High Court dismisses judicial review challenging planning permission for data centre on climate grounds.
Legislator summary
AI generatedThe High Court dismissed the applicants' judicial review challenging a planning permission for a data centre development. The applicants, including environmental NGOs and climate scientists, argued the decision violated climate legislation and failed to mandate renewable energy sources. The court held that the applicants failed to discharge their onus of proving the decision was outside the Commission's options, noting that policy documents were flexible rather than prescriptive and that the decision was rational and valid.
Legislator headnote
AI generatedSection 50 of the Planning and Development Act 2000; Section 15 of the Climate Action and Low Carbon Development Act 2015: Judicial review is limited to reviewing legality rather than merits, and applicants must discharge the onus to demonstrate a decision falls outside the spectrum of options open to the decision-maker.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
[2026] IEHC 156
THE HIGH COURT
PLANNING & ENVIRONMENT
[H.JR.2024.0000708]
IN THE MATTER OF SECTION 50 OF THE PLANNING AND DEVELOPMENT ACT 2000 AND
SECTION 15 OF THE CLIMATE ACTION AND LOW CARBON DEVELOPMENT ACT 2015
BETWEEN
COLIN DOYLE, FRIENDS OF THE IRISH ENVIRONMENT CLG, FUTUREPROOF CLARE,
MARTIN KNOX AND CHRISTINE SHARP
APPLICANTS
AND
AN COIMISIÚN PLEANÁLA, THE GOVERNMENT OF IRELAND, IRELAND AND THE
ATTORNEY GENERAL
RESPONDENTS
AND
ART DATA CENTRES LIMITED
NOTICE PARTY
(No. 3)
Date of impugned decision: 5 April 2024
Date proceedings commenced: 30 May 2024
Date of main hearing of Module I: 25 February 2025
Date of main hearing for Module II: 2 March 2026
Date draft judgment circulated: 6 March 2026
JUDGMENT of Humphreys J. delivered on Friday the 13th day of March 2026
1. The applicants who challenge a data centre development here comprise two environmental
NGOs with a strong record of relevant activism, and three individuals who have obviously very
genuine concerns and strong awareness of the ramifications of the climate emergency. The first
named applicant Dr Doyle holds a BA (Mod) in Physics, an MSc in Physics, a Postgraduate Diploma
in Environmental Pollution, and a PhD in Climate Science. He has over twenty-five years of
experience in environmental science in Ireland, including consultancy in the preparation of
environmental impact assessments and emissions monitoring for a wide range of industrial and
commercial projects. The fourth named applicant is a retired academic and environmental manager.
The fifth named applicant is a horticulturalist and an environmental activist. Professor Daly who is
well-known for her penetrating and lucid contributions to public understanding of climate science
has weighed in to support the applicants, along with a body of other material and affidavits put
forward. The primary question for the court, however, is not whether it would have interrogated
the application for permission more sceptically. It is whether the applicants have overcome the onus
to demonstrate that the permission fell outside the spectrum of options open to the commission in
determining what was consistent with the matters referred to in climate legislation. Judicial review
is not politics by other means. As far as jurisdictions like ours are concerned, a court’s role, to state
the obvious, is to limit itself to reviewing the legality rather than merits of any given decision, and
to do so by reference only to the issues that are duly pleaded and that properly arise, having regard
to what was before the decision-taker, and within the confines of the substantive law, particularly
as definitively interpreted domestically by the apex court within the given jurisdiction, and by the
CJEU in the case of European law issues where those arise, as well as subject to the rules of forensic
engagement, particularly the onus of proof generally resting with a challenger. Upholding a decision
is not necessarily an endorsement of its merits any more than quashing a decision is necessarily
indicative of a lack of merit. Amongst the many aspects of the case one could highlight at the outset,
three points particularly stand out. Firstly, by virtue of the game-changing response document from
John Spain Associates, this is a project that is going to be powered from renewable energy. It is
therefore a project that prima facie the commission was able to regard as not being one that in
itself causes major net emissions. Secondly, the climate challenge is virtually exclusively
pleaded as a matter of domestic law. No principle of EU law (such as the EU Charter, art. 191(2)
TFEU, the polluter pays principle, the European Climate Law (Regulation 2021/1119), Council
Regulation (EU) 2022/2577 (see Case C-325/25 Eneco Wind) or otherwise) is pleaded in that regard.
Even the environmental impact assessment (EIA)/ habitats directive/ derogation licence issue is
focused on bats, not on climate. The strategic environmental assessment (SEA) and water
framework (WFD) directive points were not pursued. The glancing and purely narrative reference
to the environmental impact assessment report (EIAR) in sub-ground 25 does not constitute a proper
or any legal plea of contravention of EU law. And thirdly, this was a case where the applicants did
not suggest to the other parties the possibility of seeking input from independent expert
scientific entities (such as the Environmental Protection Agency (EPA) for example) in an amicus
role to assist the court on any of the more general questions, given the particular difficulties that
arise in science-heavy climate litigation, as discussed in Friends of Killymooney Lough v. An
Coimisiún Pleanála No. 1 [2025] IEHC 407 (Unreported, High Court, 8 July 2025) at 174.
Judgment history
2. In Doyle v. An Bord Pleanála (No. 1) [2025] IEHC 158 (Unreported, High Court, 21 March
2025), I held that the inspector’s failure to acknowledge the single Leisler’s bat (Nyctalus leisleri)
roost in Building 6C constituted a harmless error which did not warrant quashing the permission and
dismissed the applicants’ case in relation to Module I of the proceedings.
3. In Doyle v. An Bord Pleanála (No. 2) [2025] IEHC 205 (Unreported, High Court, 11 April
2025), the applicants argued that their Module I costs of making failed points should be reserved
rather than be the subject of no order, a submission which I rejected.
Geographical context
4. Two related commission decisions are challenged here. The data centre decision
(https://www.pleanala.ie/en-ie/case/314474), involves the construction of six two-storey data
centre buildings, associated structures and all ancillary site works on a 60 hectare site at Tooreen,
Cahernalough and adjacent townlands, Tulla Road, Ennis, Co. Clare, subject to conditions for a 10-
year period at Tooreen, Cahernalough, Knockanean, Ballymacahill, Muckinish and Rosslevan, Tulla
Road, Ennis, Co. Clare
5. The substation decision (https://www.pleanala.ie/en-ie/case/313895) involves the
development of a 110 kV GIS substation with two 110 kV underground transmission cables
connecting to existing 110 kV overhead lines to the north, and two 110 kV underground cables
connecting to the existing Ennis 110 kV substation and associated works in the Townlands of
Tooreen, Cahernalough, Knockanean, Ballymacahill, Muckinish and Rosslevan to the north-east of
Ennis, on the Tulla Road (R352), Co. Clare.
Facts
6. On 16 July 2021, the notice party submitted a planning application to Clare County Council
for a development comprising the construction of six two-storey data centre buildings, associated
structures and all ancillary site works on a 60 hectare site at Tooreen, Cahernalough and adjacent
townlands, Tulla Road, Ennis, Co. Clare (planning reg. ref. no. 21/757 refers). The data centre
application was accompanied by, inter alia, an EIAR and a Natura impact statement (NIS).
7. On 8 September 2021, the planning authority requested further information in relation to
the data centre application (RFI) and a response to the RFI was provided on behalf of the notice
party on 25 February 2022. The RFI response was readvertised as required by the planning authority
on the basis that it contained significant additional data.
8. Clarification on the RFI response was sought by the planning authority on 28 April 2022, and
a reply to same was submitted on 10 June 2022, which included an updated EIAR (described in the
commission’s order as a “consolidated EIAR”). Chapter 8 of the consolidated EIAR includes the
following:
“Electricity providers form part of the EU-wide Emission Trading Scheme (ETS) and thus
greenhouse gas emissions from these electricity generators are not included when
determining compliance with the targeted 30% reduction in the non-ETS sector i.e.
electricity associated greenhouse gas emissions will not count towards the Effort Sharing
Decision target. Thus, any necessary increase in electricity generation due to data centre
demand will have no impact on Ireland’s obligation to meet the EU Effort Sharing Decision.
Under this scenario, as outlined in the Regulation, the new electricity provider will be treated
as a ‘new entrant’ under Phase IV of the ETS (i.e. an electricity generator obtaining a
greenhouse gas emissions permit for the first time after 30th June 2018). The new electricity
provider will be required to purchase allocations in the same manner as existing players in
the market using the European Energy Exchange. EU leaders have also decided that during
Phase IV (2021-2030) 90% of the revenue from the auctions will be allocated to the Member
States on the basis of their share of verified emissions with 10% allocated to the least
wealthy EU member states. The revised EU ETS Directive has enshrined in law the
requirement that at least 50% of the auctioning revenues or the equivalent in financial value
should be used for climate and energy related purposes.
…
In terms of the Proposed Development, as the facility generates over the threshold of 20
MW, a greenhouse gas emission permit will be required which will be regulated under the
ETS scheme also. Thus, whether the facility is operated by electricity or gas engines onsite,
the emissions are not included when determining compliance with the targeted 30%
reduction in the non-ETS sector. In addition, on a EU-wide basis, where the ETS market in
2018 is approximately 1,655 million tonnes CO2eq, the impact of the emissions associated
with the proposed development will be less than 0.040% of the total EU-wide ETS market
which is imperceptible.
…
Data centres are typically 84% more efficient than on-premises servers and the GHG savings
associated with this are not included in the GHG emissions total. In addition, in terms of
total forecasted capacity, it is predicted that 1,700MW of data centres capacity will be
operational by 2025 in Ireland. However, the carbon intensity of electricity is predicted to
decrease from 331 gCO2/kWh in 2019 to 100 gCO2/kWh in 2030 as a result of the increase
in renewables to 70% of the electricity market by 2030. Overall, it is predicted that data
centres will peak at 2.2% of total GHG emissions in 2024 and will fall or level off after this
date.
The indirect CO2 emissions from electricity to operate the facility will not be significant in
relation to Ireland’s national annual CO2 emissions. A Report titled ‘Energy Related CO2
Emissions In Ireland 2005 – 2018 (2019 Report)’ published by the Sustainable Energy
Authority of Ireland (SEAI, 2020) states the average CO2 emission factor for electricity
generated in Ireland was 375 gCO2/kWh in 2018. This average CO2 emission factor is based
on the national power generating portfolio. On the basis that the Proposed Development
will consume 200 MW of power this equates to 1752 GWh annually based on the assumption
of the national fuel mix. This translates to approximately 657,000 tonnes of CO2eq per
year. This will have an indirect, long-term, negative and slight impact on climate.”
9. The clarification response was readvertised as required by the planning authority on the
basis that it contained significant additional data.
10. The council’s planner prepared three reports as part of the consideration of the application
– dated 8 September 2021, 18 April 2022, and 4 August 2022. Same, inter alia, considered the
issue of climate impacts, including the submissions/objections raised; and noted, as to energy supply
for the development, that a balance would be achieved as Ireland moves towards the achievement
of its renewable energy targets. The council’s planner’s report also provides the conclusions on the
planning assessment, including in relation to, inter alia:
“• The design of the data centre development to facilitate the use of renewable
hydrogen energy in the future and, in order to minimise air quality impacts, incorporate gas
engines for selective catalytic deduction.
• The proposed development including an energy centre which runs on natural gas
and is capable of generating 120MW. The proposed energy centre is also capable of running
on hydrogen when supplies become available, thereby providing a path to the use of
decarbonised energy sources for the entire development.
• By reference to the previous Climate Action Plan 2021 and various other policies,
the data centre development would be ‘in accordance with the proper planning and
sustainable development of the area’.”
11. On 8 August 2022, the planning authority made a decision to grant planning permission.
12. Seven third-party appeals were lodged with the commission in respect of the PDC – by An
Taisce, Friends of the Irish Environment, Futureproof Clare, Clare Green Party, Christine Sharp,
Martin Knox, and Colin Doyle.
13. The commission’s reference for the data centre application appeal was ABP-314474-22.
14. Relatedly, on 23 June 2022, the notice party submitted a strategic infrastructure
development (SID) application to the commission under s. 182A of the Planning and Development
Act 2000 (the 2000 Act) for the development of a 110 kV gas insulated switchgear substation with
two 110 kV underground transmission cables connecting to existing 110 kV overhead lines to the
North, and two 110 kV underground cables connecting to existing Ennis 110 kV substation to the
West, and associated works. The commission’s reference for the substation application was ABP-
313895-22.
15. As the commission points out, the notice party submitted substantial documentation in
response to the appeals, inter alia addressing the greenhouse gas (GHG) emissions issues. I would
broadly accept the commission’s summary of these:
“38. Following various appeals by third parties, the Developer lodged a comprehensive
suite of appeal documents to the Commission in response – which included:
• Appeal Response Report from John Spain Associates, dated 26 September 2022,
which addressed the various grounds of appeal, including by reference to the evidence
informing the application and the further evidence adduced for the purposes of responding
to the appeal. In this respect, it provided a response to the submissions made alleging
errors or omissions in the application documentation in respect of the consideration of
climate – stating, inter alia:
‘…
Contrary to the submission of Dr Colin Doyle (at para 2) the applicant has not sought to
argue, solely on the basis that the development operates within the ETS, that the proposed
development complies with both European and national policy. The applicant has fully
addressed the requirements of EU, national, regional and local policy in the EIAR and other
technical reports submitted in relation to the application.
…
As is clear from Chapter 8 of the EIAR, the Applicant's references to GHG emissions falling
within the EU ETS regime are simply directed at highlighting that in Ireland, as in all EU
Member States, the EU ETS is an EU wide regime; and that EU ETS emissions are not
calculable for the purpose of Member States' EU targets and reduction obligations in respect
of non-trading sector emissions (e.g. transport, agriculture, buildings (heating) etc (under
the EU's 'Effort-Sharing Regulation'). That is an entirely accurate and factual statement in
relation to the basic structure/intent of the EU ETS relative to non-trading sector emissions,
targets and reduction obligations of Member States.
The same part of the Appeal has suggested that, by expressing the quantum of estimated
GHG emissions (related to energy generated for the proposed facility) by reference to total
EU-wide EU ETS-related emissions, that the Applicant is somehow avoiding or concealing
the quantum of GHG emissions relative to national GHG emissions. That is, again, not an
accurate reading or interpretation of the information that the Applicant has provided in the
EIAR; because it is very clear that the Applicant has referenced estimated GHG emissions
from the facility as well as referencing national-level GHG emissions.
The EU ETS has been the flagship GHG reduction mechanism within the EU – both collectively
across the EU and within individual Member States - since the commencement of its pilot
phase in 2005. Since then, through phases 1, 2 and 3 and, most recently, the current
phases 4 (running to 2030) of the EU ETS system, it covers c. 10,000 installations across
the EU. As referred to in the environmental response note prepared by AWN (appendix 3 to
this response document) significant GHG reductions have been achieved under the EU ETS.
These have been achieved by virtue of its design, its ‘pricing in’ of carbon and also by virtue
of its annual ‘linear reduction factor’.
As indicated above, when it comes specifically to non-trading sector specific emission
reduction targets for EU Member States, the EU ETS is not calculable – for the simple reason
that the EU ETS is separate to the non-trading sector. That is simply the discrete point that
that the Applicant has made; and it is erroneous of the Appellant to state that the Applicant,
in making that point/distinction, is somehow avoiding indicating EU ETS emissions in national
terms.
In any event, outside of EU-wide targets i.e. in relation to domestically-set, economy- wide
GHG reduction targets set by Member States for themselves, EU ETS- regulated installations,
because they are GHG sources, will, in relation to the reductions they achieve, contribute to
the overall performance of individual Member States in achieving those domestically-
set/national economy-wide (combined EU ETS and Non-EU ETS) targets. In that regard,
contrary to the Appellant’s assertions regarding the Applicant’s references to the EU ETS,
the position is that the EU ETS is an important mitigation mechanism for all Member States
GHG reduction efforts.…
…
Indeed in relation to the most important target – the 2050 target - just as the EU's ultimate
target ( and most legally- binding target - under the EU ‘Climate Law’) is one of achieving
climate neutrality (‘Net Zero’) by 2050, that is precisely the same target as Ireland has
undertaken under the Climate Action and Low Carbon Development Act 2015 (as amended
in 2021) and all reductions achieved by Irish EU ETS-participating installations will contribute
towards that.’
• Response addressing the principles for sustainable data centre development (§4.54
et seq).
• AWN Appeal Response, dated September 2022 (Appendix 3 of Appeal document) –
outlining:
‘…the energy generated and associated GHG emissions to serve the proposed development
will fall within the scope of the EU Emissions Trading System (ETS) either as a result of
electricity from the national grid (with diesel generators as an emergency measure) (for
Phase 1) or as a result of onsite generation of electrical power using gas generators (Phase
2 & 3) with all phases requiring a Greenhouse Gas Permit in order to operate…’ (§1.4)
‘…Within the context of global or EU-wide emissions, the GHG emissions associated with the
project are small. The approach that has been adopted at EU level is the EU Climate and
Energy Package…’ (§1.8)
‘The ETS is a “cap and trade” system where an EU-wide limit, or cap, is set for participating
installations. Thus, the geographical location of a given development within the EU is not
relevant as there is only one EU-wide target which is applicable to the ETS and thus the
cumulative direct and indirect climate assessment of relevance in this context is the GHG
emissions associated with the EU under the ETS. When viewed in this context, on an EU-
wide basis, where the ETS market in 2021 was approximately 1,307 million tonnes CO2eq,
the impact of the emissions from the proposed development, either from electricity
generation from the national grid or from onsite generation, will be less than 0.05% of the
total EU-wide ETS market. Thus, where there is a medium sensitivity environment and the
magnitude of impact of the project is small, this equates to a slight impact.’ (§1.10)
‘In terms of the specific references to CO2 emissions within the third party appeals, the
emissions associated the development (either directly or indirectly) will be within the ETS
mechanisms as outlined in Section 8.7.2.2 of the EIAR’. (§1.15)
‘It should be noted that the projected CO2 emissions (as quoted in Section 8.7.2.2 of the
EIAR) associated with the proposed development are calculated based on the 2018 grid mix.
The national fuel mix will decrease in carbon intensity as the grid reaches the 80% in
renewables predicted for 2030 (see Figure 3 below). Therefore, the servicing of Phase 1
from the national grid will allow for a reduction in the emissions associated with the proposed
development over time. In addition, the introduction of biomethane into the natural gas
network will also lead to reductions in emissions from Phases 2 & 3 over time.’ (§1.16)
It should also be observed that the appeal submission addressed PAS 2050 (inter alia, §1.17)
– noting that same was raised by the Applicants in their appeal.
This report proceeds to then set out an assessment of the significance of the emissions
(§1.27 et seq) – by reference to the Institute of Environmental Management and Assessment
(IEMA) guidance note on ‘Assessing Greenhouse Gas Emissions and Evaluating their
Significance’ (IEMA, 2022) – concluding:
‘Thus, through a series of measures including project replacement, a reduction in residual
emissions through best practice and the implementation of a series.’
Thus, we see an identified methodology which informed the consideration of GHG emissions
– a methodology which the Commission was entitled to consider as appropriate. In this
respect, the Applicants are not correct that there was a failure to consider the extent of
emissions (Submissions, §77), same were considered, and found to be acceptable in the
Developer’s documentation, with which the Commission agreed.
It further addressed the contentions raised in the appeal regarding alleged non-compliance
with s.15 of the 2015 Act and the CAP – addressing the carbon budgets and sectorial
emission ceilings (§3.10 et seq), and setting out for stated reasons that:
‘…as outlined below, the facility will operate in compliance with the policies and objectives
of the 2021 Climate Act. The phasing of the development and the period taken to reach full
capacity within each planned phase will result in the “ramping up” of demand associated
with the project over a number of years during the lifetime of the 10 year permission.’
(§3.15)
In this context, the report (pg.19) expressly quotes s.15 of the 2015 Act in its amended
form – consistent with ‘so far as practicable’ – and explains that the ‘GHG emissions
associated with the proposed project are in compliance with the above mentioned plans,
strategies and objectives’ (§3.17 et seq).
Noting the foregoing, the Applicants complaint that there was a failure to address the
development by reference to sectoral emissions ceiling and carbon budgets (Submissions,
§93 et seq) is not correct. Noting the relevant policy context, which conforms with s.15, the
assessment of GHG emissions, including by reference to the sectoral emissions ceiling and
carbon budgets was analysed in the Developer’s documentation – which aligns with the
requirements of the Development Plan in terms of the requirement to provide an analysis
and which the Commission was lawfully entitled to accept (contrary to the Applicants’
complaints at Submissions, §106).
The report also addresses the national climate objective – stating (§3.22):
‘Thus, the proposed project aligns with the national climate objective as the project will be
within the EU ETS which is the cornerstone of the EU’s objective to reduce GHG emissions
by at least 55% by 2030 (compared to 1990) and to achieve climate neutrality by 2050.’
The report addresses each of the matters arising under s.15 of the 2015 Act, insofar as same
arose, and provides informed responses. In this respect, for example, in respect of
mitigating GHG emissions, the report outlines (§3.23 et seq):
‘The project will replace activities which have a higher GHG profile. Data storage facilities
represent a significantly more efficient means of data storage when compared to a
distributed model of enterprise data storage by individuals and companies (or “enterprise
sites”). …
A range of measures will be employed which is in line with “best practice” as outlined in
IEMA (IEMA, 2022) including the installation of solar panels, the installation of a vertical
farm and the installation of flow and return pipes from the Energy Centre which will allow
an onward connection to a local user for heat or a future heat network.
Measures will be implemented in line with “best practice” as outlined in IEMA (IEMA, 2022).
