPK 329 straipsnio 2 dalyje nenustatÄ.                           Apeliacinis skundas atmetamas.             Teismas Å¡alių 2010-11-19 sudarytÄ Statybos rangos sutartį Nr. 6117B-W0011 aiÅ¡kina vadovaudamasis CK 6.193 str. iÅ¡dÄstytomis sutarÄių aiÅ¡kinimo taisyklÄmis.
Visos sutarties sÄ lygos turi bÅ«ti aiÅ¡kinamos atsižvelgiant į jų tarpusavio ryšį, Sutarties esmÄ ir tikslÄ bei jos sudarymo aplinkybes. AiÅ¡kinant sutartį, reikia atsižvelgti ir į įprastines sÄ lygas, nors jos sutartyje nenurodytos, taip pat turi bÅ«ti atsižvelgiama į Å¡alių derybas dÄl sutarties sudarymo, Å¡alių tarpusavio santykių praktikÄ , Å¡alių elgesį po sutarties sudarymo ir paproÄius (CK 6.193 str. 2 d. ir 5 d.). TeisÄjų kolegija sutinka su atsakovo argumentu, kad piniginių sumų sulaikymas pagal Sutarties bendrosios dalies 9.7 punktÄ ir piniginių sumų sulaikymas, numatytas Sutarties specialiosios dalies 7.2 b punkte yra garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ, t.y. dvi savarankiÅ¡kos atsakovo teisių gynimo priemonÄs, kurios yra įgyvendinamos skirtingais Sutarties vykdymo etapais.
Antrosios priemonÄs, numatytos Sutarties Specialiosios dalies 7.2 b) punkte, galiojimas negali prasidÄti kol nepasibaigÄ pirmoji priemonÄ numatyta Bendrosios dalies 9.7 punkte. Sutarties vykdymo metu Å¡alys nuosekliai ir naudojosi Sutarties Bendrosios dalies 9.7 punkte numatyta priemone, t.y. nuo kiekvienos apmokamos sÄ skaitos sulaikinÄjo po 5 procentus apmokamos sumos, kol susidarÄ visa sulaikyta 32686,33 Lt suma; susiraÅ¡inÄjime su ieÅ¡kovu atsakovas akcentavo, kad naudojasi bÅ«tent Bendrosios dalies 9.7 punkte nustatyta teise.
Sutarties Bendrosios dalies 9.7 punkte numatyta atsakovo teisÄ pasibaigtų, kai atsakovas įvykdytų Bendrosios dalies 9.7 b) punkto ii) papunkÄio sÄ lygas, t.y. po Galutinio akto be iÅ¡lygų pasiraÅ¡ymo pateiktų garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ. Bendrosios dalies 9.7 b) punktas numato, kad turi bÅ«ti iÅ¡pildytos abi sÄ lygos, t.y. ir pasiraÅ¡ytas Galutinis perdavimo aktas, ir pateikta garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ.             Apeliantas sulaikytÄ pagal Bendrosios dalies 9.7 punktÄ sumÄ nepagrįstai traktuoja kaip Bendrosios 8.5 punkte numatyto įsipareigojimo įvykdymÄ . BesÄ lyginÄ pirmo pareikalavimo garantinio laikotarpio įsipareigojimų pagal sutartį įvykdymo garantija turi bÅ«ti užtikrinamas bÅ«tent statybos darbų garantinio laikotarpio įsipareigojimų vykdymas, o neprasidÄjus garantiniam laikotarpiui nebÅ«tų galimybÄs ja pasinaudoti, taip pat nebÅ«tų galima nustatyti pateiktinos priemonÄs galiojimo termino.
Garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ galima pateikti tik po to, kai yra pasiraÅ¡omas Galutinis perdavimo aktas (Sutarties Bendrosios dalies 8.5 punktas), kuris yra siejamas ir garantinio laikotarpio pradžia (Sutarties Bendrosios dalies 7.1 punktas). Pinigų sulaikymas kaip garantinio laikotarpio įsipareigojimų užtikrinimo alternatyva banko arba nurodytų draudimo bendrovių garantijoms (Sutarties Specialiosios dalies 7.2 b) punktas) yra siejama bÅ«tent su apelianto pasirinkimu. IeÅ¡kovas turÄjo praneÅ¡ti, kuriÄ garantinio laikotarpio prievolių užtikrinimo alternatyvÄ renkasi pagal Sutarties Bendrosios dalies 13 straipsnio nuostatos.