As set out within the appended letter from the applicant, the applicant has had positive
engagement in relation to the securing of a CPPA to provide renewable power to offset that
used by the proposed development. The letter forms Appendix 5 to the JSA response
document. The letter notes that the timeline associated with the delivery of the proposed
development over the duration of the 10-year permission sought aligns with the intended
delivery of significant renewable capacity by renewable energy providers in the vicinity of
the proposed development…’
The AWN Appeal Response also addresses climate adaption (§3.25 et seq) and decarbonised
data centres by design (§4.0 et seq) – this included further consideration of the Data Centre
Enterprise Strategy.
The foregoing report is important in the context of this case as same is largely ignored by
the Applicants. However, when same is considered – noting that the Inspector and the
Commission ultimately agreed with the Developer’s position – it is clear that the evidence
was informed by a correct understanding of s.15 of the 2015 Act (i.e. the correct legislative
text).
• Appendix 5 of the appeal response comprises correspondence regarding a Corporate
Power Purchasing Agreement (‘CPPA’) – which details the Developer’s engagement with
renewable energy providers.
• Appendix 6 of the appeal response included a HDR Response which further addressed
how same accords with the Data Centre Enterprise Strategy by reference to the principles
set out in same – including in relation to the proposed use of gas. As to energy usage and
renewable policy, noting the phased nature of the development, it provides:
‘The data centre building design is based on best in class low energy technologies to ensure
that the buildings have the lowest energy usage possible in the first instance.
Where possible, direct renewable energy production is provided on the data centre campus,
primarily in the form of solar/PV arrays.
The energy centre will be provided with gas engines that will be enabled to run on initially
natural gas but also onto blends of natural gas, biomethane and hydrogen. The engines will
then have the ability to provide power to the data centres and also, if required, to disconnect
the data centre campus to be off grid and even to allow export to the electricity grid.
CPPAs and/or direct private wire connections will be avidly encouraged to link up with local
renewable energy sources, particularly local wind farms.’
The report also addressed submissions regarding the potential future use of hydrogen –
stating:
‘In this regard it is correct that currently there is no production of hydrogen on any significant
scale that is being used by Gas Networks Ireland (GNI) in their gas transmission system.
This is not a surprise, in GNI’s Vision 2050, they say that hydrogen production (green or
blue) is being considered and the intention for it to be in the mix of gases in the gas network
by 2030 onwards as per Figure 1 above (extracted from GNI’s Vision 2050). For the first 5
or more years from 2030, the quantum of hydrogen intended to be injected is small, a few
percent, but will increase but even by 2050 it is only likely to make up around 12% of the
total volume supplied.
It is true that fully replacing Natural Gas completely with hydrogen is currently not an option
due to the embrittlement of pipework by hydrogen itself, however there are already many
gas networks around the world where natural gas has been replaced in part (up to 20%)
with hydrogen with no issues at all. So a mix of only 12% hydrogen is clearly an achievable
target.
… the intention by GNI to introduce biomethane sources from existing waste streams (see
earlier reference to KPMG/GNI report 2021) from a range of food and agricultural waste
products…”
16. The council’s submission on the appeal is highlighted by the commission as follows:
“40. The Council also provided submissions on the various appeals, reiterating the
rationale for the first instance grant of permission, whilst also addressing the points raised
in the appeals. The Council’s submissions:
• Included a detailed consideration of the Data Centre Enterprise Strategy.
• Included submissions on the EIAR, including air and climate.
• Addressed the 2015 Act and climate impacts/justice – outlining that, for stated
reasons, it was considered that ‘the proposed development is in line with the overarching
principles underpinning’ the 2015 Act.
• Noted that the potential for the energy centre to run off alternative supplies, such
as hydrogen, provided a path to the use of decarbonised energy resources. The Council
further outlined that it was a matter for the Developer ‘to engage commercially with end
users / tenants of the proposed development in relation to Corporate Power Purchase
Agreements’.
• Outlined that Government Policy ‘advocates for a plan led approach in the delivery’
of data centres, which the Council considers it adopted in zoning the lands in the
Development Plan. The Council’s submission concluded by stating that it:
‘…considers that the proposed development represents a plan led approach to the
development of a data centre in Ennis, which has the potential to contribute to enterprise
and regional policy objectives and represent a strategically important element of Ireland’s
economic prospects…’”
17. The inspector carried out a site inspection on 3 September 2022.
18. The notice party submitted a response to the appeals (with appendices) on 26 September
2022.
19. Submissions were made in response, notably by Dr Doyle.
20. The Climate Action Plan 2023 (the first to be prepared under the Climate Action and Low
Carbon Development (Amendment) Act 2021, and following the introduction, in 2022, of economy-
wide carbon budgets and sectoral emissions ceilings (SECs)) was launched on 21 December 2022.
21. On 11 January 2023, the commission gave notification that it would not be possible to
determine the appeal within the statutory period of 18 weeks and indicated its intention to determine
the appeal by 4 April 2023.
22. On 3 April 2023, the commission gave notification that it would not be possible to determine
the appeal by 4 April 2023. It expressed the hope that it would receive the inspector’s report and
recommendation “in the near future”.
23. As part of the Climate Action Plan 2023, the National Hydrogen Strategy was published by
the Department of the Environment, Climate and Communications on 12 July 2023.
24. The inspector carried out a further site inspection 13 October 2023.
25. On 11 December 2023, the inspector submitted a report to the commission which contained
a recommendation that planning permission should be granted subject to 17 conditions. The
inspector also conducted an EIA and an appropriate assessment (AA).
26. She was also appointed by the commission to prepare a report on the substation application
and on the same date, she submitted a report to the commission on that application in which she
recommended that planning permission be granted subject to 14 conditions.
27. A commission direction dated 27 March 2024, in respect of the data centre application
indicated that the commission decided to grant permission generally in accordance with the
inspector’s recommendation. The commission direction indicated that the commission had
undertaken an AA in respect of a number of “screened in” European sites. The direction indicated
that the commission considered that the information before it was sufficient to undertake a complete
assessment of all aspects of the proposed development in relation to the conservation objectives of
the said European sites using the best available scientific knowledge in the field.
28. The commission’s direction also indicated that the commission undertook an EIA of the
proposed development.
29. A commission direction dated 27 March 2024, in respect of the substation application is
framed in similar terms to that relating to the data centre application.
30. On 5 April 2024, the commission granted planning permission for the data centre
development subject to 17 conditions. On the same date, it granted permission for the substation
development subject to 14 conditions. The commission’s orders in respect of both records that it
carried out an EIA and an AA of the proposed development.
Procedural history
31. On 30 May 2024, the applicants’ statement of grounds was filed in the High Court Central
Office.
32. On 24 June 2024, I granted leave to apply for judicial review seeking, inter alia, an order
quashing the commission’s decisions taken on 5 April 2024. On the same date I fixed a hearing
date of 25 February 2025 for the judicial review for two days.
33. On 7 October 2024, in advance of delivering a statement of opposition the commission’s
solicitors wrote to the other parties indicating that the commission had decided not to oppose the
applicants’ claim for certiorari quashing the commission’s decisions on the data centre application
and the substation application. Their letter stated:
“Having regard to the circumstances of this case and, in particular, the plea(s) advanced at
Core Ground 6 of the said Statement of Grounds – namely, that the Board erred in law in
failing to consider adequately the environmental effects of the proposed developments on
the environment, specifically in terms of impacts on bat fauna for the purposes of the
Environmental Impact Assessment carried out by the Board.”
34. The legal community will be forever grateful to the unsuccessfully appealing applicants in
Ballyboden Tidy Towns Group v. An Bord Pleanála & Ors. [2024] IESC 4 (Unreported, Supreme
Court, Donnelly J., 22 February 2024) (O’Donnell C.J., Woulfe, Hogan and Collins JJ. concurring),
because that case clarified the really important procedural point that a developer can defend a
permission even if the decision-taker does not. On foot of the procedure recognised in that decision,
on 25 November 2024, the notice party communicated to the court that it was seeking that the
hearing date of 25 February 2024 would be retained to facilitate a hearing in relation to core ground
6 only, as the notice party intended to resist certiorari being granted by reference to the ground on
which the commission’s concession was made. I directed that the matter proceed as a modular
hearing for one day on 25 February 2025, on the question of whether I should quash the decisions
in light of the commission’s concession.
35. On 5 December 2024, the notice party’s solicitors wrote to the commission’s solicitors
stating:
“We note that there are sixteen paragraphs contained in the Applicant's Statement of
Grounds with respect to Core Ground 6. Can you please confirm the exact point(s) pleaded,
under Core Ground 6, which forms the basis of your client's concession, so that the precise
contours of the upcoming hearing can be defined.”
36. On 9 December 2024, the commission’s solicitors wrote to the solicitors for the other parties,
clarifying that:
“The Board accepts the errors pleaded in the particulars set out at §91-§93 of the Statement
of Grounds insofar as same are premised on the Inspector’s statement (at pg.74 of the
Inspector’s Report) … On the basis that the information before the Board, including the
updated EIAR, the evidence demonstrated that the Proposed Development would result in
the loss of a bat roost. Thus, in failing to recognise the loss of the bat roost, it is conceded
that the Inspector and the Board erred in failing to identify, consider and assess the potential
impacts of the Proposed Development on bat fauna for the purposes of EIA.”
37. On 16 December 2024, I directed that the hearing scheduled for 25 February 2025 would
be in relation to the matters in §§91-93 only of the applicant’s statement of grounds, following
clarification from the commission in its letter of 9 December 2024 that its concession related only to
the matters pleaded thereunder.
38. On 23 December 2024, the notice party served a limited statement of opposition, together
with a verifying affidavit sworn by Deborah Delaney and an affidavit of Colm Clarke.
39. On 23 January 2025, the applicants’ solicitors sent a letter to the notice party’s solicitors
asserting that the notice party’s statement of opposition addressed the entirety of the grounds
pleaded in relation to core ground 6. The letter stated that:
“This was not what was required, and would appear to be an attempt to impermissibly
expand on the matters directed to be heard at the hearing. The Affidavit of Ms Delaney
traverses matters far beyond those in ground 91- 93 of the Statement of Opposition.
Furthermore, your client has delivered an affidavit of Colm Clarke ecologist and it is clear
that this Affidavit also addresses issues which go far beyond what is in issue in relation to
grounds 91-93 of the Statement of Opposition.”
40. The letter indicated that the applicants would apply to have parts of the statement of
opposition struck out and the notice party’s affidavits “resworn to address the matters relevant to
those to be addressed at the forthcoming hearing”.
41. On 24 January 2025, the notice party’s solicitors sent a letter to the applicant’s solicitors
stating:
“…[o]ur client fully accepts that the issue which the Court has to decide on 25 February 2025
relates specifically to paragraphs 91-93 of the Statement of Grounds, concerning the effect
of a factual error which appears on page 74 of the Inspector’s report on the Data Centra
application, in the section of her report dealing with ecology issues and bats in particular.
The extract states, inter alia, that ‘[t]he various EIAR desk-top and site surveys confirm that
the site and environs are frequented by bats, and although some of the older farm buildings
may also have roosting potential, the applicant confirmed that no roosts were recorded
during the surveys …
It would be entirely unrealistic and artificial, and a waste of court time, to ask the Court to
determine whether the Inspector’s factual error should result in the Board’s decision being
quashed without addressing the other matters [in Core Ground 6], including the allegation
that the Board had no objective information before it in terms of the impacts on bat fauna
for the purposes of the EIA and/or the issue of whether a derogation licence was required in
advance of the Board’s decision. Indeed, were our client to simply deal with the issue of the
Inspector’s factual error in isolation from the treatment of the issue of bat fauna generally,
it could expect to be criticised by both your client and the Court, given the overlap between
the issues and the critical requirement of the Court to have an understanding of the totality
of the matters raised in Core Ground 6 in considering proportionality. Furthermore, given
that our client is asking the Court to exercise its discretion against quashing, it is imperative
that the Court has a full picture of the issues in order to properly consider the matter. In so
doing, our client is not asking the Court to do anything other than determine the issue with
respect to the Inspector’s factual error.”
42. On 27 January 2025, on the application of the applicants, the matter was listed before the
court and I clarified – with the agreement of the applicants and the notice party – that where the
commission concedes a ground and the court conducts a modular hearing on the notice party’s
application determining whether the decision should be quashed in light of the commission’s
concession, for the purposes of determining that issue, the court approaches the application on the
basis that all other issues would be resolved in the notice party’s favour. However, in the event that
the court exercises its discretion against quashing and the matter proceeds to a further module
dealing with the remaining grounds which the commission has not conceded, those other issues
revert to being fully in contest for the purposes of the subsequent module.
43. On 3 February 2025, the applicants’ solicitors confirmed that the applicants would not be
filing replying affidavits in response to the notice party’s limited statement of opposition and
affidavits.
44. On 5 February 2025, the notice party delivered its legal submissions.
45. On 19 February 2025, the applicants delivered their legal submissions.
46. Module I was heard on 25 February 2025.
47. In the No. 1 judgment delivered on 21 March 2025, I dismissed the argument raised in that
Module.
48. Module II would have happened much sooner but for the fact that the issue got caught up
in the appeal in Coolglass. The proceedings were adjourned from time to time thereafter to await
the decision in the Coolglass proceedings which was delivered on 4 February 2026 (Coolglass v. An
Coimisiún Pleanála [2026] IESC 5 (Unreported, Supreme Court, 4 February 2026).
49. Module II was heard shortly thereafter on 2 March 2026. At the end of that hearing the
notice party produced a document, which I had suggested as a possible way to clarify the point
made in written submissions, which was their attempt at classifying the point in time at which various
issues had been raised by the applicants. I indicated that I might review and reformat the document
and put the matter in for mention at 09:30 the following morning for arrangements to be made for
the applicants input by way of response.
50. At the conclusion of the foregoing final mention, I decided that it was not necessary to pursue
further written submissions subject to reserving the right to revisit that if I thought it necessary in
the course of writing, so judgment was then reserved at the end of that listing. I record my thanks
to all of the lawyers for their endeavours to assist the court.
51. On 6 March 2026, a draft of the present judgment was sent to the parties to give an
opportunity to identify any errors. The rules of engagement in such a situation are that the draft is
without prejudice to the right of the court ultimately to issue a judgment in whatever form or with
whatever content it considers appropriate.
52. Any comments must be emailed to the court and uploaded to ShareFile in writing by the
notified deadline, and should not be to reargue the substance (submissions to that effect will be
disregarded) but are confined to matters such as:
(i) informing the court as to whether a formal judgment is required, and if so on what
issues;
(ii) informing the court as to whether a judgment might be oral or written or partly in
both modes;
(iii) any typographical, factual or legal errors in the decision;
(iv) any redaction of personal information that the party wishes to request;
(v) in the event that the court proposes to place pivotal reliance on any authority or
material not previously adverted to, as opposed to where such material merely
reinforces a point that the court was making in any event, any comment as to why
such material should not lead to the proposed conclusion; identifying points that the
court proposes to address but that the parties consider it unnecessary to address;
(vi) requesting the court to decide a point that, while unnecessary to decide, is one the
party considers could beneficially be decided;
(vii) identifying significant procedural, factual or legal points that the party considers that
the court was required to address but has not addressed or not provided reasons
for; and
(viii) any other suggestions as to the wording (as opposed to substance) of the decision
if the proposed wording causes any significant issue for a party for any identified
reason.
53. It is then entirely a matter for the court as to whether to list the matter for mention, or
whether to simply give judgment with or without amendment to respond to any such comments or
for any other reason that appears appropriate to the court. Any judgment may be given without
further notice following the expiry of the specified period, whether comments are made or not. That
period will not be extended save in exceptional circumstances. All parties involved are requested to
positively confirm to the court the position including if they have no observations on the draft
legitimately falling within the foregoing parameters. Overall the draft judgment procedure is a
concession which parties can engage with but must do so with immediate dispatch, discipline and
focus – it is not the opening of a new phase of the litigation that gives rise to “an entitlement to
elaborate procedures at every point” (to use a phrase of O’Donnell C.J. (Dunne, Charleton and Baker
JJ. concurring) in O’Sullivan v. Health Service Executive [2023] IESC 11 (Unreported, Supreme
Court, 10 May 2023) at para. 39); and still less should the procedure invite the perhaps “serious
error, to which lawyers are prone, to approach any such case on the tacit assumption that only
procedures which approximate to a criminal trial are fair, and anything which departs from that is
somehow dubious” (O’Donnell J. in O'Sullivan v. Sea Fisheries Protection Authority [2017] IESC 75,
[2017] 3 I.R. 751, [2018] 1 I.L.R.M. 245, 780).
54. Draft judgments are not public domain materials and, while they can be shared between the
lawyers concerned and their clients, subject to the following, it is inappropriate for any person to
refer to them for any purpose other than to assist the court in relation to the finalisation of the
formal judgment. Therefore anyone with information as to the text, content or proposed outcome
of any draft is required not to publish or transmit such information to others save solely by way of
private transmission for the legitimate purposes of assisting in the finalisation of the judgment and
subject to a similar restriction on any recipient. Trial participants should take reasonable steps to
keep drafts confidential. On this topic, see Attorney General v. Crosland (No. 2) [2021] UKSC 58,
[2022] 1 W.L.R. 367, [24/01/2022] T.L.R. 1 which discusses why restriction on publication of draft
judgments is in the interests of the administration of justice; see also Baigent v. Random House
Group Ltd [2006] EWHC 1131 (Ch), [2006] 5 WLUK 45, (2006) 150 S.J.L.B. 603 (Smith J.); R.
(Counsel General for Wales) v. Secretary of State for Business, Energy and Industrial Strategy
[2022] EWCA Civ 181, [2022] 1 W.L.R. 1915, [2022] 4 All E.R. 599 (Sir Geoffrey Vos MR; Davies
and Dingemans LJJ. concurring); Public Institution for Social Security v. Banque Pictet & Cie SA and
others [2022] EWCA Civ 368, [2022] 3 WLUK 291, [2022] B.L.R. 349 (Carr LJ; Jackson and Simler
LJJ. concurring); Itkin v. Wood [2023] JRC 101 (Unreported, Royal Court of Jersey, 22 June 2023).
The contents of this paragraph constitute an immediately effective direction of the court to the
parties and anyone having notice of the draft judgment with effect from the date of circulation of
the draft.
55. While on some previous occasions periods of 7 or more days have been allowed for
comments this has led to unintended slippage so there is a case for a tighter timeline, as in the High
Court of England & Wales (the draft is provided “by 4 p.m. on the second working day before handing
down”, Practice Direction 40E, Reserved Judgments, para. 2.3). The deadline for such comments
from the parties was to be 16:00 on Tuesday 10 March 2026. The opposing parties pointed out a
typographical error (in fact one that had its origin in the applicants’ material). Contrary to the
request set out above, the applicants failed to respond to the court in any manner by the specified
deadline.
Relief sought
56. The reliefs sought are as follows:
“1) An Order of Certiorari quashing the decisions, and each of them, dated 5 April 2024
of the first named Respondent granting planning permission to the Notice Party for:
(a) the construction of a proposed data centre (PDC) located in Ennis, County Clare,
comprising six two-storey data centre buildings with three storey plant/office levels and
associated ancillary development that will have a combined gross floor area of 118,740
square metres, including a 120MW gas powered electricity generation facility and
dispatchable electricity generation facility powered by 66 diesel generators (ABP-314474-
22, ‘the Data Centre Decision’);
(b) the provision of a new 110 kilovolt (kV) Gas Insulated Switchgear (GIS) grid
substation (the Substation), two 110 kV underground transmission cables connecting to
existing 110kV overhead lines to the north of the proposed substation, and two 110kV
underground transmission cables connecting to the existing Ennis 110kV grid substation
(located to the east of the M18 and to the north of the Tulla Road (R352), along with
associated and ancillary works) (ABP-313895-22, ‘the Substation Decision’).
[In this Statement of Grounds any reference to a document contained in the planning files
before the Board or the Planning Authority relate to the application and appeal in respect of
the PDC, unless otherwise stated].
2) Such declaration(s) of the legal rights and/or legal position of the applicants and (if
and insofar as legally permissible and appropriate) persons similarly situated and/or of the
legal duties and/or legal position of the respondents as the court considers appropriate.
3) A declaration that the State's adoption of the ‘Government Statement on the Role of
Data Centres in Ireland's Enterprise Strategy July 2022’ is invalid as it was not subject to
assessment for the purposes of Articles 1 and 3 of Directive 2001/42/EC of the European
Parliament and of the Council of 27 June 2001 on the assessment of the effects of certain
plans and programmes on the environment.
4) If necessary, a stay on works being carried out pursuant to the Data Centre Decision
and the Substation Decision pending the resolution of these proceedings.
5) A Declaration that the within proceedings are covered by the protective costs
provisions of Section 50B of the Planning and Development Act 2000 (as amended), and/or
otherwise.
6) Further or other orders.
7) Costs.”
Grounds of challenge
57. The core grounds of challenge are as follows:
“DOMESTIC LAW GROUNDS
1. The Data Centre Decision is invalid in that the Board failed to apply and/or consider
its mandatory obligation under section 15 of the Climate Action and Low Carbon
Development Act 2015 (as amended by Section 17 of the Climate Action and Low Carbon
Development (Amendment) Act 2021), namely in so far as practicable, to perform its
functions in a manner consistent with the matters stated in section 15, including (a) the
most recent approved climate action plan, (the Climate Action Plan 2023), (d) the
furtherance of the national climate objective, and (e) the objective of mitigating greenhouse
gas emissions (GHG emissions) and adapting to the effects of climate change in the State;
and/or failed to provide sufficient reasons to explain how it sought to apply and/or consider
its mandatory obligation under the 2015 Act, further particulars of which are contained
below.