Byloje nustatyta, kad ieÅ¡kovas (apeliantas) niekada nÄra praneÅ¡Äs atsakovui, kad jis pasirinko ir/ar pateikÄ vienÄ ar kitÄ prievolių užtikrinimo priemonÄ. Toks apelianto elgesys patvirtina, kad apeliantas niekada pats nemanÄ kad yra įvykdÄs savo sutartinius įsipareigojimus tiek, kad galÄtų pateikti garantinio laikotarpio įsipareigojimų užtikrinimo priemonÄ. Apeliantas savo 2013 m. gegužÄs 23 d. praneÅ¡ime atsakovui nurodÄ, kad â... tikÄtina Užsakovas (t.y. Atsakovas) taikÄ Statybos rangos SutartiesNr. 6117B-W0011 specialios dalies 7.2. punkto (b) papunktį ir kaip garantijÄ sulaikÄ mokÄtinÄ Rangovui (t.y.
Apeliantui) sumÄ ...â (b.l.54-55). TeisÄjų kolegijos vertinimu, apeliantas praneÅ¡imo dÄl užtikrinimo bÅ«do pasirinkimo neteikÄ ir tikÄjosi kad atsakovas âtaikÄâ Specialiosios dalies 7.2 b) punkto nuostatÄ .             TeisÄjų kolegija, taip pat atsižvelgia į Å¡alių sudarytos Sutarties nuostatų, dÄl kurių aiÅ¡kinimo vykstÄ ginÄas, tikslÄ . IeÅ¡kovas atliko tik dalį atsakovo statomo didelio objekto darbų. Akivaizdu, kad atsakovas, bÅ«damas ieÅ¡kovo darbų užsakovu siekÄ, kad ieÅ¡kovas siekÄ ir atsakovas neturÄjo pagrindo manyti kitaip, kad darbų rezultato kokybÄs garantija turi įsigalioti po viso objekto užbaigimo ir pridavimo.
Byloje nustatytos faktinÄs aplinkybÄs, kad apeliantas darbus pagal sutartį turÄjo pabaigti iki 2011.04.15 d. Apeliantas paskutinius darbus pagal Sutartį perdavÄ 2011.06.23 (b.l.60), ir liko neatlikÄs dalies darbų (likutis pagal aktÄ - 16.101,16 Lt) (b.l.60-61). Viso objekto Statybos užbaigimo aktas jokiu bÅ«du negali patvirtinti apelianto atliktų darbų tinkamumo 2011 metais. Sutarties Bendrosios dalies 2.1.3, 6.2, 6.11 punktus Galutinį aktÄ parengti ir pateikti atsakovui privalÄjo apeliantas. Apeliantas neneigia, kad jis neparengÄ ir nepateikÄ Galutinio perdavimo akto, nors privalÄjo tai padaryti, taÄiau apeliaciniame skunde tik deklaratyviai teigia, kad pirmosios instancijos teismas netyrÄ aplinkybių, kad ieÅ¡kovas neparengÄ ir neperdavÄ iÅ¡pildomosios dokumentacijos.
Pats ieÅ¡kovas neįrodinÄjo aplinkybių apie tinkamÄ savo įsipareigojimų įvykdymÄ .              Apeliacinio skundo argumentas, kad užsakovas (atsakovas) sugalvojo taikyti savigynos priemonÄ nuo 2013-02-07, nepagrįstas. IeÅ¡kovas nepaneigÄ teismo posÄdžio metu duotų atsakovo paaiÅ¡kinimų, kad trÅ«kstamus apelianto neatliktus darbus ir nepateiktÄ iÅ¡pildomÄ jÄ dokumentacijÄ sutvarkÄ savo jÄgomis, siekdamas iÅ¡vengti darbų ir dokumentų rengimo uždelsimo, galinÄio įtakoti viso objekto statybÄ ir atitinkamai atsakovo atsakomybÄ prieÅ¡ generalinį objekto rangovÄ .