2. The Data Centre Decision is invalid in that the Board acted irrationally, erred in law
and/or failed to provide reasons and/or adequate reasons, in finding that the PDC would
have potentially positive environmental impacts, based on a future switch to the use of
sustainable/renewable gas supplies, which do not exist in sufficient volumes for any practical
application in respect of the PDC and which are not expected to exist in sufficient volumes
for any practical application in respect of the PDC at any point during the operational phase
of the PDC, further particulars of which are contained below.
3. The Data Centre Decision is invalid in that the Board acted irrationally by failing to
require any mitigation of the GHG emissions from the PDC, further particulars of which are
contained below.
EUROPEAN LAW GROUNDS
4. The Data Centre Decision is invalid in that the Board treated the Government
Statement on the Role of Data Centres in Ireland's Enterprise Strategy July 2022 as the
framework for development consent in respect of data centres: while simultaneously
deciding that the Government Statement on the Role of Data Centres in Ireland's Enterprise
Strategy July 2022 is not a plan or programme to which Article 3(2) of the Strategic
Environmental Assessment (SEA) Directive applies, further particulars of which are
contained below.
5. The Data Centre Decision is invalid as it relied on the Government Statement on the
Role of Data Centres in Ireland's Enterprise Strategy July 2022 which is invalid as it was not
assessed for the purposes of Articles 1 and 3 of Directive 2001/42/EC of the European
Parliament and of the Council of 27 June 2001 on the assessment of the effects of certain
plans and programmes on the environment, further particulars of which are contained below.
6. The Data Centre Decision and the Substation Decision are invalid as the Board failed
to consider adequately or at all the environmental effects of the proposed development on
the environment in terms of impacts on bat fauna for the purposes of the EIA assessment
carried out by the Board and/or had no objective information before it to support a conclusion
of no significant effects on the environment for the purposes of the Board's EIA assessment
and/or impermissibly granted development consent prior to a decision granting a derogation
licence authorising bat roost removals and/or disturbance to bat species, further particulars
of which are contained below.
7. The Data Centre Decision is invalid as the Board granted planning permission in
breach of Article 4(1) of Directive 2000/60/EC of the European Parliament and of the Council
of 23 October 2000 establishing a framework for Community action in the field of water
policy (the ‘Water Framework Directive’) and/or Regulations 4 and 5 of the European
Communities Environmental Objectives (Surface Waters) Regulations 2009 because the
Board did not ensure that the grant of planning permission would not cause a deterioration
of the status of a body of surface water or that it would not jeopardise the attainment of
good surface water status or of good ecological potential and good surface water chemical
status and/or the Board could not have arrived at that conclusion in the absence of the
developer making available to the public during the procedure for approving the project the
data which were necessary in order to assess the effects of the development on receiving
waterbodies, further particulars of which are contained below.
VALIDITY GROUND
8. The State's adoption of the Government Statement on the Role of Data Centres in
Ireland's Enterprise Strategy July 2022 is invalid as it was not subject to assessment for the
purposes of Articles 1 and 3 of Directive 2001/42/EC of the European Parliament and of the
Council of 27 June 2001 on the assessment of the effects of certain plans and programmes
on the environment, further particulars of which are contained below.”
The impugned decision
58. The impugned decision provides as follows:
“An Bord Pleanála
Board Order ABP-314474-22
Planning and Development Acts 2000 to 2022
Planning Authority: Clare County Council
Planning Register Reference Number: 21/757
Appeal by Colin Doyle of 12 Cottage Gardens, Station Road, Ennis, County Clare and by
others against the decision made on the 8th day of August, 2022 by Clare County Council to
grant subject to conditions a permission to Art Data Centres Limited care of John Spain
Associates of 39 Fitzwilliam Place, Dublin in accordance with plans and particulars lodged
with the said Council.
Proposed Development: Permission of 10 years in duration sought for development
consisting of: the demolition of an existing single storey with pitched roof farm dwellinghouse
together with eight number farm outbuildings on the overall site. The construction of six
number two-storey data centre buildings with three-storey plant/office levels and associated
ancillary development that will have a combined gross floor area of 118,740 square metres.
These data halls are maximum 19 metres high and will consist of the data halls and air
handling units and offices and ancillary plant and support. Each of the six data centre
buildings will include data halls, associated electrical and mechanical plant rooms, loading
bays, maintenance and storage spaces, office administration areas, pump rooms, water
storage tanks, and plant, as well as backup (standby) generators (11 number per building)
for emergency use only situated along one elevation of each building. The standby diesel
generators will have associated eight-metre-high flues. Each generator will also include local
diesel storage tanks with a single refuelling area to serve the proposed emergency
generators. A gas-powered energy centre and Above Ground Installation (AGI) 4,674 square
metres in size. The energy centre will primarily comprise 18 number lean-burn natural gas
engines, two number pump rooms, and fuel storage compound. Each generator will have
its own flue of 25 metres height. The energy centre and buildings within the compound will
be 12 metres high, single storey with mezzanine level. The buildings will house ancillary
office, welfare facilities and associated parking. A two-storey Vertical Farm Building. The
vertical farm will be circa 2,430 square metres and 12 metres high. It will comprise circa
service area of 1,444 square metres, handling area of 844 square metres and ancillary areas.
Solar panels located on each of the data centres and rainwater harvesting included in the
development. Undergrounding of two existing overhead 110kV electricity transmission lines.
Ancillary site development works that will include attenuation ponds and the installation of
pipes and connections to the public water supply, foul and storm water drainage network
and installation of utility ducts and cables. Other ancillary site development works will
include hard and soft landscaping throughout the site, lighting, fencing, signage, central
services road and internal access roads, security gate, 299 number car parking spaces and
126 number bicycle parking spaces. The development will be enclosed with landscaping to
all frontages, including the retention of an ecological buffer area to the west. The
development will be accessed from the Tulla Road (R352) with the provision of a new
vehicular access road, together with an emergency access/egress road to the south-west of
the site. A shared surface cycle/footpath is to be provided along both sides of the Tulla
Road across the campus site's full road frontage. All associated and ancillary works. The
application site has a total of circa 60 hectares with a nett area for development of circa 45
hectares, and is bound to the south by R352 (Tulla Road), to the east and the north by
agriculture land, to the west by the M18, all in the townlands of Tooreen, Cahernalough,
Knockanean, Ballymacahill, Muckinish and Rosslevan, Tulla Road, Ennis, County Clare, as
revised by the further public notices received by the planning authority on the 9th day of
March, 2022 and on the 14th day of June, 2022.
Decision
GRANT permission for the above proposed development in accordance with the said plans
and particulars based on the reasons and considerations under and subject to the conditions
set out below.
Reasons and Considerations
The Board in making its decision had regard to the following:
(a) the National Planning Framework - Ireland 2040,
(b) the Climate Action Plan 2023,
(c) the Regional Spatial and Economic Strategy for the Southern Region 2020,
(d) the policies of the planning authority as set out in the Clare County Development
Plan 2023-2029,
(e) the Government Statement on the Role of Data Centres in Ireland's Enterprise
Strategy July 2022,
(f) the distance to dwellings or other sensitive receptors,
(g) the submissions made in connection with the planning application and the appeal,
(h) the likely consequences for the environment and the proper planning and sustainable
development of the area in which it is proposed to carry out the proposed development and
the likely significant effects of the proposed development on European Sites, and
(i) the report and recommendation of the Inspector.
Appropriate Assessment: Stage 1:
The Board agreed with the screening assessment and conclusion carried out in the
Inspector's Report that the Old Domestic Building (Keevagh) Special Area of Conservation
(Site Code: 002010), the Dromore Woods and Laughs Special Area of Conservation (Site
Code: 000032), the Old Domestic Buildings, Rylane Special Area of Conservation (Site Code:
002314), the Lower River Shannon Special Area of Conservation (Site Code: 002165), the
Ballyallia Lough Special Protection Area (Site Code: 004041), the River Shannon and River
Fergus Estuaries Special Protection Area (Site Code: 004077), the Slieve Aughty Mountains
Special Protection Area (Site Code: 004168) and the Corofin Wetlands Special Protection
Area (Site Code: 004220) are the European Sites in respect of which the proposed
development has the potential to have a significant effect in view of the Conservation
Objectives for the sites and that Stage 2 Appropriate Assessment is, therefore, required.
Appropriate Assessment: Stage 2:
The Board considered the consolidated Natura Impact Statement, and all the other relevant
submissions on file, and carried out an appropriate assessment of the implications of the
proposed development on the Old Domestic Building (Keevagh) Special Area of Conservation
(Site Code: 002010), the Dromore Woods and Loughs Special Area of Conservation (Site
Code: 000032), the Old Domestic Buildings, Rylane Special Area of Conservation (Site Code:
002314), the Lower River Shannon Special Area of Conservation (Site Code: 002165), the
Ballyallia Lough Special Protection Area (Site Code: 004041), the River Shannon and River
Fergus Estuaries Special Protection Area (Site Code: 004077), the Slieve Aughty Mountains
Special Protection Area (Site Code: 004168) and the Corofin Wetlands Special Protection
Area (Site Code: 004220) in view of the sites' Conservation Objectives. The Board
considered that the information before it was sufficient to undertake a complete assessment
of all aspects of the proposed development in relation to the sites' Conservation Objectives
using the best scientific knowledge in the field. In completing the assessment, the Board
considered, in particular, the following:
(i) the site-specific Conservation Objectives for the European Sites,
(ii) the current conservation status, threats and pressures on the qualifying
interest/special conservation interest features,
(iii) the likely direct and indirect impacts arising from the proposed development, both
individually or in combination with other plans or projects,
(iv) the view of the Department of Arts, Heritage and the Gaeltacht, and
(v) the mitigation measures which are included as part of the current proposal.
In completing the appropriate assessment, the Board accepted and adopted the appropriate
assessment carried out in the Inspector's Report in respect of the potential effects of the
proposed development on the aforementioned European Sites.
In overall conclusion, the Board was satisfied that the proposed development would not
adversely affect the integrity of the European Sites in view of the sites' Conservation
Objectives and there is no reasonable scientific doubt as to the absence of such effects.
Environmental Impact Assessment:
The Board completed an environmental impact assessment of the proposed development
taking account of:
(a) the nature, scale, location and extent of the proposed development,
(b) the Environmental Impact Assessment Report (EIAR), the consolidated EIAR report,
and associated documentation submitted in support of the application,
(c) the submissions received from the prescribed bodies, planning authority and third
parties, and
(d) the Inspector's report.
The Board considered that the Environmental Impact Assessment Report (EIAR) and
consolidated EIAR report, supported by the documentation submitted by the applicant,
adequately considers alternatives to the proposed development and identifies and describes
adequately the direct, indirect, secondary and cumulative effects of the proposed
development on the environment. The Board agreed with the examination, set out in the
Inspector's report, of the information contained in the EIAR report and consolidated EIAR
report and associated documentation submitted by the applicant and submissions made in
the course of the application.
The Board considered that the main significant direct and indirect effects of the proposed
development on the environment are, and would be mitigated, as follows:
• The risk of pollution of ground and surface waters, or changes to ground water flow
paths during the construction phase through a lack of control of surface water during
excavation and construction, the mobilisation of sediments and other materials during
excavation and construction. The construction of the proposed development could also
potentially impact negatively on ground and surface waters by way of contamination through
accidents and spillages, and disrupting flow paths. These impacts would be mitigated by the
implementation of the Drainage Management Plan, agreement of measures within a
Construction and Environment Management Plan, and the implementation of mitigation
measures related to: design and avoidance; accidental spills and contamination; sediment
and erosion control; and drainage management.
• Biodiversity impacts arising from habitat loss and fragmentation, changes to the
vegetation on the site, loss of foraging habitat and disturbance to otters, badgers, birds and
bats, connections to foraging, aquatic and water dependent habitats and general disturbance
during the construction and operational phases. These impacts would be mitigated by the
agreement of measures within a Construction and Environment Management Plan, the
measures contained in the Landscape and Biodiversity Management Plan, and the
implementation of mitigation measures which include: Pre-construction Bird, Bat & Mammal
Surveys; Water Quality protection measures (as above); an Invasive Species Management
Plan; and the appointment of a Project Ecologist.
• The proposed development gives rise to an increase in vehicle movements and
resulting traffic impacts during the construction phase and significant impacts on the road
network can be avoided by the proposed works along the road network. These impacts
would be mitigated by the agreement of measures within a Construction and Environment
Management Plan and the implementation of mitigation measures related to: pre-
construction road condition surveys; deliveries; and implementation of a Construction Traffic
Management Plan and Construction and Demolition Waste Management Plan.
• Air pollution and noise during the construction and operational phase which would
impact negatively on sensitive ecological receptors and populations in the vicinity of the site.
These impacts are substantially avoided by the limited number of sensitive receptors in close
proximity to the proposed development. Any remaining impacts would be mitigated by the
agreement of measures within a Construction and Environment Management Plan and the
implementation of mitigation measures related to: air quality, dust and noise.
• The impacts on residential amenity during the construction and operational phases
would be avoided by the implementation of the measures set out in the Environmental
Impact Assessment Report (EIAR) and the consolidated EIAR report which include specific
provisions relating to the control and management of dust, noise, water quality and traffic
movement.
• The impacts on cultural heritage during the construction and operational phases
would be avoided by the implementation of the measures set out in the Environmental
Impact Assessment Report (EIAR) and the consolidated EIAR report, and by compliance with
the recommended conditions in relation to archaeological assessment of the site.
• The proposed development would have potentially positive environmental impacts
during the operational phase arising from the undergrounding of the existing overhead
transmission cables, and from the future switch to the use of sustainable/renewable gas
supplies in the energy centre for energy generation, with a corresponding reduction in carbon
emissions.
The Board completed an environmental impact assessment in relation to the proposed
development and concluded that, subject to the implementation of the mitigation measures
proposed, and subject to compliance with the conditions set out below, the effects of the
proposed development on the environment, by itself and in combination with other plans
and projects in the vicinity, would be acceptable. In doing so, the Board adopted the report
and conclusions of the Inspector.
Conclusions on Proper Planning and Sustainable Development:
It is considered that, subject to compliance with the conditions set out below, the proposed
development would be in accordance with European, national, regional and local planning
and related policy, would not have an unacceptable impact on the landscape or ecology,
would not seriously injure the visual or residential amenities of the area or of property in the
vicinity, and would be acceptable in terms of traffic safety and convenience. The proposed
development would, therefore, be in accordance with the proper planning and sustainable
development of the area.
Conditions
1. The proposed development shall be carried out and completed in accordance with
the plans and particulars lodged with the application, as amended by the further plans and
particulars received by the planning authority on the 25th day of February, 2022, the 10th
day of June, 2022 and by An Bord Pleanala on the 26th day of September, 2022, except as
may otherwise be required in order to comply with the following conditions. Where such
conditions require details to be agreed with the planning authority, the developer shall agree
such details in writing with the planning authority prior to commencement of development
and the proposed development shall be carried out and completed in accordance with the
agreed particulars.
Reason: In the interest of clarity.
2. This permission shall be for a period of 10 years from the date of this Order.
Reason: In the interest of clarity and orderly development.
3. The mitigation measures identified in the Environmental Impact Assessment Report,
the Natura Impact Statement and other plans and particulars submitted with the planning
application and appeal shall be implemented in full by the developer, except as may
otherwise be required in order to comply with the conditions of this permission.
Reason: In the interest of clarity and the protection of the environment during the
construction and operational phases of the proposed development.
4. The developer shall comply with the following general requirements:
(a) The developer shall submit full details in relation to all external finishes of all
buildings to the planning authority for written agreement prior to commencement of
development.
(b) No additional artificial lighting shall be installed or operated on site unless authorised
by a prior grant of planning permission.
(c) Operational noise levels shall not exceed 55dB(A) Leq 1hr at the nearest existing
noise sensitive locations between 0800 and 2000 hours (Monday to Friday inclusive) and
shall not exceed 45dB(A) Leq 1hr at any other time.
(d) Each fencing panel shall be erected such that for a minimum of 300 millimetres of
its length its bottom edge is no less than 150 millimetres from ground level.
(e) Cables within the site shall be located underground.
(f) No additional signage or advertising shall be erected on the lands or buildings
without a prior grant of planning permission.
Reason: In the interest of clarity, of visual and residential amenity, to allow wildlife to
continue to have access to and through the site, and to minimise impacts on drainage
patterns and surface water quality.
5. The developer shall comply with the following nature conservation requirements:
(a) A suitably qualified and experienced Project Ecologist shall be appointed to oversee
the protection of biodiversity during the construction phase, and for a monitoring period of
five years following completion of the development.
(b) The Project Ecologist shall certify that the completed development is compliant with
the Environmental Impact Assessment Report and Natura Impact Statement mitigation
measures and the following conditions.
(c) No felling or vegetation removal shall take place during the period 1st March to 31st
August.
(d) A pre-construction bat survey shall be carried out by a suitably qualified ecologist
during the active bat season.
(e) Any destruction of bat roosting sites or relocation of bat species shall be carried out
by a suitably qualified ecologist under a Derogation Licence granted by the Minister for
Housing, Local Government and Heritage.
(f) A pre-construction otter survey shall be carried out by a suitably qualified ecologist.
(g) Any destruction or relocation of otter halts shall be carried out by a suitably qualified
ecologist under a Derogation Licence granted by the Minister for Housing, Local Government
and Heritage.
(h) Mammal friendly fencing shall be installed during the construction and post
construction phases.
Reason: In the interest of biodiversity and nature conservation.
6. The developer shall implement mitigation measures to lessen the potential for
impacts on badgers arising from the excavation and construction works:
(a) A 30-metre cordon shall be installed around any badger sett entrances, which shall
be screened and remain in place throughout the construction works.
(b) There shall be no artificial lighting of any badger sett entrances during the
construction and operational phases.
(c) During the breeding season, no works shall take place within 50 metres of the sett
for general construction and 150 metres for noisy and vibratory activities.
(d) The built-in construction design shall allow for escape from trenches.
Reason: To ensure appropriate monitoring of the impact of the proposed development on
the badger species of the area.
7. The landscaping proposals shall be carried out within the first planting season
following commencement of construction of the proposed development during the first phase
of the works. Only native species of trees and hedgerow shall be planted. All existing
roadside hedgerows (except at access point openings) and hedgerows around the outer
perimeter of the site shall be retained. The landscaping and screening shall be maintained
at regular intervals. Any trees or shrubs planted in accordance with this condition which are
removed, die, become seriously damaged or diseased within two years of planting shall be
replaced by trees or shrubs of similar size and species to those original required to be
planted. The landscaped berms located in the southern section of the site, shall be
constructed during the first phase of the works.
Reason: To assist in screening the proposed development from view and to blend it into its
surroundings in the interest of visual amenity, in the interest of biodiversity and to protect
wildlife.
8. The developer shall comply with the following transportation requirements:
(a) A final Traffic Management Plan for the construction phase of the proposed
development shall be submitted to, and agreed in writing with, the planning authority prior
to commencement of development.
(b) The Traffic Management Plan shall ensure that there is not a backlog of construction
traffic from the M18/Junction 13 and shall include for staggered deliveries to the site.
(c) Construction of the proposed right-hand turning lane at the main access shall be
commenced concurrently with the commencement of the site works and shall be completed
within six months of the commencement of development on site. The site access and right-
hand turning lane, including the proposed pavement overlay, shall be undertaken as
indicated in the details submitted with the planning application and detailed design, including
drainage arrangements, along the R352 Tulla Road. Works shall be carried out by the
developer at its own expense.
(d) Design details in relation to the proposed pedestrian crossing points on the R352
Tulla Road shall be submitted to the planning authority for written agreement prior to
commencement of development. The crossing points shall be fully in-situ prior to occupation
of the development and the works shall be carried out by the developer at its own expense.
(e) Design details in relation to the proposed shared use footpath/cycle track shall be
submitted to the planning authority for written agreement prior to commencement of
development. The shared use footpath/cycle track shall be located on both sides of the
R352 Tulla Road along the extent of the development boundary to a point just east of the
L8168 side road junction, and the works shall be carried out by the developer at its own
expense.
(f) Details of the exact location of the bus stop shall be submitted to the planning
authority for written agreement prior to commencement of development, which should be
constructed prior to the operation of any part of the proposed development.
(g) CCTV cameras shall be fixed and angled to face into the site and shall not be directed
towards adjoining properties or the road.
Reason: In the interest of pedestrian, cyclist and traffic safety, infrastructure provision, and
the proper planning and sustainable development of the area.
9. Water supply and drainage arrangements, including the attenuation and disposal of
surface water, and flood risk management, shall comply with the requirements of Irish Water
and the planning authority for such works and services, as appropriate.
Reason: In the interest of public health and to ensure a proper standard of development.
10. The developer shall comply with the following additional water supply and drainage
requirements:
(a) The storm water attenuation pond and primary network shall be installed in Phase 1
of the proposed development.
(b) Drainage on to the R352 Tulla Road and the site access shall be by means of a
separate drainage network and attenuation system that discharges directly to the
Ballymacahill/Spancelhill Stream. This system shall be independent of the M18 Motorway
Drainage network.
(c) The final size, volume and design of the proposed attenuation pond and associated
infrastructure shall comply with section 2.2.5 of the Engineering Report received by the
planning authority on the 25th day of February, 2022 and the clarification of further
information response received on the 10th day of June, 2022.
(d) The developer shall install the storm water network, hydrocarbon interceptors and
attenuation area as part as per the designer's requirements and the manufacturer's
instructions, and a suitability qualified Engineer shall certify same. The certification shall be
submitted to the planning authority for written agreement prior to the occupation of any
part of the proposed development.
(e) The developer shall submit details in relation to the maintenance requirements and
schedules for the storm water network and attenuation area to the planning authority for
written agreement prior to the occupation of any part of the proposed development.
(f) The proposed development shall provide 48-hour storage in respect of the adiabatic
cooling waters.
Reason: In the interest of public health and to ensure a proper standard of development.
11. The construction of the proposed development shall be managed in accordance with
a Construction and Environmental Management Plan, which shall be submitted to, and
agreed in writing with, the planning authority prior to commencement of development. This
plan shall provide details of intended construction practice for the proposed development,
including noise management measures, traffic management, protection of wayleaves, an
invasive species management plan, an asbestos management plan, and off-site disposal of
construction /demolition waste.
Reason: In the interest of public safety and residential amenity.
12. Site development and building works shall be carried out only between the hours of
0700 to 1900 Mondays to Fridays, inclusive, between 0800 to 1400 hours on Saturdays and
not at all on Sundays or public holidays. Deviation from these times shall only be allowed
in exceptional circumstances where prior written approval has been received from the
planning authority.
Reason: In order to safeguard the residential amenities of property in the vicinity.
13. The site development and construction works shall be carried out in such a manner
as to ensure that the adjoining roads are kept clear of debris, soil and other material.
Cleaning works shall be carried on the adjoining public roads by the developer and at the
developer's expense on a daily basis.
Reason: To protect the residential amenities of property in the vicinity.
14. The developer shall comply with the following archaeological requirements:
(a) Pre-development archaeological testing shall be undertaken by a suitably qualified
archaeologist licensed under the National Monuments Acts 1930-2004. No sub-surface work
shall be undertaken in the absence of the archaeologist without his/her written consent.
(b) A report, containing the results of the assessment, shall be submitted to the planning
authority and, arising from this assessment, the developer shall agree in writing with the
planning authority details regarding any further archaeological requirements (including, if
necessary, archaeological excavation) prior to commencement of construction works. A
copy of the report shall be submitted to the Department of Housing, Local Government and
Heritage.
(c) The planning authority and the Department of Housing, Local Government and
Heritage shall be notified in writing at least four weeks prior to the commencement of any
site operations (including hydrological and geotechnical investigations) relating to the
proposed development.
In default of agreement on any of these requirements, the matter shall be referred to An
Bord Pleanala for determination.
Reason: In order to conserve the archaeological heritage of the area and to secure the
preservation (in-situ or by record) and protection of any archaeological remains that may
exist within the site.
15. The developer shall submit details in relation to the occupation, operation and
management of the Vertical Farm to the planning authority for written agreement prior to
commencement of development.
Reason: In the interest of orderly development.
16. Prior to commencement of development, the developer shall lodge with the planning
authority a bond of an insurance company, a cash deposit, or other security to secure the
provision and satisfactory completion of the development, coupled with an agreement
empowering the planning authority to apply such security or part thereof to the satisfactory
completion of any part of the development.
Reason: To ensure the satisfactory completion of the development.
17. The developer shall pay a financial contribution to the planning authority in respect
of public infrastructure and facilities benefiting development in the area of the planning
authority that is provided or intended to be provided by or on behalf of the authority in
accordance with the terms of the Development Contribution Scheme made under section 48
of the Planning and Development Act 2000, as amended. The contribution shall be paid
prior to the commencement of development or in such phased payments as the planning
authorities may facilitate and shall be subject to any applicable indexation provisions of the
Scheme at the time of payment. Details of the application of the terms of the Scheme shall
be agreed between the planning authority and the developer or, in default of such
agreement, the matter shall be referred to the Board to determine the proper application of
the terms of the Scheme.
Reason: It is a requirement of the Planning and Development Act 2000, as amended, that a
condition requiring a contribution in accordance with the Development Contribution Scheme
made under section 48 of the Act be applied to the permission.”
Some general considerations
59. It may be of assistance to set out some general considerations arising from previous caselaw,
under a number of headings as follows.
The eight-fold test for relief by way of judicial review
60. As set out in Reilly v. An Coimisiún Pleanála [2025] IEHC 659 (Unreported, High Court, 28
November 2025) and other cases (see also Foran v. An Coimisiún Pleanála & Glenveagh [2026] IEHC
23), there is an eight-fold path to obtaining relief by way of judicial review. These tests are
cumulative, and relief should only be granted if the proceedings meet all of the following:
(i) the applicant complies with jurisdictional requirements (e.g. time or standing to
bring the proceedings at all (as opposed to standing for particular issues within a
case that the applicant can bring at a general level));
(ii) the applicant’s point is legally correct and workable;
(iii) the applicant’s point is properly pleaded with the requisite specificity;
(iv) the specific point is one that the applicant has standing to make (bearing in mind
that while standing can relate to issues such as ius tertii it does not generally require
prior participation in the process insofar as there is an EU/Aarhus Convention
dimension);
(v) material capable of sustaining the point was properly before the decision-taker
at the relevant time such as to give rise to a duty to consider it (subject to exceptions
primarily related to failure by the decision-taker to fulfil her autonomous
obligations);
(vi) the applicant has discharged the onus of proof to establish all facts necessary for
relief;
(vii) any error must transcend the harmless, the non-material and the purely technical
lacking real-world consequences, bearing in mind that if error is demonstrated, then
the onus shifts to the opposing parties to show harmlessness; and
(viii) the exercise of discretion does not militate against the making of the order (such
as considering the proportionality of the order sought), bearing in mind that
discretion is limited in an EU law context.
61. Before dealing with specific elements in detail, some general comments are worth noting at
this juncture:
(i) Judicial review is concerned with the legality rather than the correctness of the
decision: per Clarke J. (Dunne J. concurring) in Sweeney v. Fahy [2014] IESC 50
(Unreported, Supreme Court, 31 July 2014) at paras. 3.8-3.15. It is not an appeal
on the merits and it is not for the court to substitute its view for that of the decision-
taker: per Finlay C.J. in the State (Keegan) v. Stardust Compensation Tribunal
[1986] I.R. 642 at p. 654 (Hamilton P. concurring); per Denham J. in Meadows v.
Minister for Justice, Equality and Law Reform [2010] IESC 3, [2010] 2 I.R. 701 at p.
743; per Lady Hale in R (Cart) v. Upper Tribunal [2011] UKSC 28, [2012] 1 AC 663
at para. 47: “it is not difficult to dress up an argument as a point of law when in
truth it is no more than an attack upon ... factual conclusions”. See also Stapleton
v. An Bord Pleanála & Savona [2025] IEHC 178 (Unreported, High Court, Holland J.,
1 April 2025); Moran v. An Bord Pleanála [2025] IEHC 510 (Unreported, High Court,
26 September 2025) per Farrell J. at 11.
(ii) As Singh L.J. and Carr J. put it in R (Hoareau and Bancoult) v. Secretary of State for
Foreign and Commonwealth Affairs [2019] EWHC 221 (Admin), [2019] 1 W.L.R.
4105 at [326] (emphasis added): “Judicial review is not, and should not be
regarded as, politics by another means”. The court must keep the separation
of powers firmly in mind: Sinnott v. Minister for Education [2001] IESC 63, [2001]
2 I.R. 545 (Keane C.J., Denham, Murphy, Murray, Hardiman, Geoghegan and
Fennelly JJ.); T.D. v. Minister for Education [2001] IESC 101, [2001] 4 I.R. 259
(Keane C.J., Denham, Murphy, Murray and Hardiman JJ.); B. v. Child & Family
Agency & Ors. [2025] IESC 2 (Unreported, Supreme Court, Hogan J., 27 January
2025) (O’Donnell C.J., Murray, Collins and Donnelly JJ. concurring), para. 62;
consequently the courts must respect the principle that policy choices are for other
branches of government. To stray into policy fundamentally distorts the process
because “[t]he administrator is often concerned with broad considerations of the
public interest whereas the judge tends to focus on the claims of the parties to the
case before him” De Blacam, Judicial Review, 2nd ed, p. 97. What O’Donnell C.J.
(Charleton and Woulfe JJ. concurring) has recently said of Article 42A is true of the
Constitution and law generally – it is not “an open-ended provision that requires
courts to substitute their judgment on social issues ... for that of the
Oireachtas” (G. v. Ireland [2025] IESC 49 (Unreported, Supreme Court, 26
November 2025) at 68). Nor is the equality guarantee to “become instead a more
general power to second guess legislative choices in difficult areas where the courts
have very limited insight. ” (at para. 86). He noted:
“In Re SC [2021] UKSC 26, [2022] AC 223, Lord Reed cautioned against an
expansive application of the equality guarantee contained in Article 14 ECHR
observing that, in effect, since legislation was the art of differentiation, any
legislation could be contested from the point of view of equality, and that a
broad and expansive application of the guarantee risked undue interference
with the sphere of political choice. I agree. Once it is established that a
classification is not arbitrary or capricious or based on prejudice or
stereotype, then this is an area where there is particular merit in the
observations of Chief Justice Stone that ‘[c]ourts are not the only agency of
government that must be assumed to have capacity to govern’ (United
States v Butler (1936) 297 US 1).”
(iii) Insofar as concerns evaluative judgement, the weight to be given to any
consideration or piece of evidence is quintessentially a matter for the decision-taker:
Tesco Stores Ltd v. Secretary of State for the Environment [1995] 1 WLR 759 (HL),
780 (Lord Hoffmann); per Keane C.J. (Denham, Murphy and McGuinness JJ.
concurring) in Baby O v. Minister for Justice [2002] IESC 44, [2002] 2 I.R. 169,
[2003] 1 I.L.R.M. 24; M.E. v. Refugee Appeals Tribunal [2008] IEHC 192
(Unreported, Birmingham J., 27 June 2008) at para. 27; Heathrow Airport Ltd [2020]
UKSC 52, [2021] 2 All E.R. 967, [2021] P.T.S.R. 190, [2020] 12 W.L.U.K. 212, Lord
Hodge and Lord Sales SCJJ. at 121; Moran v. An Bord Pleanála [2025] IEHC 510
(Unreported, High Court, 26 September 2025) per Farrell J. at 12. Generally
speaking evaluative judgements involving a significant degree of planning
judgement and not tainted by other procedural, legal or factual errors are reviewable
on an irrationality standard: Sherwin v. An Bord Pleanála [2024] IESC 13
(Unreported, Supreme Court, Woulfe J., 11 April 2024) (Charleton, O’Malley, Baker
and Murray JJ. concurring); Barr J. in Graymount House Action Group v. An Bord
Pleanála [2024] IEHC 327 (Unreported, High Court, 31 May 2024), leave to appeal
refused in Graymount House Action Group v. An Bord Pleanála [2025] IESCDET 22
(Dunne, Woulfe and Hogan JJ., 17 February 2025).
(iv) A decision must be read in a way that makes sense rather than nonsense if
such a reading is available. It is not the case that decisions must be read in the
most erroneous way possible so that applicants can get their order of certiorari (M.R.
(Bangladesh) v. International Protection Appeals Tribunal [2020] IEHC 41, [2020] 1
JIC 2903 (Unreported, High Court, 29 January 2020); Rostas v. DPP [2021] IEHC
60 (Unreported, High Court, 9 February 2021) at §50; St. Margaret’s Recycling v.
An Bord Pleanála [2024] IEHC 94 (Unreported, High Court, Phelan J., 20 February
2024) at §57); Duffy v. An Bord Pleanála [2025] IEHC 715 (Unreported, High Court,
Farrell J., 30 December 2025) at 32.
(v) Thus a decision should not be read as invalid if a valid reading is reasonably
available: see M.R. (Bangladesh) v. International Protection Appeals Tribunal
[2020] IEHC 41 (Unreported, High Court, 29 January 2020) at §7; Mulloy v. An Bord
Pleanála [2024] IEHC 86 (Unreported, High Court, Holland J., 12 March 2024) at
§178 (citing O’Donnell v. An Bord Pleanála [2023] IEHC 381 (Unreported, High
Court, 1 November 2023)); Save Roscam Peninsula CLG v. An Bord Pleanála (No.
6) [2024] IEHC 335 (Unreported, High Court, 7 June 2024) at §64); thus for example
“unhelpful” statements should not be read as inconsistent with statutory factors if
the decision can be read as valid – E.M. v. Minister for Justice and Equality [2024]
IESC 3 (Unreported, Supreme Court, 21 February 2024) per Dunne J. (Charleton,
Woulfe, Murray and Donnelly JJ. concurring); Friends of Killymooney Lough v. An
Coimisiún Pleanála [2025] IEHC 407 (Unreported, High Court, 16 July 2025); Moran
v. An Bord Pleanála [2025] IEHC 510 (Unreported, High Court, 26 September 2025)
per Farrell J. at 13, and this applies even if the wording is sub-optimal: Duffy v. An
Bord Pleanála [2025] IEHC 715 (Unreported, High Court, Farrell J., 30 December
2025) at 32.
(vi) It is not appropriate to engage in legalistic over-parsing or micro-analysis of
decisions, or of legal instruments generally, frequently based on semantic
querulousness: per Sullivan J. in R (Blewett) v. Derbyshire County Council [2003]
EWHC 2775 (Admin), [2004] Env. L.R. 29 at para. 41; R. (Friends of the Earth Ltd
and others) v. Heathrow Airport Ltd [2020] UKSC 52, [2021] 2 All E.R. 967, [2021]
P.T.S.R. 190, [2020] 12 W.L.U.K. 212, Lord Hodge and Lord Sales SCJJ.; per
O’Donnell C.J. (Dunne, Charleton and Baker JJ. concurring) in O’Sullivan v. HSE
[2023] IESC 11 (Unreported, Supreme Court, 10 May 2023) at para. 37. As stated
by Peart J. in G.T. v. Minister for Justice, Equality and Law Reform [2007] IEHC 287,
[2007] 7 JIC 2708 (Unreported, High Court, 27 July 2007), para. 3: “It is not
desirable that a decision be parsed and analysed word for word in order to discern
some possible infelicity in the choice of words or phrases used and to hold that a
finding of credibility adverse to the applicant is invalid, unless the matters relied
upon have been clearly misunderstood or mis-stated by the decision maker. The
whole of the decision must be read and considered in order to reach a view as to
whether, when the decision is read in its entirety and considered as a whole, there
was no reasonable basis for the decision maker reaching that conclusion”. See also
A.I.M.Z. v. Refugee Applications Commission & Ors. [2008] IEHC 420, [2008] 11
JIC 0705 (Unreported, High Court, 7 November 2008) at para. 24 per Clarke J.; per
McCarthy J. in S.A. v. Refugee Appeals Tribunal & Anor. [2009] IEHC 383, [2010] 7
JIC 2803 (Unreported, High Court, 28 July 2009), para. 13; per Clark J. in Obuseh
v. Minister for Justice, Equality and Law Reform & Ors. [2010] IEHC 93, [2010] 1
JIC 1404 (Unreported, High Court, 14 January 2010), para. 21; per MacEochaidh J.
in Bondo v. Minister for Justice & Ors. [2012] IEHC 454, [2012] 11 JIC 0903
(Unreported, High Court, 9 November 2012), para. 24; per Barr J. in P.M. v. Refugee
Appeals Tribunal [2014] IEHC 497, [2014] 10 JIC 0204 (Unreported, High Court, 2
October 2014), para. 59; per Faherty J. in O.S. v. Refugee Appeals Tribunal [2015]
IEHC 839, 2015 WJSC-HC 25494, [2015] 12 JIC 1505 (Unreported, High Court, 15
December 2015), para. 59; X.E. v. International Protection Appeals Tribunal [2018]
IEHC 402, [2018] 7 JIC 0405 (Unreported, High Court, Keane J., 4 July 2018); B.D.C.
(Nigeria) v. International Protection Appeals Tribunal [2018] IEHC 460, [2018] 7 JIC
2006 (Unreported, High Court, 20 July 2018), para. 7; Moran v. An Bord Pleanála
[2025] IEHC 510 (Unreported, High Court, 26 September 2025) per Farrell J. at 13.
Mere technicalities are not normally a proper basis for the grant of relief: see e.g.
The State (Toft) v. Galway Corporation [1981] ILRM 439, Pembroke Road
Association v. An Bord Pleanála [2022] IESC 20, [2022] 2 ILRM 417, Moore v. Dun
Laoghaire Rathdown County Council [2016] IESC 70, [2017] 3 I.R. 42, [2017] 2
I.L.R.M. 21 (Clarke, Laffoy and O’Malley JJ.) para. 4.8 (distinguishing a substance
point from “a technicality”). In Save Cork City Community Association CLG v. An
Bord Pleanála [2022] IESC 52, [2024] 1 I.R. 205 at 60, Woulfe J. (Dunne, Charleton,
O’Malley and Hogan JJ. concurring) said (without needing to decide the point) that
there was “a great deal of force” in the submission that it would be disproportionate
to quash a decision on the basis of a “technical procedural error”. See also
Watchhouse Cross Shopping Centre v. An Coimisiún Pleanála [2025] IEHC 520
(Unreported, High Court, 3 October 2025).
(vii) Relatedly, a decision must be read in the round and in its context. One has to view
an administrative decision in the round, and not place undue weight on semantic
quibbles in respect of micro-sub-elements of it: O.A.A. v. Minister for Justice,
Equality and Law Reform & Anor. [2007] IEHC 169, [2007] 2 JIC 0904 (Unreported,
High Court, Feeney J., 9 February 2007); J.B.R. v. Refugee Appeals Tribunal & Ors.
[2007] IEHC 288, [2007] 7 JIC 3110 (Unreported, High Court, Peart J., 31 July
2007); per Cooke J. in I.R. v. Minister for Justice [2009] IEHC 510, [2015] 4 I.R.
144 at p. 152; M.R. (Bangladesh) v. International Protection Appeals Tribunal [2020]
IEHC 41, [2020] 1 JIC 2903 (Unreported, High Court, 29 January 2020), para. 6. A
decision should be read not solely from an applicant’s point of view (an impossible
standard), but from the starting point of it being valid rather than invalid where
possible. One has to stand back and ask what the decision is fundamentally
saying (O’Donnell & Ors. v. An Bord Pleanála [2023] IEHC 381 (Unreported, High
Court, 1 November 2023), para. 54; St. Margaret’s Recycling v. An Bord Pleanála
[2024] IEHC 94 (Unreported, High Court, Phelan J., 20 February 2024) at §57;
Moran v. An Bord Pleanála [2025] IEHC 510 (Unreported, High Court, 26 September
2025) per Farrell J. at 13.
(viii) Judicial review is not an exercise in pointless formalism: see for example Okunade
v. Minister for Justice [2018] IESC 56, [2018] 11 JIC 1401 (Unreported, Supreme
Court, 14 November 2018) per O’Donnell J. (Clarke C.J. and O’Malley J. concurring)
at para. 21. It is not a game where the respondents can score as many goals as
they like, but if the applicant scores one goal, the game is over. The court must
make a balanced and reasonable assessment of the overall sustainability of
a decision, even if there is an argument for saying that limited parts of it are sub-
optimal: M.R. (Bangladesh) v. International Protection Appeals Tribunal [2020] IEHC
41, [2020] 1 JIC 2903 (Unreported, High Court, 29 January 2020), para. 21.
(ix) It is not for the applicant to dictate the procedures to be adopted or the form
of a decision: see for example per Ryan P. (Peart and Hogan JJ. concurring) in A.B.
v. Minister for Justice and Equality [2016] IECA 48, [2016] 2 JIC 2602, 2016 WJSC-
CA 1525 (Unreported, Court of Appeal, 26 February 2016) at para. 43.
Pleadings
62. Some relevant legal principles concerning pleading requirements which have been rehearsed
in previous caselaw include the following:
(i) Applicants are confined to their pleadings: A.P. v. Director of Public
Prosecutions [2011] IESC 2, [2011] 1 I.R. 729, [2011] 2 I.L.R.M. 100, [2011] 1 JIC
2501; Khashaba v. Medical Council [2016] IESC 10, [2016] 3 JIC 0701, 2016 WJSC-
SC 12280 per O’Malley J. (Denham C.J. and Clarke J. concurring) at para. 56; Casey
v. Minister for Housing, Planning and Local Government & Ors. [2021] IESC 42,
[2021] 7 JIC 1606 (Unreported, Supreme Court, Baker J., 16 July 2021) (Clarke
C.J., O'Donnell, MacMenamin and Dunne JJ. concurring) at §§29 and 31; Concerned
Residents of Treascon and Clondoolusk v. An Bord Pleanála & Ors. [2024] IESC 28,
[2024] 7 JIC 0402 (Unreported, Supreme Court, 4 July 2024) per Murray J. at paras.
39 et seq. (O'Donnell C.J., Woulfe, Collins and Donnelly JJ. concurring); Eglington
Residents Association v. An Bord Pleanála [2025] IEHC 209 (Unreported, High Court,
Farrell J., 15 April 2025) at 11. The rules of pleading are well-established, clear and
mandatory, and are of particular importance in a context of special complexity such
as technical EU-heavy areas of planning law; while exact specification of every jot
and tittle of a case is an impossible standard, an applicant can only be permitted to
advance at a hearing a point that is acceptably clear from the express terms of the
statement of grounds, subject to the grant of any order allowing an amendment:
Reid v. An Bord Pleanála (No. 7) [2024] IEHC 27, [2024] 1 JIC 2401 (Unreported,
High Court, 24 January 2024).
(ii) Pleading requirements in judicial review are “stringent”, allowing “little room
for manoeuvre”: People Over Wind & Anor. v. An Bord Pleanála & Ors. (No. 1) [2015]
IEHC 271, [2015] 5 JIC 0106 (Unreported, High Court, Haughton J., 1 May 2015).