LR CK 6.698 str. 2 d. numato, kad âgarantiniai terminai pradedami skaiÄiuoti nuo darbų rezultato atidavimo naudoti dienosâ; LR Statybos įstatymo 36 str. 1 d. numato, kad garantinis terminas skaiÄiuojamas nuo statinio pripažinimo tinkamu naudoti dienos. Preziumuojama, kad darbų kokybÄs garantija taikoma darbų rezultato sudÄtinÄms dalims (CK 6.664 str. 2 d.). TeisÄjų kolegijos vertinimu, statybos darbai turi bÅ«ti užbaigti ir perduoti kaip visuma, ir tik nuo tokio perdavimo gali bÅ«ti pradÄtas skaiÄiuoti garantinis terminas.
Sutarties Objekto statyba buvo užbaigta 2012-10-15, kÄ patvirtina statybos užbaigimo aktas Nr. SUA-00- 121015-00362 (b.l.96-98). Nurodytų aplinkybių visuma lemia tai, kad ieÅ¡kovo atliktų darbų kokybÄs garantijos laikotarpis prasidÄjo 2012-10-15, todÄl tik nuo Å¡io momento prasidÄjo Sutarties Specialiosios dalies 7.2 b) punkte nustatytos Sutarties vykdymo garantijos priemonių taikumo laikotarpis. Å alių pasiraÅ¡ytoje sutartyje buvo sulygta, kad tais atvejais, kai užsakovas yra pasinaudojÄs teise sulaikyti 5 procentų dydžio rangovui mokÄtinÄ sumÄ , o rangovui yra keliama bankroto byla, teismo nutarties dÄl bankroto bylos iÅ¡kÄlimo rangovui priÄmimas yra juridinis faktas, kuriam įvykus Sutarties kaina be atskiro Å¡alių susitarimo yra sumažinama Sutarties specialiosios dalies 7.2 punkte nurodyta suma, kuri sudaro 5 procentus ir yra lygi 32 868,33 Lt (b.l.28).
Vadinasi, užsakovas (atsakovas) ir rangovas (ieÅ¡kovas) sutartyje buvo numatÄ prevencinÄ sÄ lygÄ , pagal kuriÄ iÅ¡ esmÄs rangovas įsipareigojo užsakovui savo statybų verslo veiklÄ vykdyti taip, kad bÅ«tų iÅ¡vengta bankroto ar restruktÅ«rizavimo. Pagrįsta pirmosios instancijos teismo iÅ¡vada, kad rangovo bankroto ar restruktÅ«rizavimo iÅ¡kÄlimo atveju iÅ¡ esmÄs apsunkinamas rangos Sutarties tÄstinių įsipareigojimų, tokių kaip kelis metus trunkanti garantinÄ priežiÅ«ra ir kt., vykdymas, kas kelia prielaidÄ , todÄl rangovo bankroto ar restruktÅ«rizavimo atveju bÅ«tų pažeidžiami teisÄti užsakovo lÅ«kesÄiai, kilÄ dÄl pirminių statybos rangos sutartyje sulygtų sÄ lygų įgyvendinimo.
Akivaizdu, kad rangovas, kuriam iÅ¡kelta bankroto byla, negalÄs pateikti banko ar draudimo bendrovÄs garantijų arba pats suteikti garantinÄs priežiÅ«ros paslaugas, todÄl užsakovo elgesys sulaikant garantijos dydį atitinkanÄiÄ pinigų sumÄ yra pagrįstas sÄ Å¾iningos verslo praktikos požiÅ«riu. Duomenų, kad ieÅ¡kovo bankroto byla bus užbaigta taikos sutartimi ir ieÅ¡kovas tÄs įprastÄ veiklÄ , nÄra.             Be to, pagal CK 6.46 str. 2 d. skolininkas turi teisÄ sustabdyti prievolÄs vykdymÄ , kai kreditorius nevykdo savo prieÅ¡prieÅ¡inÄs pareigos, jeigu skolininko ir kreditoriaus prieÅ¡prieÅ¡inÄs pareigos susijusios taip, kad galima pateisinti prievolÄs vykdymo sustabdymÄ .Vadovaudamasi Lietuvos Respublikos civilinio proceso kodekso 326 straipsnio 1 dalies 1 punktu, 331 straipsniu, teisÄjų kolegija                                                                n u t a r i a :
                          Vilniaus miesto apylinkÄs teismo 2013 m. lapkriÄio 14 d. sprendimÄ palikti nepakeistÄ .                        Kolegijos pirmininkas                                                                         Andrius Ignotas           Kolegijos teisÄjos                                                                            Asta RadzeviÄienÄ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Aldona TilindienÄ