“It shall not be sufficient for an applicant to give as any of his grounds for the
purposes of paragraphs (ii) or (iii) of sub-rule (2)(a) an assertion in general terms
of the ground concerned, but the applicant should state precisely each such ground,
giving particulars where appropriate, and identify in respect of each ground the facts
or matters relied upon as supporting that ground”: Order 84 r. 20(3) RSC. “If on
the Grounds pleaded there is genuine ‘doubt, ambiguity or confusion’ an Applicant
in Judicial Review cannot have the benefit of it”, per Holland J. in Ballyboden Tidy
Towns Group v. An Bord Pleanála & Ors. [2022] IEHC 7, [2022] 1 JIC 1001
(Unreported, High Court, 10 January 2022) at para. 308.
(iii) Complex EU law arguments need to be articulated with particular clarity. It
is particularly important, in the case of an allegation of a failure properly to transpose
an obligation under EU law, that the requirements of O. 84, r. 20(3) be observed:
Sweetman v. An Bord Pleanála (Sweetman XV) [2020] IEHC 39, [2020] 1 JIC 3104
(Unreported, High Court, 31 January 2020) per McDonald J. at para. 103 (cited with
approval by Murray J. (O'Donnell C.J., Woulfe, Collins and Donnelly JJ. concurring)
in Concerned Residents of Treascon and Clondoolusk v. An Bord Pleanála [2024]
IESC 28, [2024] 7 JIC 0402 (Unreported, Supreme Court, 4 July 2024); Rushe v. An
Bord Pleanála [2020] IEHC 122, [2020] 3 JIC 0502 (Unreported, High Court, 5 March
2020) per Barniville J.; attempts to launch for example non-transposition claims not
set out on the pleadings are impermissible: Alen-Buckley v. An Bord Pleanála [2017]
IEHC 311, [2017] 5 JIC 1211 (Unreported, High Court, Costello J., 12 May 2017).
(iv) Recital of high-level principles does not create certiorari by osmosis – an applicant
must specify a route-map connecting the particular factual problem alleged with
the particular relief sought via a chain of reasoning: Ballyboden Tidy Towns v. An
Bord Pleanála [2021] IEHC 648 (Unreported, High Court, 7 January 2022), para. 20;
Foley v. Environmental Protection Agency [2022] IEHC 470 (Unreported, High Court,
Twomey J., 24 January 2023), paras. 71-72; Stapleton v. An Bord Pleanála & Savona
[2024] IEHC 3 (Unreported, High Court, Holland J., 13 February 2024), para. 124.
(v) Scattergun pleadings are liable to be viewed as “a witch’s brew designed to spread
maximum confusion and to permit any argument to be made at the hearing that
ingenuity can suggest”: Hellfire Massy Residents Association v. An Bord Pleanála
[2022] IESC 38, [2024] 1 I.R. 386, [2022] 10 JIC 2402 per O’Donnell C.J. at para.
22 (Dunne, Woulfe, Hogan and Murray JJ. concurring). MacMenamin J. (Fennelly
and Clarke JJ. concurring) in Babington v. Minister for Justice Equality and Law
Reform & Ors. [2012] IESC 65 (Unreported, Supreme Court, 18 December 2012)
referred to the pleading requirements in judicial review and said at para. 7:
“Regrettably, these explicit stipulations are frequently not complied with, and the
same grounds are set out in as many different, varying, (and wearying)
reformulations of the same point as can be conceived. Practitioners should realise
that, in this entirely counterproductive and unnecessary process, there is a real risk
of not being able to see the wood for the trees. A good point does not gain force by
repetition”.
(vi) While the court has jurisdiction to grant unpleaded reliefs it can allow such relief
only within the contours of the case as defined by the pleaded grounds:
Concerned Residents of Treascon and Clondoolusk v An Bord Pleanála [2024] IESC
28, [2024] 7 JIC 0402 (Unreported, Supreme Court, 4 July 2024), para. 42 per
Murray J. (O'Donnell C.J., Woulfe, Collins and Donnelly JJ. concurring). Therefore a
court can’t grant relief if there is no supporting ground for it.
(vii) It is not necessary that the specific provisions of national or EU law relied
on are expressly enumerated if they are implicitly identifiable with acceptable
clarity: Eco Advocacy CLG v. An Bord Pleanála (No. 4) [2023] IEHC 713 (Unreported,
High Court, 18 December 2023); Kennedy & Anor. v. An Bord Pleanála [2024] IEHC
570 (Unreported, High Court, 7 October 2024), para. 132; Leech v. An Bord Pleanála
[2024] IEHC 599 (Unreported, High Court, Farrell J., 12 November 2024); Mount
Salus Residents' Owners Management Company Limited by Guarantee v. An Bord
Pleanála & Ors. [2025] IEHC 14 (Unreported, High Court, Holland J., 15 January
2025), para. 39. The standard is acceptable clarity, not express enumeration.
(viii) As noted by the Court of Appeal in Carvill v. An Bord Pleanála [2025] IECA 84
(Unreported, Court of Appeal, Barniville P., Collins and Faherty JJ., 11 April 2025)
at para. 148, where a developed pleading objection is made, the court should not
accept the point made by the applicant without first addressing the
objection. That said, the court can reject a point without deciding the pleading
objection if it fails either way.
The lens of the material before the decision-maker
63. The foundational concept is that consideration by a decision-taker involves essentially three
elements, which are probably best categorised as follows (see Rural Residents Wind Aware v. An
Coimisiún Pleanála (I) [2025] IEHC 600 (Unreported, High Court, 6 November 2025) at 76):
(i) matters that must be considered either autonomously – normally finite and well
identified – or only if they are raised, such as submissions;
(ii) matters that must not be considered; and
(iii) an infinite range of other matters which a decision-taker may consider if she wants
to but does not have to.
64. Therefore if an autonomous duty does not arise, and if there is no breach of a prohibition on
considering something, then everything else falls under the rubric of what was before the decision-
taker at the time of the decision. Thus:
(i) a basic principle is that in general, the legality of a decision is viewed through the
lens of the material before the decision-taker at the time of the decision,
and not with the benefit of further evidence in hindsight, although there are defined
exceptions: I.S.O.F. v. Minister for Justice, Equality and Law Reform [2010] IEHC
457 (Unreported, High Court, Cooke J., 17 December 2010); Jahangir v. Minister for
Justice and Equality [2018] IEHC 37, [2018] 2 JIC 0102 (Unreported, High Court, 1
February 2018); M.H. (Bangladesh) v. Refugee Appeals Tribunal [2018] IEHC 496,
[2018] 6 JIC 2607 (Unreported, High Court, 26 June 2018); B.D. (Bhutan and Nepal)
v. Minister for Justice and Equality [2018] IEHC 461, [2018] 7 JIC 1709 (Unreported,
High Court, 17 July 2018); A.J.A. (Nigeria) v. International Protection Appeals
Tribunal [2018] IEHC 671, [2018] 11 JIC 1403 (Unreported, High Court, 14
November 2018); O.A. (Nigeria) v. International Protection Appeals Tribunal [2018]
IEHC 661, [2018] 11 JIC 2003 (Unreported, High Court, 20 November 2018); De
Souza v. Minister for Justice and Equality [2019] IEHC 440, [2019] 6 JIC 0407
(Unreported, High Court, 4 June 2019); Ratushnyak v. Minister for Justice and
Equality [2019] IEHC 619 (Unreported, High Court, 16 August 2019) per Keane J.
at paras. 35 to 36; J.W. v. Minister for Justice and Equality [2020] IEHC 500, [2020]
10 JIC 1501 (Unreported, High Court, 15 October 2020); Reid v. An Bord Pleanála
[2021] IEHC 230, [2021] 4 JIC 1204 (Unreported, High Court, 12 April 2021);
Clonres CLG v. An Bord Pleanála & Ors. [2021] IEHC 303, [2021] 5 JIC 0706
(Unreported, High Court, 7 May 2021) at para. 87; Google v. Data Protection
Commission [2024] IEHC 577 (Unreported, High Court, Barr J., 11 October 2024);
Moran v. An Bord Pleanála [2025] IEHC 510 (Unreported, High Court, 26 September
2025) per Farrell J. at 16; Eglington Residents Association v. An Bord Pleanála
[2025] IEHC 209 (Unreported, High Court, Farrell J., 15 April 2025) at 9; Duffy v.
An Bord Pleanála [2025] IEHC 715 (Unreported, High Court, Farrell J., 30 December
2025) at 54;
(ii) it follows that if the consideration of something isn’t an autonomous obligation, and
if nobody in the process raises that something, then belatedly introducing the
point in judicial review is not generally a plausible or permissible basis for quashing
a decision: North Great Georges Street Preservation Society v. An Bord Pleanála
[2023] IEHC 241 (Unreported, High Court, 15 May 2023). In particular in the climate
context, although not confined to that, the extent to which issues were raised in the
process is of major importance (Coolglass para. 118(xiv)). Exceptions are discussed
in Reid v. An Bord Pleanála (No. 1) [2021] IEHC 230 (Unreported, High Court, 12
April 2021) – if such exceptions apply then the court can potentially receive new
evidence;
(iii) the concept of autonomous duties should not be extended to nullify the requirement
to make the point to the decision-taker. Where the decision-taker fails to engage
with the relevant statutory test at all (as in Sherwin for example), one can
characterise that as a breach of an autonomous duty, whether or not submissions
on the point were also made, but where the decision-taker does address the
appropriate test, the outcome of that should not normally be condemned on the
basis of some new argument or evidence which was never put forward in the
process, consistently with the foregoing caselaw.
(iv) it follows a fortiori that if an applicant not only fails to make the point to the decision-
taker but makes a contrary point, that is disqualifying in terms of permitting an
applicant to obtain an order quashing a decision on such an inconsistent basis (see
Clifford v. An Bord Pleanála [2021] IEHC 459 (Unreported, High Court, 12 July
2021), para. 52(ii) where landowners tried to object to a condition that had been
inserted on foot of their own substantive submissions; McGowan v. An Coimisiún
Pleanála [2025] IEHC 405 (Unreported, High Court, 16 July 2025) §§140 & 160;
Fernleigh RA v. An Coimisiún Pleanála [2025] IEHC 655 (Unreported, High Court,
Holland J., 28 November 2025) at 63).
Onus of proof
65. Some relevant legal principles concerning the onus of proof which have been rehearsed in
previous caselaw include the following:
(i) With only defined and extremely limited exceptions, in judicial review the onus of
proof is on the applicant at all times: per Denham J. (Murray C.J. and Fennelly
J. concurring) in Meadows v. Minister for Justice, Equality and Law Reform [2010]
IESC 3, [2010] 2 I.R. 701 at p. 743; Cork County Council v. Minister for Housing,
Local Government and Heritage (No. 1) [2021] IEHC 683 (Unreported, High Court,
5 November 2021) at §57; Monkstown Road Residents Association v. An Bord
Pleanála [2022] IEHC 318 (Unreported, High Court, 31 May 2022) at para. 96 per
Holland J.; that remains the case even when in a constitutional challenge it is proved
that constitutional rights have been interfered with: O’Doherty and Waters v.
Minister for Health [2022] IESC 32, [2023] 2 I.R. 488, [2022] 1 I.L.R.M. 421 per
O’Donnell C.J. (Irvine P., MacMenamin, O'Malley, Baker and Murray JJ. concurring)
at para. 116; Moran v. An Bord Pleanála [2025] IEHC 510 (Unreported, High Court,
26 September 2025) per Farrell J. at 14. To put the same point another way, there
is a presumption of validity for administrative decisions: per Finlay P. in In re
Comhaltas Ceoltóirí Éireann (Unreported, High Court, 5 December 1977) and per
Keane J. in Campus Oil v. Minister for Industry and Energy (No. 2) [1983] I.R. 88 at
102; Grassridge v. Dun Laoghaire Rathdown County Council [2024] IEHC 669
(Unreported, High Court, Holland J., 25 November 2024), para. 22; Moran v. An
Bord Pleanála [2025] IEHC 510 (Unreported, High Court, 26 September 2025) per
Farrell J. at 15.
(ii) The onus shifts only in defined special circumstances. For example, where an error
is demonstrated by an applicant, the onus shifts to opposing parties to show
that the error is harmless: H.A. v. Minister for Justice [2022] IECA 166, [2022] 7
JIC 2201 (Unreported, Court of Appeal, Donnelly J., 22 July 2022) at para. 48 (Ní
Raifeartaigh and Collins JJ. concurring). An onus on a decision-taker in the
administrative process (e.g. to conduct a valid AA) does not convert into an
evidential or any burden in the judicial process to show that the decision is valid (for
reasons explained in Sherwin v. An Bord Pleanála [2023] IEHC 26, [2023] 1 JIC
2701 (Unreported, High Court, 27 January 2023) at para. 85).
(iii) The onus of proof does not shift to a developer merely because the decision-
taker does not defend the decision on a given point or generally. Such a rule
would be inconsistent with the Supreme Court’s finding in Ballyboden Tidy Towns
Group v. An Bord Pleanála & Ors. [2024] IESC 4 (Unreported, Supreme Court,
Donnelly J., 22 February 2024) (O’Donnell C.J., Woulfe, Hogan and Collins JJ.
concurring) that a developer can defend a permission even if the decision-taker does
not.
(iv) In the context of a challenge to an environmental assessment, the onus of proof to
show, by evidence (normally expert evidence), or by demonstrating a flaw
on face of material, that AA/EIA was defective, or that there were factual
circumstances requiring a decision-taker to consider any other autonomous
obligation, lies on the applicant: R v. Crischuk, 2010 BCSC 716 (Barrow J.) at paras.
36-38, affirmed 2010 BCCA 391, 2010 D.T.C 5141; Reid v. An Bord Pleanála (No.
1) [2021] IEHC 230, [2021] 4 JIC 1204 (Unreported, High Court, 12 April 2021),
para. 19; An Taisce v. an Bord Pleanála & Ors. [2022] IESC 8, [2022] 2 I.R. 173,
[2022] 1 I.L.R.M. 281 per Hogan J. at para. 124 (O'Donnell C.J., Dunne, Charleton
and Woulfe JJ. concurring); Carrownagowan Concern Group v. An Bord Pleanála
[2024] IEHC 300 (Unreported, High Court, 20 May 2024) at §191(v) (leave to appeal
refused in Carrownagowan Concern Group v. An Bord Pleanála [2025] IESCDET 9
(Charleton, Collins and Donnelly JJ., 27 January 2025)); Salmon Watch Ireland,
Inland Fisheries Ireland, Sweetman & Ors. v. Aquaculture Licences Appeals Board &
Ors. [2024] IEHC 421 (Unreported, High Court, Holland J., 12 July 2024), §1097;
Nagle View Turbine Aware Group v. An Bord Pleanála [2024] IEHC 603 (Unreported,
High Court, 1 November 2024) at para. 115; Minoa Ltd v. An Bord Pleanála [2024]
IEHC 704 (Unreported, High Court, Heslin J., 10 December 2024), para. 333; Ó
Murthuile v. An Bord Pleanála [2025] IEHC 498 (Unreported, High Court, Farrell J.,
19 September 2025) at 55; Oxigen v. An Coimisiún Pleanála [2025] IEHC 632
(Unreported, High Court, 19 November 2025) (for example, in relation to proving
that a decision-taker lacks expertise). Thus, apart from (i) failure to consider
something that the decision-taker was autonomously required to consider, (ii) patent
flaw on the face of the materials, or (iii) other legal error, inadequate consideration
or failure to dispel scientific doubt has to be established by admissible evidence
(normally expert evidence) in the judicial review showing either that reasonable
doubt was created by the material before the decision-taker at the time (albeit not
limited to what was adduced by the applicant specifically), or that such material
even if uncontradicted would on its face have created doubt in the mind of a
reasonable expert: An Taisce v. An Bord Pleanála (No. 2) [2021] IEHC 422, [2021]
7 JIC 0205 (Unreported, High Court, 2 July 2021) at §7 and §8; Carrownagowan
Concern Group v. An Bord Pleanála [2024] IEHC 300 (Unreported, High Court, 20
May 2024) at §191(v), leave to appeal refused: Carrownagowan Concern Group v.
An Bord Pleanála [2025] IESCDET 9 (Charleton, Collins and Donnelly JJ., 27 January
2025); Kennedy v. An Bord Pleanála [2024] IEHC 570 (Unreported, High Court, 7
October 2024) at §105; Roache v. An Bord Pleanála [2024] IEHC 311 (Unreported,
High Court, Phelan J., 21 May 2024) at §117; Kennedy v. An Bord Pleanála [2024]
IEHC 570 (Unreported, High Court, 7 October 2024) at 73; Ryanair DAC v. An Bord
Pleanála [2025] IEHC 74 (Unreported, High Court, 14 February 2025) at §64 et seq.;
analogously, Donegal County Council v. Planree [2024] IECA 300 (Unreported, Court
of Appeal, Butler J., 18 December 2024), para. 141; Massey v. An Bord Pleanála
(No. 2) [2025] IEHC 206 (Unreported, High Court, 11 April 2025). As noted in Nagle
View Turbine Aware Group v. An Bord Pleanála [2024] IEHC 603 (Unreported, High
Court, 1 November 2024), summarised in the non-precedential determination
refusing leave to appeal [2025] IESCDET 41 (O’Malley, Murray and Donnelly JJ., 10
March 2025) at para. 8, “the critical point was that scientific and factual
shortcomings in EIA or indeed in an Appropriate Assessment, must be established
by the applicant who bore the burden of proof”. Similarly, leave to appeal was
refused in Eco Advocacy v. An Bord Pleanála [2025] IESCDET 74 (Dunne, Hogan and
Donnelly JJ., 4 June 2025) where “The applicant’s claim failed for the reason that
the High Court accepted that the respondent had come to a lawful conclusion of no
doubt that an appropriate assessment was not needed and that the respondent had
given reasons for that conclusion. On the judicial review the applicant had not
displaced that conclusion by way of evidence” (para. 25). That is consistent with
the general law: O’Doherty and Waters v. Minister for Health [2022] IESC 32, [2023]
2 I.R. 488, [2022] 1 I.L.R.M. 421 per O’Donnell C.J. (Irvine P., MacMenamin,
O’Malley, Baker and Murray JJ. concurring). The Supreme Court determination in
100 Meter Tall Group v. An Bord Pleanála [2025] IESCDET 85 (Charleton, Hogan and
Collins JJ., 1 July 2025) is to the same effect: “17. As [the trial judge] pointed out
(at para. 196) the Court of Justice ruled in Case C-721/22 Eco Advocacy CLG
(EU:C:2023:477) the Board simply provides ‘reasons sufficient to explain that the
decision does not create reasonable scientific doubt as to impact on European sites.’
This was simply the test which [the trial judge] applied in the present case. He
concluded (at para. 230) that the Board had addressed the issue of potential bird
movements of water birds and hen harriers and ‘gives reasons for that conclusion
which the applicants have not displaced evidentially.’ 18. The Court considers that
this second issue involves the application of standard principles and does not meet
the constitutional criteria”. See also Eco Advocacy CLG v. An Bord Pleanála &
Statkraft [2025] IEHC 15 (Unreported, High Court, 15 January 2025) at §95;
Concerned Residents of Coolkill v. An Bord Pleanála & Midsal Homes [2025] IEHC
265 (Unreported, High Court, Holland J., 19 May 2025) at 309.
(v) The onus of proof as to an inadequacy in the decision cannot be discharged by
mere assertion: Joyce Kemper v. An Bord Pleanála [2020] IEHC 601, [2020] 11
JIC 2402 (Unreported, High Court, Allen J., 24 November 2020) at §9; Murphy v.
An Bord Pleanála [2024] IEHC 59 (Unreported, High Court, Bolger J., 6 February
2024) at §14; nor does mere assertion create scientific doubt for AA purposes:
Harrington v. An Bord Pleanála [2014] IEHC 232, [2014] 5 JIC 0909 (Unreported,
High Court, O’Neill J., 9 May 2014); Murphy v. An Bord Pleanála [2024] IEHC 59
(Unreported, High Court, Bolger J., 6 February 2024) at §14; Duffy v. An Bord
Pleanála [2024] IEHC 558 (Unreported, High Court, Holland J., 27 September 2024)
at §40-§41.
(vi) If demonstration of error depends on expert opinion, the onus of demonstration in
that regard cannot be discharged by non-expert views articulated by or on
behalf of an applicant. Such an exercise in ultracrepidarianism is generally
inadmissible on standard evidential principles insofar as matters of opinion are
concerned: Massey v. An Bord Pleanála (No. 2) [2025] IEHC 206 (Unreported, High
Court, 11 April 2025).
(vii) Where there is a conflict of admissible evidence, in the absence of cross-examination
such a conflict must generally be resolved against the party carrying the onus
of proof: RAS Medical Ltd v. Royal College of Surgeons in Ireland [2019] IESC 4,
[2019] 1 I.R. 63, [2019] 2 I.L.R.M. 273 (Clarke C.J.) (O’Donnell, MacMenamin,
Dunne and Finlay Geoghegan JJ. concurring). That is normally the applicant but in
the case of an opposing party asserting that a demonstrated error is harmless, the
conflict will be resolved against the opposing party.
(viii) That said, while conflict between equally inherently credible averments, with no
cross-examination, is generally resolved against the party carrying the onus of proof,
a court is not always obliged to regard all averments as being equally
credible, or to disregard internal or evident problems with them (see by
analogy the manner in which the Supreme Court considered it was entitled to prefer
an affidavit over even oral evidence in Koulibaly v. Minister for Justice, Equality and
Law Reform [2004] IESC 50, [2004] 7 JIC 2906 (Unreported, Supreme Court,
Denham J. (Geoghegan and McCracken JJ. concurring), 29 July 2004)). Among the
matters to which regard might be had would be included the failure to explain
patently relevant questions that are clearly within that party’s responsibility (Doorly
v. Corrigan [2022] IECA 6 (Unreported, Court of Appeal, 21 January 2022) at para.
137 (Ní Raifeartaigh and Pilkington JJ. concurring)). This specific and common sense
power of the court to evaluate inherent defects in evidence remains notwithstanding
caselaw on cross-examination such as RAS Medical or Re Bayview Hotel (Waterville)
Limited [2022] IEHC 516 (Unreported, High Court, Butler J., 8 September 2022).
This is consistent by analogy with the judgment of Hardiman J. (Hanna and Feeney
JJ. concurring) in DPP v. Barnes [2006] IECCA 165, [2007] 3 I.R. 130, [2007] 1
I.L.R.M. 350 at para. 95 – the court as finder of fact is “not ... constrained” to accept
“the only account available” even if that account is provided by oral evidence. The
evidence of experts is one area where the court is not automatically obliged to accept
evidence absent cross-examination: Tesco Ireland Limited v. Stateline Transport
Limited [2024] IECA 46 (Unreported, Court of Appeal, Butler J., 23 February 2024).
Reasons
66. Key elements of the law relating to reasons include:
(i) The standard is the obligation to provide the main reasons on the main issues:
Connelly v. An Bord Pleanála [2018] IESC 31, [2018] 2 I.L.R.M. 45 (Clarke C.J.)
(O’Donnell, Dunne, O’Malley and Finlay Geoghegan JJ. concurring); Balz v. An Bord
Pleanála [2019] IESC 90, [2023] 3 I.R. 751, [2020] 1 I.L.R.M. 367 per O’Donnell J.;
Balscadden Road SAA Residents Association Ltd v. An Bord Pleanála (No. 1) [2020]
IEHC 586, [2020] 11 JIC 2501 (Unreported, High Court, 25 November 2020);
Atlantic Diamond v. An Bord Pleanála [2021] IEHC 322 (Unreported, High Court, 14
May 2021); Grassridge v. Dun Laoghaire Rathdown County Council [2024] IEHC 669
(Unreported, High Court, Holland J., 25 November 2024), para. 59; Pat O’Donnell v.
Dublin City Council [2024] IEHC 671 (Unreported, High Court, Holland J., 26
November 2024), para. 129; per Barr J. in Graymount House Action Group v. An
Bord Pleanála [2024] IEHC 327 (Unreported, High Court, 31 May 2024), leave to
appeal refused in Graymount House Action Group v. An Bord Pleanála [2025]
IESCDET 22 (Dunne, Woulfe and Hogan JJ., 17 February 2025); see also non-
precedentially Morris v. An Bord Pleanála [2025] IESCDET 25 (Dunne, Woulfe and
Hogan JJ., 17 February 2025); Ó Murthuile v. An Bord Pleanála [2025] IEHC 498
(Unreported, High Court, Farrell J., 19 September 2025) at 49; Moran v. An Bord
Pleanála [2025] IEHC 510 (Unreported, High Court, 26 September 2025) per Farrell
J. at 33; reasons are to be understood in context of the “Broad issues” – Finlay C.J.
(Griffin, Hederman and Lynch JJ. concurring) in O’Keefe v. An Bord Pleanála [1993]
1 I.R. 39, [1992] I.L.R.M. 237 at p. 76 or “Broad gist” – Faulkner v. Minister for
Industry and Commerce 1997 WJSC-SC 962, [1996] 12 JIC 1007 (Unreported,
Supreme Court, 10 December 1996) per O’Flaherty J. (Hamilton C.J. and Barrington
J. concurring).
(ii) A decision-taker is not required to give “reasons for the reasons”: Munby L.J.
(Tomlinson and Patten LJJ. concurring) in In re A. and L. (Children) [2011] EWCA
Civ. 1611, [2011] 12 W.L.U.K. 725, [2012] 1 F.L.R. 1243, [2012] Fam. Law 285, at
para. 35 (in the context of judicial reasoning – the administrative obligation can’t be
greater); N.P.B.K. (D.R.C.) v. International Protections Appeals Tribunal [2020]
IEHC 450 (Unreported, High Court, 25 September 2020) at 29; Ó Murthuile v. An
Bord Pleanála [2025] IEHC 498 (Unreported, High Court, Farrell J., 19 September
2025) at 49.
(iii) Certain issues are to be viewed objectively as main reasons given the
nature of the process or decision at issue – for example if it is in dispute as to
whether key statutory criteria for the decision have been satisfied. Where the
commission is disagreeing with a council (Sherwin v. An Bord Pleanála [2023] IEHC
26, [2023] 1 JIC 2701 (Unreported, High Court, 27 January 2023)) or with its own
inspector on a point on which the grant or refusal of permission turns, such an issue
is virtually by definition a main issue, speaking objectively, such that a decision not
to give reasons on it would be held to be erroneous (Crekav Trading GP Ltd v. An
Bord Pleanála and Ors. [2020] IEHC 400 (Unreported, High Court, Barniville J., 31
July 2020); Clonres CLG v. An Bord Pleanála & Ors. [2021] IEHC 303 (Unreported,
High Court, 7 May 2021); O'Donnell v. An Bord Pleanála [2023] IEHC 381
(Unreported, High Court, 1 November 2023); Killegland Estates Ltd v. Meath County
Council [2023] IESC 39 (Unreported, Supreme Court, Hogan J., 21 December 2023);
Ventaway v. An Coimisiún Pleanála [2025] IEHC 406 (Unreported, High Court, 16
July 2025); Phelan Walsh v. An Bord Pleanála [2025] IEHC 533 (Unreported, High
Court, Nolan J., 8 October 2025) at 53 citing Connelly v. An Bord Pleanála [2018]
IESC 31, [2021] 2 I.R. 752, [2018] 2 I.L.R.M. 453 (Clarke C.J.)). In the case of the
inspector, there is the additional factor that by contrast with a normal case where
the commission adopts the inspector’s reasons, in a case where the commission
disagrees it must come up with reasons of its own. Where the commission disagrees
with the inspector’s conclusion but on a basis that was not dealt with at all by the
inspector, then any enhanced reasons obligation does not apply: AAI Baneshane v.
An Coimisiún Pleanála [2025] IEHC 641 (Unreported, High Court, 21 November
2025).
(iv) As to what are the main issues arising from submissions of interested parties,
the decision in Friends of the Irish Environment CLG & Anor. v. Minister for Housing,
Local Government and Heritage & Ors. [2025] IECA 128 (Unreported, Court of
Appeal, 5 June 2024) is clear that, per Hyland J. (Costello P. and Collins J.
concurring) at para. 148, it is for the decision-taker in the first instance to decide
whether submissions raise relevant issues. Failure to address an issue in a
submission can be challenged in the normal way.
(v) There is no obligation to provide a discursive, narrative consideration or to
“engage with” submissions in such a sense, or to provide an issue-by-issue or
submission-by-submission response: see Oguekwe v. Minister for Justice, Equality
and Law Reform [2008] IESC 25, [2008] 3 I.R. 795, per Denham J. (Murray C.J.,
Fennelly, Kearns and Finnegan JJ. concurring) referring to the lack of a need for a
“micro specific format” (at p. 819); per Clarke J. (Fennelly and MacMenamin JJ.
concurring) in Rawson v. Minister for Defence [2012] IESC 26 (Unreported, Supreme
Court, 1 May 2012) at para. 6.9, referring to the need for a “reasoned but not
discursive ruling”. Confusing a lack of narrative discussion with a lack of reasons is
a classic applicant’s fallacy: see e.g. Ó Murthuile v. An Bord Pleanála [2025] IEHC
498 (Unreported, High Court, Farrell J., 19 September 2025) at 23.
(vi) Reasons may be found anywhere, not necessarily in the decision itself, for
example in an inspectors report: Connelly v. An Bord Pleanála [2018] IESC 31,
[2021] 2 I.R. 752, [2018] 2 I.L.R.M. 453, para. 9.2 per Clarke C.J. (O’Donnell,
Dunne, O’Malley and Finlay Geoghegan JJ. concurring); Sherwin v. An Bord Pleanála
[2024] IESC 13 (Unreported, Supreme Court, 11 April 2024) per Woulfe J.
(Charleton, O’Malley, Baker and Murray JJ. concurring) at para. 129; thus no
additional requirement for reasons is required when adopting a reasoned report (for
example of a chief executive or indeed an inspector): Killegland Estates v. Meath
County Council [2022] IEHC 393, [2022] 7 JIC 0106 (Unreported, High Court, 1 July
2022) at para. 65; Shadowmill v. An Bord Pleanála [2023] IEHC 157 (Unreported,
High Court, Holland J., 31 March 2023), para 84; Pat O’Donnell v. Dublin City Council
[2024] IEHC 671 (Unreported, High Court, Holland J., 26 November 2024) at para.
144.
(vii) Reasons may be implicit from the context, for example it can be implicit that
matters submitted were held not to be outweighing when placed against factors
supporting the conclusion arrived at: Rana v. Minister for Justice [2024] IESC 46
(Unreported, Supreme Court, O’Malley J., 18 October 2024), paras. 96-99 (Dunne,
Hogan, Collins and Donnelly JJ. concurring).
(viii) Consistently with the principle that there do not need to be reasons for the reasons,
a decision-maker doesn’t need to give reasons for not changing her mind from
an already-articulated position, or for not making an exception to a clear policy
for which reasons have been previously articulated, unless there is a significant
change in circumstances or the unusual case of a new point being made of such
significance that it needs to be expressly addressed: AAI Baneshane v. An Coimisiún
Pleanála [2025] IEHC 641 (Unreported, High Court, 21 November 2025). That
principle in turn reflects an even broader principle that a re-iteration of a previous
position or decision is not a new decision for the purposes of judicial review, and
does not for example re-start the clock for challenge: Killegland v. Meath County
Council [2022] IEHC 393 (Unreported, High Court, 1 July 2022). That said, a new
plan is indeed a new decision and can be challenged afresh even if it contains the
proverbial old wine in a new bottle. But an individual decision does not become a
fresh decision merely because the decision-maker is asked to change her mind and
doesn’t.
(ix) There is no obligation to give reasons for not changing the status quo, for example
maintaining a previous plan provision, in respect of which reasons would have been
given at an earlier stage: Jones v. South Dublin County Council [2024] IEHC 301
(Unreported, High Court, 11 July 2024) at §209, Voyage Property v. Limerick City
and County Council [2025] IEHC 696 (Unreported, High Court, Holland J., 16
December 2025) at 106.
(x) There is no obligation to state reasons for what is obvious: Killegland Estates
v. Meath County Council [2022] IEHC 393, [2022] 7 JIC 0106 (Unreported, High
Court, 1 July 2022) (from which the Supreme Court dismissed an appeal, [2023]
IESC 39 (Unreported, Supreme Court, Hogan J., 21 December 2023) (O’Donnell C.J.,
Charleton, O’Malley, Baker, Woulfe and Donnelly JJ. concurring)), para. 83;
Industrial Development Agency v. Information Commissioner [2024] IEHC 649
(Unreported, High Court, Phelan J., 15 November 2024), para. 132.
(xi) There is no obligation to give reasons for rejecting a legally incorrect point:
see Ironborn v. Dun Laoghaire Rathdown County Council [2023] IEHC 477
(Unreported, High Court, Mulcahy J., 31 July 2023). Reasons are tied into the
exercise of evaluation and judgement, so if the latter do not arise then neither does
the former – thus there is no need for reasons if there is in fact no evaluation
by the decision-taker – if the issue is correctly applying a mandatory, non-
discretionary, non-evaluative, legal rule, a valid decision does not become invalid
due to failure to explain the law or indeed to give reasons for the rejection of a
legally incorrect submission.
(xii) There is generally no obligation to give reasons for not changing one’s mind
from a previously articulated position absent a significant change in circumstances
or a significant new point: Killegland Estates v. Meath County Council [2022] IEHC
393, [2022] 7 JIC 0106 (Unreported, High Court, 1 July 2022), para. 67; Pat
O’Donnell v. Dublin City Council [2024] IEHC 671 (Unreported, High Court, 26
November 2024), para. 145 per Holland J.
(xiii) A decision should not be quashed for lack of reasons if nobody could be in any
real doubt as to what the reasons were: Killegland Estates v. Meath County Council
[2023] IESC 39, [2023] 12 JIC 2109 (Unreported, Supreme Court, 21 December
2023) per Hogan J. (O’Donnell C.J., Charleton, O’Malley, Baker, Woulfe and Donnelly
JJ. concurring); Moran v. An Bord Pleanála [2025] IEHC 510 (Unreported, High
Court, 26 September 2025) per Farrell J. at 34.
(xiv) If some reasons are good and others are bad, the decision may be severable if the
good reasons are stand-alone (McCarthy Meats v. Minister for Housing, Planning
and Local Government [2020] IEHC 371, [2020] 7 JIC 2707 (Unreported, High Court,
Heslin J., 27 July 2020); Murtagh v. An Bord Pleanála [2023] IEHC 345 (Unreported,
High Court, Owens J., 29 March 2023); Ironborn v. Dun Laoghaire Rathdown County
Council [2023] IEHC 477 (Unreported, High Court, Mulcahy J., 31 July 2023);
Voyage Property v. Limerick City and County Council [2025] IEHC 696 (Unreported,
High Court, Holland J., 16 December 2025)).
(xv) Reasons are not severable if there is a certain link between the reasons (Element
Power Ireland Ltd v. An Bord Pleanála [2017] IEHC 550 (Unreported, High Court,
Haughton J., 28 September 2017)).
(xvi) Reasons should not be created ex post facto: K v. Minister for Justice [2022]
IEHC 582 (Unreported, High Court, Bolger J., 21 October 2022); Ballindooley
Developments Limited v. Minister for Housing Local Government and Heritage & Ors.
[2025] IEHC 109 (Unreported, High Court, Holland J., 20 February 2025), although
reasons that existed at the relevant time can be evidenced after the event if
appropriate: RPS Consulting Engineers Ltd v. Kildare County Council [2015] IEHC
113, [2017] 3 I.R. 61 at para. 109.
The climate law context
67. Insofar as relevant, some relevant issues concerning the climate context include the
following:
(i) According to the statutory Climate Action Plan 2025 published under the Climate
Action and Low Carbon Development Act 2015 as amended, as well as known critical
risks of climate change, “[w]e also face increasing risks of reaching irreversible
climate tipping points, with unknown and potentially catastrophic
consequences for societies, ecosystems and economies” (p. 22, emphasis added).
Previous decisions have noted that “[t]he climate emergency represents a critical
risk to human and natural life on earth” (e.g. Wild Ireland Defence v. An Coimisiún
Pleanála [2025] IEHC 726 (Unreported, High Court, 17 December 2025) at 53). One
recent widely-reported study noted that “research on climate tipping points,
amplifying feedbacks, and cascading interactions shows that several Earth system
components may be closer to destabilizing than once believed. These processes are
thought to be the precursors of a potential ‘hothouse trajectory’: a pathway in which
self-reinforcing feedbacks push the climate system past a point of no return,
committing the planet to substantially higher long-term temperatures, even if
emissions are later reduced. Policymakers and the public, however, remain
largely unaware of the risks posed by such a practically irreversible transition”
(emphasis added) (William J. Ripple et al., “The risk of a hothouse Earth trajectory”,
One Earth, 101565, 11 February 2026).
(ii) Domestic law imposes significant climate-related obligations on national decision-
takers, including in the field of planning. The Climate Action and Low Carbon
Development (Amendment) Act 2021 (amending the Climate Action and Low Carbon
Development Act 2015) mandates the achievement of a net-zero carbon economy
by 2050 (s. 3(1) of 2015 Act as substituted by the 2021 Act), with a legally binding
51% reduction in emissions by 2030 compared to 2018 levels (s. 6A(5) of 2015 Act
as substituted by the 2021 Act): see Coolglass v. An Coimisiún Pleanála [2026] IESC
5 (Unreported, Supreme Court, 4 February 2026).
(iii) EU law also involves significant climate-related objectives and obligations. Directive
2009/28/EC of the European Parliament and of the Council of 23 April 2009 on the
promotion of the use of energy from renewable sources and amending and
subsequently repealing Directives 2001/77/EC and 2003/30/EC established
mandatory targets for the consumption of energy from renewable sources by
member states. Regulation (EU) 2018/1999 of the European Parliament and of the
Council of 11 December 2018 on the Governance of the Energy Union and Climate
Action, amending Regulations (EC) No 663/2009 and (EC) No 715/2009 of the
European Parliament and of the Council, Directives 94/22/EC, 98/70/EC,
2009/31/EC, 2009/73/EC, 2010/31/EU, 2012/27/EU and 2013/30/EU of the
European Parliament and of the Council, Council Directives 2009/119/EC and (EU)
2015/652 and repealing Regulation (EU) No 525/2013 of the European Parliament
and of the Council (the Governance Regulation) was adopted to implement the Paris
Agreement commitments (agreement at conference of parties of the UNFCCC (the
United Nations Framework Convention on Climate Change opened for signature at
UN Conference on Environment and Development, Rio de Janeiro, Brazil, 3-14 June
1992) (COP21) in Paris, on 12 December 2015). By way of implementation of the
Paris Agreement, the European Climate Law (2021) (Regulation (EU) 2021/1119 of
the European Parliament and of the Council of 30 June 2021 establishing the
framework for achieving climate neutrality and amending Regulations (EC) No
401/2009 and (EU) 2018/1999) involves a reduction of GHG emissions for the EU
by at least 55% by 2030 compared to 1990 levels. Ireland’s Nationally Determined
Contributions (NDCs) under Paris are as part of the EU contribution to GHG
reductions. Council Regulation (EU) 2022/2577 of 22 December 2022 lays down a
framework to accelerate the deployment of renewable energy. Article 3(1)
introduced a presumption of overriding public interest for renewable energy projects
for the purpose of the birds, habitats and strategic environmental assessment (SEA)
directives, and provision was made for the acceleration of such projects. The current
version of the Renewable Energy Directive (REDIII), Directive (EU) 2023/2413 of
the European Parliament and of the Council of 18 October 2023 amending Directive
(EU) 2018/2001, Regulation (EU) 2018/1999 and Directive 98/70/EC as regards the
promotion of energy from renewable sources, and repealing Council Directive (EU)
2015/652, provides for a presumption of overriding public interest and for
accelerated timelines including requiring judicial remedies to be the most expeditious
available in national law.
(iv) The ECHR, relevant to domestic law via the European Convention on Human Rights
Act 2003, involves a binding legal obligation to address climate change: Verein
KlimaSeniorinnen Schweiz and Others v Switzerland (9 April 2024, App. no.
53600/20) (this is consistent with the decisions of all other international courts/
tribunals: International Court of Justice Advisory Opinion of 23 July 2025,
Obligations of States in respect of Climate Change; International Tribunal for the
Law of the Sea, Advisory opinion, Request by Commission of Small Island States,
21 May 2024; Inter-American Court of Human Rights, Request by Chile and
Colombia, Opinión Consultiva Oc-32/25 De 29 de Mayo de 2025).
68. The Supreme Court summarises its conclusions on the 2015 Act at para. 118 of Coolglass.
Arising from that one can highlight the following, taking the liberty of eliding some text specific to
the arguments in that particular case (particularly the applicant’s phrasing of the test at first instance
which I had agreed with – the Supreme Court obviously didn’t uphold that particular wording but
one needs to bear in mind the general point that everything arises in context, and the arguments at
trial and appeal level seem to have been significantly different on all sides as the judgment seems
to recognise) (emphasis added):
(i) “The evident purpose and effect of s. 15 of the 2015 Act following the amendments
made in 2021, is to strengthen the obligations imposed upon bodies (including the
Commission) and to make the performance of all their functions consistent with the
climate objectives insofar as is practicable. That obligation is, in principle,
enforceable by a court.”
(ii) “The requirement imposed by s. 15, cannot simply be reduced to a purely procedural
obligation, or confined to operation at a programmatic level. Therefore, the
provision requires more than that bodies (including the Commission) that are
subject to its terms ‘have regard to’ the climate objectives referred to in
the section.”
(iii) “While the language ‘in a manner consistent with’ looks to the outcome of the
performance of the relevant function, it also implies that there is a range of
possible outcomes open to the relevant body which may satisfy the
application, and a degree of tolerance in the manner in which it is achieved.”
(iv) “That tolerance is further reinforced by the inclusion in s. 15 of the
qualification entailed by the words ‘in so far as practicable’. These make it
clear that the section contemplates that there may be circumstances in which a
relevant body may not be required to perform its functions in a manner consistent
with the s. 15(1) objectives. The decided cases propose that ‘in so far as practicable’
means something that is capable of being carried into action having regard to such
practical difficulties that exist, but does not permit the taking of mere matters of
convenience into consideration. That qualification is, however, to be contrasted with
phrases such as ‘insofar as possible’, which are more demanding. It comprehends
what is practical in the circumstances and appropriate to the requirements
of the situation.”
(v) “Because s. 15(1) applies to all relevant bodies, and the exercise of their functions,
the impact in fact of the section will vary depending on the functions of the
relevant body, and the matters to which they are obliged to have regard, or
to implement.”
(vi) “The question for a court where it is asserted that the actions of any relevant body
failed to comply with s. 15(1), is whether the performance of the functions of
the relevant body in that regard falls within the spectrum of possible
outcomes that could be said to be consistent, in so far as is practicable, with
the objective of s. 15.”
(vii) “That is a legal test. Section 15 creates a legal standard which must be
complied with by a relevant body, and if necessary enforced by courts, which
in any given case will be required to determine if any decision or action was in so
far as practicable consistent with the matters specified in s. 15.”
(viii) “Because of the range of options presented by the consistency obligation as so
explained – together with the qualification of practicability – and the difference
between an individual decision and objective stated at a high level of generality, it
should not be a difficult matter to establish such consistency, particularly
when the individual action can be shown to be consistent with some plan
or strategy which itself was prepared subject to the obligation contained in
s. 15(1) or can otherwise be taken to satisfy the obligation of consistency.”
(ix) “In the field of individual planning decisions, it is perhaps less likely that s. 15(1)
will have decisive effect than in respect of the actions of other relevant
bodies. That is because the pursuit and achievement of the climate
objective is already woven into the planning process to a significant
degree.”
(x) “... The question of consistency of an individual planning decision with the s. 15(1)
objectives, is much more complex than a traffic light system of climate friendly
‘go’ (unless impracticable), and climate unfriendly ‘stop’.”
(xi) “By the time a planning decision comes to be made, the manner in which it is
proposed the State will meet its climate objectives has been set at a national level,
percolating down to a local level through the specific context of the development
plan. A planning authority is entitled to commence into consideration with a
presumption that compliance with the development plan will itself be
compliant with its s. 15(1) duty.”
(xii) “[In the case of material contravention], it is not a case of asking whether material
contravention of the plan will assist in achieving the climate goals and therefore
granting permission for any renewable energy project that does so. The function
being exercised is the grant of permission for a development which
materially contravenes the development plan. It is this function which must
be performed so far as is practicable, consistent with the climate change
objectives in s. 15(1).”
(xiii) “If in such a case, the development plan is itself consistent with the climate
objectives set out in s. 15(1), then it will normally be the case that a decision
which complies with that plan will itself be consistent with those objectives.
However, it may be possible to contend that permission should be granted, because
it is established that the development plan does not meet the climate
objectives, or no longer does so because of a change in those objectives, or
because of particular features of the specific development. In any such
case, the Commission must consider whether it should grant the
permission, and if the matter is raised, should be able to explain why the
decision it has come to is indeed consistent with those objectives.”
(xiv) “Section 15(1) may also affect the planning process outside the question of any
material contravention. In most cases it will be the case that the project will be
entitled to permission or will be likely to be refused because of the application of
planning considerations which themselves have been shaped by the State’s plans
and strategies for the achievement of the climate objectives. But s. 15 may reinforce
that process. Where but only where it is raised in support of an application,
an authority should be able to explain why the decision it has come to is in
compliance with s. 15 (1).”
(xv) “... The duty on the Commission to perform its function in a manner consistent with
the climate objectives set out in s. 15(1), while real, effective and enforceable,
cannot be converted into the simple formula [of a traffic light system as
referred to above].”
(xvi) “… the decision and report are phrased in terms that seem to imply that the very
fact that the development would contravene the development plan was considered
itself a reason to refuse the permission. That was an error of law because the
Commission was required to consider whether the climate benefits of the
project required or justified the grant of permission notwithstanding the
material contravention of the development plan. This was reinforced, when
considered in light of the s. 15(1) obligation. …”
69. Operationalising this in the context of emissions-causing projects by way of taking the liberty
of essaying a comment in that specific context, some potential points of particular practical note
are:
(i) The extent to which climate issues were raised in the process is of major importance
(Coolglass para. 118(xiv)), such that a failure to raise climate issues may have the
effect of limiting the obligations on the decision-taker and correspondingly limiting
the scope for relief to be granted by the court.
(ii) A decision-taker can generally begin with a rebuttable presumption that other plans,
programmes and measures have been adopted in line with climate duties (Coolglass
para. 118(xi)). This presumption can be displaced, the onus to do so being
inferentially on an applicant (Coolglass para. 118(xiii)).
(iii) However, in such a case, the commission agrees that the formulation of the test
nowhere envisages an onerous obligation on an applicant to seek declaratory relief
declaring a non-2015-Act-consistent plan or programme to be invalid. Rather the
focus is on any given public body being required to exercise its relevant function in
a 2015-Act-consistent manner, including by way of considering whether the exercise
of a power to depart from a plan or programme is justified in that regard (Coolglass
para. 118(xvi)).
(iv) One can observe that the scenario that arises where a decision-taker has no
jurisdiction to depart from a plan or programme that is not 2015-Act-consistent was
not an issue in that case, but presumably that would fall under the lack of practicality
exception. By contrast with the more typical case where the commission does have
a relevant discretion, a challenger in a case where such discretion does not exist
would be required to challenge the validity of the plan or programme in order to
impugn the decision on such a ground.
(v) While the starting presumption that other entities will act consistently with the 2015
Act has the effect that climate objectives are or at least should be woven in to plans
and programmes (Coolglass para. 118(ix)), one might be allowed to point out that
the absence of any express mechanism to render such a weave meaningful was not
an issue in that case so may need further consideration if and when it arises. While
national measures distribute carbon objectives horizontally across sectors of
industry and other activity, it is not obvious how, for example, the burden of overall
national targets can be appropriately shared vertically across different geographical
areas by different planning authorities, all acting largely independently, other than
by postulating a particularly pertinent and emphatic co-ordinating responsibility on
the Minister and OPR.
(vi) The section involves a degree of flexibility and thus an applicant has the onus to
demonstrate that the performance of the functions of the relevant body falls outside
the spectrum of possible outcomes that could be said to be consistent, in so far as
is practicable, with the objective of s. 15 (Coolglass para. 118(vi)). This is not
however merely a reasonableness test: s. 15 imposes a legal duty (Coolglass para.
118(vii)).
(vii) One of the most inherent practical dimensions of consistency is the extent, if any,
of net GHG emissions in the context of a project that has gross emissions. The 2015
Act and instruments under it are geared towards an objective of “net zero” (art. 2(1)
of the European Climate Law, Regulation (EU) 2021/1119) equivalent to the “climate
neutral economy” referred to in s. 3(1) of the 2015 Act. That necessarily involves
consideration of mitigation, conditions and offsets which may change an otherwise
problematic project into a project that poses no major issue to consistency with
climate instruments and objectives.
(viii) That is additional to the more general point that the net climate objective is to be
achieved over a defined period of time so involves an overall balance between
different actions, some of which may involve net emissions in themselves (see
Coolglass para. 86).
(ix) It does not take from the foregoing, and nor does it create a simplistic traffic light
system, or dilute any of the necessary qualifications (inherent flexibility, range of
options, consistency as a spectrum, conditioned by practicability, viewed in the
context of points made in the process, a starting presumption that other plans are
climate-consistent, and so on) to observe that by necessary consequence from the
subject-matter, including the national climate objectives, the task of a decision-taker
in being readily in a position “to explain why the decision it has come to is in
compliance with s. 15 (1)” will be likely as a practical matter to be empirically
somewhat easier in the case of (a) approving or refusing a climate-neutral
development, approving a climate-positive development, or refusing a climate-
negative development, as opposed to (b) approving a climate-negative development
or refusing a climate positive-development.
(x) It can also be observed that while many of the climate instruments are
phrased in general terms, some of the duties are conceptualised in a precise
and even mathematical context. The concept of budgeting for instance, to
the extent that it arises, is inherently mathematical. This was not an issue
in Coolglass so is for a future case. But even where there are precise and
granular duties, judicial review of a decision-taker’s approach must be in the
context of the submissions made to the public body concerned, the approach
in other plans and programmes, the concept of practicability, and such a
range of options as may exist that are consistent even with granular duties.
In short, there is no automatic chain of reasoning (such as comparing
quantification of net emissions and available headroom) that applies
mandatorily and irrespective of process participants’ submissions, even for
consistency with precise mathematical limits. That said, one can argue that
that mathematical outcomes are in practice naturally facilitated by a
mathematical methodology – but we need to bear all of the foregoing
qualifications in mind.
(xi) A final important context is that while s. 15(1) requires consistency with a range of
climate instruments an objectives, the carbon budgets and SECs are omitted. Thus,
while inevitably, the climate instruments referred to in s. 15(1) will refer to budgets
and SECs, the extent to which such mention translates into a mandatory duty to act
consistently must be viewed from the starting point of the lack of independent
statutory obligation in that regard.
The issues in Module II
70. By letter of 7 October 2024, the commission indicated that it would not oppose an order of
certiorari on the basis of core ground 6 in so far as it alleged an error in the inspector’s report
concerning bat roosts. However, the notice party chose to defend the decisions and filed a limited
statement of opposition on 27 March 2024, addressing only the bat issue.
71. Due to the limited nature of the concession made by the respondent, Module I did not
consider the effect of requirement that a derogation licence be obtained in advance of consent being
given. As a result, the balance of ground 6 is at issue in this Module.
72. The commission’s written submissions seemed to be premised on a fairly enthusiastic
embrace of the No. 1 judgment, and following my having inquired as to the logical implications of
that, the commission stated that it was withdrawing its previous concession and clarified that it was
persuaded by the correctness of the No. 1 judgment (to the effect that the error about bat roosts
was, in context, harmless and not a proper basis for certiorari). That was expressly agreeing (i.e.,
on reflection) with the No. 1 decision and not simply submitting to it.
73. Core ground 4 (involving the draft data centre policy) was withdrawn. Core ground 5 (SEA
of the Government statement) was overtaken by the judgment of 4 October 2024, Friends of the
Irish Environment CLG v Government of Ireland and Others, C-727/22, ECLI:EU:C:2024:825 and is
no longer pursued. The applicants are also no longer pursuing core ground 7 (Water Framework).
The live issues are therefore confined to grounds 1, 2, 3, and the balance of 6.
Domestic law issues
Core grounds 1 to 3 – climate
74. The statement of case dealt with core grounds 1 to 3 collectively by breaking those grounds
down into a number of sub-issues.
75. Core ground 1 is:
“1. The Data Centre Decision is invalid in that the Board failed to apply and/or consider
its mandatory obligation under section 15 of the Climate Action and Low Carbon
Development Act 2015 (as amended by Section 17 of the Climate Action and Low Carbon
Development (Amendment) Act 2021), namely in so far as practicable, to perform its
functions in a manner consistent with the matters stated in section 15, including (a) the
most recent approved climate action plan, (the Climate Action Plan 2023), (d) the
furtherance of the national climate objective, and (e) the objective of mitigating greenhouse
gas emissions (GHG emissions) and adapting to the effects of climate change in the State;
and/or failed to provide sufficient reasons to explain how it sought to apply and/or consider
its mandatory obligation under the 2015 Act, further particulars of which are contained
below.”
76. Core ground 2 is:
“2. The Data Centre Decision is invalid in that the Board acted irrationally, erred in law
and/or failed to provide reasons and/or adequate reasons, in finding that the PDC would
have potentially positive environmental impacts, based on a future switch to the use of
sustainable/renewable gas supplies, which do not exist in sufficient volumes for any practical
application in respect of the PDC and which are not expected to exist in sufficient volumes
for any practical application in respect of the PDC at any point during the operational phase
of the PDC, further particulars of which are contained below.”
77. Core ground 3 is:
“3. The Data Centre Decision is invalid in that the Board acted irrationally by failing to
require any mitigation of the GHG emissions from the PDC, further particulars of which are
contained below.”
78. To understand the large amount of material the applicants have packed into these three
points we need to look at the various distinct points in the sub-grounds.
79. Unhelpfully, the applicants structured the statement of case around a separately numbered
series of headings (a) to (j) which did not follow the numerical sequence of the sub-grounds. I will
attempt to provide cross-references, but insofar as any point is inadvertently referred to under a
heading other than the potentially most appropriate one (something for which the applicants must
take complete and exclusive responsibility due to their idiosyncratic and inconsistent numbering
systems), the reader must take what follows as a whole so that all grounds should be assessed in
the light of all points made below where relevant.
Sub-grounds 1 to 6 (issue (a)) – alleged wrong question
80. The parties’ positions as recorded in the statement of case are summarised as follows:
“CORE GROUNDS 1-3 (Climate):
(a) The Wrong question
Applicants’ position
1. Firstly, the Commission has simply asked itself the wrong question for the purposes
of section 15.
2. In the Commission’s Order it records that it ‘had regard to the following…the Climate
Action Plan 2023’. That is simply the wrong question, given the amendments effected by
the 2021 Act and as further elaborated by the Supreme Court in Coolglass.
3. Where the Commission failed to even attempt to answer the correct question, the
Decision cannot stand. ‘Having regard’ to the 2015 Act would have been sufficient prior to
the 2021 Act amendments. In Coyne v An Bord Pleanala, Holland J. held that the ‘have
regard’ to obligation denoted an obligation only to (§27) ‘consider whether to take it into
account and, if so, what weight to give it’.
4. The problem for the Commission is that this is no longer the correct test. The
Applicant’s legal point is not that the Commission was not aware of the 2015 Act – it clearly
was - but rather that it failed to apply the correct legal test as required by that Act – it
merely had ‘regard’ to something that it was obliged to act ‘consistently’ with.
5. Not only did it ask itself the wrong question but the test it applied (‘have regard’) is
at the opposite end of the spectrum to the correct test (‘consistency’). Furthermore,
nowhere did the Commission’s Inspector identify the obligation to act ‘consistently’ and the
reference to ‘Compliance with Climate Policies’ is in fact a heading in the Inspector’s Report
that in fact does not mention section 15 of the 2015 Act at all.
6. The Commission applied a different test than required by the 2015 Act, and its error
is not minor. It clearly did not perform the type of analysis envisaged by Coolglass and
Killymooney. Consistency with section 15(1) is central to the proposed development given
the scale of its energy demands, and since the Commission did not ask the right question,
its decision cannot stand.
Commission’s Position
7. The jurisprudence of the Court favours substance - administrative decisions should
be not be [sic]read as unlawful or in error where a lawful readings is available. Applying
this approach, per Coyne v. An Bord Pleanála [2023] IEHC 412 Holland J. held (at §160)
that:
‘I agree with EngineNode that what matters in law is not whether the Board explicitly
mentioned s.15 or the matters it lists but is whether, in substance, it complied with s.15.’
8. On the facts, the grant of consent is consistent with the matters in s.15(1)(a)-(e)
including the CAP to the standard of consistency that Coolglass mandates.
9. If, in analysis of the rest of the grounds and sub-grounds, the Court is satisfied in
substance that ACP has performed this function, there should be no merit in this ground. If
the Court finds it has not, then this ground is largely irrelevant.
Developer’s Position
10. The Applicants’ contention that the Commission ‘asked itself the wrong question’
under section 15 of the 2015 Act (as amended) is not borne out when the Decision and
Inspector’s Report are read fairly and as a whole.
11. The gravamen of the complaint is that the Commission recorded in its Order that it
‘had regard to’ the Climate Action Plan 2023 (‘CAP 2023’), and that this language reflects
application of the pre-2021 ‘have regard to’ standard rather than the post-amendment
obligation to act ‘in so far as practicable… in a manner consistent with’ the matters set out
in s.15(1). That submission elevates form over substance. The question is whether the
Commission, in substance, performed its function in a manner consistent (in so far as
practicable) with the matters identified in s.15(1). Section 15 does not prescribe any
particular verbal formula in an order.
12. Section 15(1) does not prescribe any particular formula of words which must be
recited in an order of the Commission. What it requires is that the relevant body perform
its functions in a manner consistent, in so far as practicable, with the specified instruments.
The question for the Court, as articulated by the Supreme Court in Coolglass, is whether the
outcome falls within the spectrum of decisions that could lawfully be said to be consistent
with those instruments identified in s.15(1) and not whether the precise statutory wording
is reproduced in the decision. In this case, the Inspector identified and evaluated the
projected greenhouse gas emissions, the regulatory context (including EU ETS coverage),
mitigation measures, and national climate policy including CAP 2023, before concluding that
the development did not undermine the national climate objective. That evaluative exercise
constitutes the relevant consistency assessment.
13. The Applicants’ argument rests entirely on the appearance of the phrase ‘had regard
to’ within the list of matters considered in the Board’s Order. However:
(a) The Board was obliged to have regard to multiple instruments, some of which attract
a consistency obligation (e.g. CAP 2023 under s.15), and others which do not, e.g. the
applicable development plan. The neutral formulation in the Order reflects that composite
exercise.
(b) As a matter of logic, one cannot assess consistency without first having regard to
the instrument in question. The inclusion of CAP 2023 within the list of matters considered
is therefore a necessary step in the evaluative process.
(c) The legal question is whether the substance of the Inspector’s reasoning and the
Board’s adopted conclusions demonstrate engagement with the section 15 obligation. They
plainly do.
14. The Inspector included a discrete section dealing with climate compliance, national
climate policy, the EU Emissions Trading System, carbon budgets, and the design and
mitigation features of the project. The AWN appeal response addressed section 15 expressly
and in terms and analysed the proposed development against CAP 2023 and the national
climate objective. The Board adopted that reasoning. This is the antithesis of the defect
identified in Coolglass, where the Commission failed to engage in a real and substantive way
with the core climate argument in the context of a material contravention.
15. While the Inspector did not recite the wording of s.15 verbatim, she engaged directly
with CAP 2023, the national climate objective, and mitigation measures, and assessed the
development’s emissions profile within that framework. She concluded that the proposed
development did not undermine the objectives of those instruments. Section 15 does not
require ritualistic citation of its wording; it requires performance of the function in a
consistent manner. The Inspector’s analysis demonstrates precisely that structured
evaluative engagement.
16. The Supreme Court in Coolglass has clarified that s.15 imposes a legal obligation of
outcome, but one assessed within a spectrum of lawful possibilities, having regard to the
generality at which climate instruments are framed. That is the test to be applied here.
17. The Applicants’ further assertion that the Commission did not perform ‘the type of
analysis envisaged by Coolglass and Killymooney’ is unsustainable. This is not a case in
which the Commission ignored section 15. Climate policy was front and centre of the appeal
process. The development site was identified in the Development Plan for data centre use,
a plan presumed to have been adopted consistently with section 15. The Inspector evaluated
emissions, mitigation, ETS coverage, and decarbonisation pathways. The Board adopted
that evaluative reasoning.
18. The Applicants effectively invite the Court to require the Commission to
demonstrate, in express and formulaic terms, that it consciously applied the word
‘consistent’ rather than ‘have regard’. That is an exercise in excessive formalism. As
repeatedly emphasised in the jurisprudence on judicial review, decisions are to be read fairly,
in a common-sense manner, and so as to uphold rather than invalidate them where possible.
19. Ultimately, the Applicants have not identified any concrete respect in which the grant
of permission is inconsistent, in so far as practicable, with CAP 2023, the national climate
objective, or the objective of mitigating greenhouse gas emissions. The complaint is purely
semantic.”
81. Insofar as it is alleged that the commission asked the wrong question, there is simply nothing
in this complaint. Taking the decision as a whole it can’t be said that the commission understood
their duty as merely to have regard. The inspector referred to “compliance” with climate change
policies (p. 48 of data centre permission inspector’s report) – compliance being naturally understood
in the sense of consistency.
82. Litigation-by-selective-quotation is not a valid form of reasoning generally and certainly not
here.
83. Or to put the matter another way, if all the commission had said was that it had regard to
climate instruments, then the applicants would have a point. But they said a lot more. Putting the
different treatments of the issue together means that the reference to regard must be read in the
sense submitted by the commission here, namely that to act consistently with something one starts
with regard, but one goes on from there, as the commission did in this case. The law on asking the
wrong question (e.g. Stokes v. Christian Brothers High School Clonmel [2015] IESC 13, [2015] 2
I.R. 509; Walsh v. An Bord Pleanála [2022] IEHC 172 (Unreported, High Court, 1 April 2022)) is not
relevant because the decision can’t properly be read as indicating a misunderstanding of the test.
Sub-grounds 7 and 8 (issue (c)) – SECs and carbon budget
84. The parties’ positions as recorded in the statement of case are summarised as follows:
“(c) Failure to act consistently with the Sectoral Emissions Ceilings/Carbon Budget
Applicants’ Position
53. The obligation to comply with the SEC comes as a consequence of Section 15(1)(a).
The CAP 2023 (at 12.1.4) is required to be consistent with the SECs and the Carbon Budgets
and therefore non-compliance with the SECs and the Carbon Budgets also entails non-
compliance with the requirements of section 15(1)(a). It is also a consequence of the
Commission’s obligations pursuant to sections 15(1)(d) and (e) both of which objectives
necessarily entail or presuppose compliance with the SECs.
54. However, the Inspector (and the Commission) made no reference to same, other
than to recognise that they had been raised as an issue by the appellants. In circumstances
where there is extremely limited reference by the Commission to the Carbon Budgets (as
adopted) and the Sectoral Emissions Ceilings (as adopted), and still less any consideration
or assessment of such Budgets/ Ceilings, contrary to the requirements of section 15(1)(a),
(c), (d) and (e) of the Climate Action and Low Carbon Development Act 2015 (as amended),
the Commission cannot be said to be acting ‘in a manner consistent with’, the Climate Action
Plan 2023, the Sectoral Emissions Ceilings or the Carbon Budgets; and/or has not in any
way demonstrated the requisite consistency.
55. This is pure arithmetic, with two numbers required to perform the relevant
calculation. However the Commission didn’t establish either number. The Commission failed
to either establish the amount of emissions remaining in the relevant sectoral emissions
ceiling or the amount of emissions which would be created by the PDC. It utterly failed to
even attempt to perform its function in accordance with the Climate Action Plan and therefore
S15.
56. The Applicants' point is that there is no evidence at all that the Commission
considered, let alone acted consistently with the Carbon Budgets and Sectoral Emissions
Ceilings and in fact the information provided by the Developer shows that the PDC is
inconsistent with the electricity sectoral emissions ceiling.
Commission’s Position
57. The Commission understands the point as being that the Commission failed to either
establish the amount of emissions remaining in the relevant sectoral emissions ceiling or the
amount of emissions which would be created by the PDC – and that it utterly failed to even
attempt to perform its function in accordance with the Climate Action Plan and therefore
S15. The Applicants' point is that there is no evidence at all that the Commission considered,
let alone acted consistently with the Carbon Budgets and Sectoral Emissions Ceilings and in
fact the information provided by the Developer shows that the PDC is inconsistent with the
electricity sectoral emissions ceiling. There are three points in reply:-
58. First, the Applicants clearly chose to make their case on the basis of an assertion
that the PDC is ‘inconsistent with the electricity sectoral emissions ceiling.’ That has simply
not been proven or shown and since it is the bedrock of their argument here, and consistent
with the burden of proof in judicial review, nothing else should be entertained on this point.
59. Second, the emissions were described and by reference to the ceilings in question –
see e.g. Table 5 in the AWN Appeal Response, dated September 2022 (Appendix 3 of Appeal
document). The data is presented, and insofar as the Applicant complains elsewhere, its
presented at an 80% basis, just as the Applicant did in its pleadings, so too can the Court
expect the Commission to understand how an 80% figure looks at 100% (even if that was
relevant, given the evidence of the Notice Party on operational load). It expressly addresses
the carbon budgets and sectorial emission ceilings (§3.10 et seq), before setting out for
stated reasons that:
a. ‘…as outlined below, the facility will operate in compliance with the policies and
objectives of the 2021 Climate Act. The phasing of the development and the period taken
to reach full capacity within each planned phase will result in the “ramping up” of demand
associated with the project over a number of years during the lifetime of the 10 year
permission.’ (§3.15)
60. Third, as noted above, and consistent with the Government Statement of the Role
of Data Centre’s in Ireland’s Enterprise Strategy, the CDP operates a selective and plan lead
approach to data centres and the CDP was, in turn, examined by the Office of the Planning
Regulator and the CAP also refers to the ETS as a ‘measure’ to deliver sectoral emissions
ceilings in industry (§13.3 and §13.3.5).
61. In reality, the point amounts to no more than saying that the Applicant sees a gap
where the Commission didn’t expressly determine whether the proposed development here
exceeds the ceilings as things stand, but there is no evidence of that at all. It is in the space
of a baseless assertion which the Courts have decried in every other context when this
technique of argument in judicial review arises.
Developer’s Position
62. The Applicants’ contention that non-compliance with Sectoral Emissions Ceilings
(‘SECs’) or Carbon Budgets automatically entails non-compliance with section 15(1)
proceeds from a fundamental mischaracterisation of the statutory architecture.
63. Section 15(1) requires a relevant body to perform its functions, in so far as
practicable, in a manner consistent with the most recent CAP, the national climate objective,
and the objective of mitigating greenhouse gas emissions. It does not impose a free-
standing obligation on the Commission it convert national ceilings into project-level
prohibitions.
Carbon Budgets and SECs Operate at National Level
64. Carbon Budgets (required under s.6A of the 2015 Act) and SECs (required under
s.6C of the 2015 Act) are macro-level instruments adopted by Government, allocating
aggregate permissible emissions across sectors over multi-annual periods. They are tools
of national governance and policy implementation. They are not statutory caps directed at
individual planning authorities or at particular projects. Nothing in the 2015 Act requires
the Commission, when determining a planning application, to calculate ‘remaining
headroom’ within a sectoral ceiling or to allocate a portion of that ceiling to a proposed
development.
65. The Applicants’ submission that this is ‘pure arithmetic’ misunderstands the
structure of the legislation. The statutory question is not whether a project consumes a
percentage of a ceiling, but whether the decision to grant permission is consistent, in so far
as practicable, with the CAP and the national climate objective. The Act does not prescribe
a numerical compliance formula at project level. Notwithstanding this, the numbers
(Sectoral Emission Ceiling % and carbon budget %) are in AWN Response to the Third Party
Appeals.
No Legal Requirement for Project-Level Ceiling Reconciliation
66. The Applicants assert that the Commission was required to:
(a) establish the amount of emissions remaining within the relevant SEC; and
(b) calculate the project’s emissions;
(c) reconcile the two arithmetically; and
(d) refuse permission if a percentage threshold were exceeded.
67. Neither the 2015 Act nor CAP 2023 establishes a mechanism whereby individual
planning decisions allocate or deduct from a sectoral emissions ceiling. The Supreme Court
in Coolglass did not suggest that section 15 imposes a budget-allocation exercise on
individual planning decisions. Rather, it emphasised that section 15 creates a legal standard
of consistency assessed within a spectrum of possible outcomes (§78), having regard to the
generality at which climate instruments are framed.
68. Carbon Budgets and SECs are framed at high levels of abstraction and are
implemented through a combination of legislative, regulatory, fiscal, and infrastructural
measures. The planning code is one component of that wider machinery. The planning
decision making framework is not transformed by section 15 into a numerical gatekeeper of
sectoral quotas.
69. The Applicants’ premise that ‘the Commission didn’t establish either number’ is
factually incorrect. The EIAR quantified projected emissions. The AWN appeal response
modelled operational emissions conservatively. The figures cited by the Applicants (e.g.,
1.1% of national emissions or 12.3% of the electricity sector ceiling) derive from that
material.
70. The Inspector expressly addressed emissions, ETS coverage, mitigation, and
alignment with national policy. The suggestion that the Commission made ‘no reference’ to
Carbon Budgets other than noting that they were raised by appellants ignores the structured
climate analysis undertaken in §7 of the Inspector’s report.
71. What the Inspector did not do - because she was not required to do so - was to
conduct a speculative accounting exercise of ‘remaining sectoral headroom’ for 2030. That
exercise would in any event be inherently uncertain, as sectoral emissions trajectories
depend on a multiplicity of variables beyond any individual planning permission.
CAP 2023 Consistency Does Not Require Numerical Sectoral Alignment
72. The Applicants contend that because CAP 2023 must itself be consistent with the
Carbon Budgets and SECs (CAP 2023, §12.1.4), any development allegedly inconsistent with
a ceiling is automatically inconsistent with section 15(1)(a). That reasoning conflates
different statutory functions.
73. CAP 2023 is a national plan setting out measures to achieve the Carbon Budgets.
The Commission’s obligation is to perform its planning function in a manner consistent, in
so far as practicable, with that plan. It does not have the effect of imposing project-level
prohibitions by reference to the spare capacity in such budgets.
74. If the Applicants’ argument were correct, any project emitting GHGs within a
constrained sector would be presumptively unlawful once a projected percentage threshold
were reached. That would effectively paralyse development in emitting sectors and would
convert Carbon Budgets into rigid absolutes, which is not a result contemplated by the 2015
Act, as is clear from Coolglass.
The Electricity Sector Context
75. The Applicants assert that the projected emissions render the development
inconsistent with the electricity sectoral emissions ceiling. However, sectoral ceilings
operate at national aggregate level and are not applied as project-level thresholds.
Electricity-sector emissions are subject to the EU Emissions Trading System (ETS), which
imposes a binding cap at EU level. The Inspector was entitled to consider that regulatory
superstructure in assessing consistency with national climate objectives.
76. Secondly, sectoral ceilings operate at national aggregate level and are influenced by
grid decarbonisation, renewable deployment, interconnection, storage, and demand-side
management. It is legally incorrect to isolate a single project and equate its total emissions
with ‘inconsistency’ with a sectoral ceiling.
77. Thirdly, the development incorporated mitigation, efficiency measures, renewable
procurement potential, and adaptive capacity. The Inspector assessed these matters and
concluded that the development did not undermine the national climate objective.
The Statutory Test Remains Consistency ‘In So Far As Practicable’
78. Section 15(1) expressly qualifies the obligation by the phrase ‘in so far as
practicable.’ The Applicants’ formulation omits that statutory qualification. Planning
decisions involve balancing climate considerations with other dimensions of proper planning
and sustainable development, including economic development, regional policy,
infrastructure provision, and energy security.
79. The Board was required to integrate climate considerations into its decision-making
process, not to subordinate all other considerations to a project-level emissions arithmetic.
The Applicants’ argument seeks to transform Carbon Budgets and SECs into rigid,
numerically enforceable project-level ceilings. That is not the statutory scheme. The
Inspector quantified emissions, assessed their significance, considered mitigation and
regulatory context, and evaluated the proposal against CAP 2023 and the national climate
objective. When viewed through the lens articulated in Coolglass, the Decision falls within
the lawful spectrum of outcomes that could be regarded as consistent, in so far as
practicable, with section 15(1). The Applicants’ ‘pure arithmetic’ formulation is a merits-
based policy argument, not a legal infirmity.”
85. I have some sympathy for the applicants’ basic point which is that carbon budgeting is
ultimately mathematical. Nature cannot be fooled, as Richard Feynman was fond of saying (most
famously in Report of the Presidential Commission on the Space Shuttle Challenger Accident, Rogers,
William P.; Armstrong, Neil A.; Acheson, David C.; Covert, Eugene E.; Feynman, Richard P.; Hotz,
Robert B.; Kutyna, Donald J.; Ride, Sally K.; Rummel, Robert W.; Sutter, Joseph F., 1986). Nature
doesn’t care much for evaluative judgement, a spectrum of permissible flexibility, high-level general
principles and so on. What nature cares about is the actual number of GHG molecules in the
atmosphere. The Paris agreement, as reflected in EU law, reflects a specific mathematical
commitment, which is then translated into national levels by way of nationally determined
contributions (NDCs), also co-ordinated in EU law. That is then translated into sectoral limits in
precise numerical terms by domestic climate instruments. That’s the way it has to work.
86. Here we come up against the court’s limited role in the matter. The court is not an all-
purpose problem-solving agency. As outlined above, that role is limited by various factors, most
notably here by the extent to which substantive domestic law gives the court a function.
87. The basic problem with this ground is a straight read-across from budgets/SECs to lack of
consistency under s. 15. The first difficulty there is that budgets and SECs are not included in s.
15(1) as such – any indirect duty has to be demonstrated. The alleged pathway at 12.1.4 of CAP23
is not in fact pleaded – it first pops up in submissions. So the point fails at the outset. But if I am
wrong about that I will consider it anyway.
88. The claim of failure to have regard to relevant matters is self-defeating since the pleadings
acknowledge that the commission referred to the budgets/SECs.
89. Ultimately this ground is not sustainable in the light of Coolglass because it doesn’t
accurately reflect the doctrine of the spectrum of available options. The applicants have not
demonstrated that the decision falls outside the lawful spectrum.
90. Furthermore and even more fundamentally, it fails to take into account the mitigation of
effects as a result of corporate power purchasing agreements (CPPAs).
91. To that extent, the fact that, as the commission submits, “the Applicants clearly chose to
make their case on the basis of an assertion that the PDC is ‘inconsistent with the electricity sectoral
emissions ceiling’” leads the difficulty that, bearing in mind the CPPAs, that conclusion “has simply
not been proven or shown and since it is the bedrock of their argument here, and consistent with
the burden of proof in judicial review, nothing else should be entertained on this point”.
92. That is not to say that in another case an applicant might not put forward during the process
a more focused and nuanced critique of the net carbon impact of a development, comprehensively
taking into account both developer-friendly concerns such as risks of carbon leakage (i.e.,
displacement of projects to less regulated jurisdictions – one would have thought that data centres
were prone to this type of effect, but obviously that’s subject to evidence in an appropriate case),
or sufficiently defining the existing baseline scenario to encompass carbon-generating activities that
may be replaced by the project, as well as applicant-friendly points such as risks of rebound effects
of induced demand, or potentially displacement of renewable energy currently powering other
projects. If such a submission properly engaged with the correct legal framework for decision-
making, the commission might find itself facing a more difficult task in explaining how permission is
consistent with climate instruments. This would be particularly so where such a comprehensive
analysis indicates net GHG emissions after mitigation and offsets. That is basically a polluter pays
scenario. It is not immediately obvious as a general principle why projects creating net GHGs should
be allowed to use the sky as an open sewer for free.
Sub-grounds 9 to 11 (issue (d)) – CAP – extra-large energy users
93. The parties’ positions as recorded in the statement of case are summarised as follows:
“(d) Inconsistency with Climate Action Plan: Extra-large energy users
Applicants’ Position
80. The Climate Action Plan 2023 states (at 12.1.3) that:
‘Large energy users will need to play a critical role in the decarbonisation acceleration that
is required for the sector in delivering high levels of flexibility across time and geographical
locations, and matching energy consumption with renewable energy generation on an hourly
basis.’
81. The PDC does not match energy consumption with renewable energy generation at
all, let alone on an hourly basis.
82. As a result, in particular at peak times, the PDC will result in fossil fuel burning onsite
and through the national grid, by increasing demand generally. This is a material
inconsistency with CAP2023, which the Commission has failed to show was practicably
unavoidable. This, combined with the lack of spare carbon budget, is sufficient to
demonstrate that the Decision is inconsistent with Section 15.
83. At 12.3.4 (Further Measures) the Climate Action Plan 2023 states:
‘The third carbon budget (2031-2035) is expected to require continued electrification of
industry, the built environment, and transport, leading to substantial electricity demand
growth which will need to be almost fully decarbonised. This may require the following
potential policies in the third carbon budget period.
- A policy to require future dispatchable generation to be zero carbon gas ready.
- Policies to ensure that zero carbon gases, like hydrogen, are utilised in the electricity
sector to provide zero carbon dispatchable electricity at sufficient scale;’
84. The PDC’s dispatchable generation will be powered by diesel and will not be zero
carbon gas ready. This is a further material inconsistency with CAP 2023, which the
Commission has failed to show was practicably unavoidable.
Commission’s Position
85. The Applicant’s rely on Section 12.1.3 of CAP23 to say there needs to be matching
on an hourly basis, and they say there isn’t.
86. CAP23 cannot be read like this. In this respect, Section 12.1.3 is titled ‘the scale of
the challenge’ and the ‘challenge’ in this respect is how the electricity sector can de-
carbonise. The contents of Section 12.1.3 are not an immediate prescription of demands
for how development consent may be granted, but an essaying of what the challenge
involves setting out the scale of it and in that respect, over time, it is provided that ‘Large
energy users will need to play a critical role in the decarbonisation acceleration that is
required for the sector in delivering high levels of flexibility across time and geographical
locations, and matching energy consumption with renewable energy generation on an hourly
basis’ and, in particular, ‘More granular certification processes will be required, including
“time stamped” guarantees of origin, so that energy intensive users can demonstrate that
they are using zero emissions electricity during the same hour and geographical location to
match all of their consumption on a 24-hours a day, seven days a week basis.’ The point,
however, is that the very processes envisaged here to meet the challenge don’t presently
exist. Section 12.1.4 then sets out what CAP23 says about the measures to ‘meet the
challenge.’ Those measures are proposed at an architectural or high level, and do not
include, for example, at present, a measure requiring development consent conditioning to
match demand on an hourly basis. Indeed, it specifically says that between ‘now and 2030’
what is required is the national delivery of ‘a flexible system to support renewables and
demand.’
87. The point here is that a present absence of matching demand to supply on an hourly
basis (if that was proven) does not mean inconsistency with CAP23. And, insofar as the
point is about matching, generally, the Commission relies on the point made elsewhere
herein about CPPAs.
Developer’s Position
88. Section 12.1.3 the CAP relied upon by the Applicants is a policy aspiration describing
the role large energy users will need to play in sectoral decarbonisation. It does not create
a legally binding requirement that every large energy user must achieve hourly renewable
matching as a precondition to development consent. To the extent that the Applicants seek
to elevate §12.1.3 into a binding consent condition requirement, that contention does not
arise clearly from the pleaded grounds. Insofar as the Applicants seek to make such a case
via the Statement of Case, this is impermissible.
89. CAP 2023 does not prescribe a statutory rule that planning permission may only be
granted to large energy users capable of demonstrable hourly renewable alignment. The
language is directional and strategic, not prescriptive or self-executing at project level. The
relevant passages are framed in directional and systemic terms and contemplate progressive
implementation through market and regulatory reform.
90. Section 15 requires performance of functions in a manner consistent, in so far as
practicable, with CAP 2023. It does not require the Commission to ensure full operational
compliance with every forward-looking policy ambition at the date of consent.
91. The Inspector considered the project’s energy strategy, which includes:
(a) on-site generation;
(b) grid supply interaction;
(c) adaptability to renewable gases;
(d) load management and system integration; and
(e) renewable procurement potential, including CPPAs.
92. The development incorporates features aligned with CAP objectives for large users,
including:
(a) co-location of demand and generation, reducing transmission losses;
(b) load flexibility potential;
(c) infrastructure capable of transition to hydrogen and biomethane blends as same
come on line;
(d) solar PV integration;
(e) district heating potential and heat reuse;
(f) energy efficiency measures.
93. The Applicants’ assertion that the PDC ‘does not match energy consumption with
renewable energy generation at all’ ignores both the renewable procurement commitments
advanced in the appeal response and the adaptive design of the facility.
94. In any event, CAP 2023 doesn’t require real-time hourly renewable matching at the
point of consent. Such alignment is a system-wide objective to be implemented
progressively through market design, grid development, regulatory reform, and contractual
mechanisms.
95. The Applicants argue that at peak times the PDC will result in fossil fuel burning,
whether on-site or through grid demand. That observation is neither novel nor legally
determinative. The electricity system remains in transition and CAP 2023 contemplates a
phased decarbonisation of dispatchable generation. The existence of fossil generation in the
current system does not render every electricity-consuming development inconsistent with
CAP. Section 15(1) does not impose an immediate fossil-free threshold. The statutory
question is whether the decision is consistent, in so far as practicable, with the trajectory
toward decarbonisation. The Inspector’s analysis addressed precisely that trajectory.
96. The Applicants rely on §12.3.4 (Further Measures) of CAP 2023, which identifies
potential policies that ‘may’ be required in the third carbon budget period (2031–2035),
including:
- a policy to require future dispatchable generation to be zero carbon gas ready;
- policies to ensure hydrogen utilisation at scale.
97. That passage is explicitly forward-looking and conditional (‘may require’). It does
not constitute a binding rule presently in force.
98. The proposed development’s energy centre engines are capable of operating on
natural gas initially and transitioning to renewable gas blends (including biomethane and
hydrogen) as those fuels become commercially and physically available. The Inspector
addressed that adaptability.
99. The reference to diesel generators concerns back-up generation. Backup diesel plant
is standard in data centre infrastructure for emergency resilience. It does not define the
primary operational energy model. CAP 2023 does not prohibit the existence of diesel
backup plant during the transition period.
100. The Applicants’ argument effectively treats prospective future policy considerations
as if they were current statutory prohibitions. That is not the legal position.
101. The Applicants assert that any departure from hourly renewable matching or zero-
carbon dispatchable status constitutes a ‘material inconsistency’ unless shown to be
‘practicably unavoidable’.
102. That formulation inverts the statutory test. Section 15 doesn’t require the
Commission to demonstrate why full decarbonisation is ‘practicably unavoidable’. It requires
the Commission to perform its function in a manner consistent, in so far as practicable, with
the CAP.
103. The Inspector engaged with CAP 2023, sectoral context, energy system transition,
and mitigation measures. The Board adopted that reasoning. There is no requirement for
the Commission to prove the absence of any theoretical inconsistency; rather, the question
is whether the decision falls within the lawful spectrum of outcomes consistent with national
climate policy.”
94. Sub-grounds 9 to 11 are mere recitals of documents or statements of legal or policy context,
not actual pleas of a specific legal wrong, so there is nothing that one needs to deal with.
95. But assuming counterfactually that the point was properly pleaded, the previous problems
apply. The commission does not have an inherent obligation to apply any particular formula when
approaching the question of consistency.
96. The relied-on §12.3.4 (Further Measures) of CAP23 is inherently flexible and does not either
on its own terms or at all bindingly demand a negative outcome here in the way the applicants
assert.
97. The applicants have again failed to show that the commission acted outside the spectrum of
permissible options.
Sub-grounds 12 to 21 (issue (e)) – CAP – hydrogen
98. The parties’ positions as recorded in the statement of case are summarised as follows:
“(e) Inconsistency with Climate Action Plan: Hydrogen
Applicants’ Position
104. The Commission relied upon ‘the future switch to the use of sustainable / renewable
gas supplies in the energy centre for energy generation’, to find the PDC would have a
potentially positive environmental impact, despite such use of renewable gas being directly
excluded by 13.3.3 of CAP 2023.
105. The National Hydrogen Strategy (NHS), which is integrated and forms part of the
Climate Action Plan 2023, was published by the Department of the Environment, Climate
and Communications on 12 July 2023. At Section 3.2 the NHS 2023 states: ‘The use of
hydrogen as a primary energy source for large electricity users, such as data centres, is
considered a low priority end-use, as the direct supply of electricity from renewable sources
will be more efficient.
106. The NHS 2023 uses an estimated efficiency factor of 70% for the creation of
hydrogen using excess electricity, with the caveat that ‘Significant uncertainty exists around
these figures given renewable hydrogen is a nascent technology’. AWN Consulting provides
an estimate for the generation of electricity using such gas powered generation facilities of
45% efficiency. If such efficiency levels were achieved using hydrogen, the generation of
electricity using hydrogen produced using electricity might reach 31.5%. As such, 387MW
of constant renewable electricity would be required to fuel the 120MW gas powered
electricity generation.
107. However, the Government Statement on the Role of Data Centres (created on foot
of Climate Action Plan 2021 and incorporated into CAP2023) requires (at page 11), an
increased level of renewable energy production in order to address their intermittency.
Where offshore wind is the source, the requirement is increased by 80% (a directly electrified
100MW data centre requires 180MW of offshore wind). As such the PDC would require an
additional 696.6MW of offshore wind to be put in place, to mitigate its effects. For solar
power the requirements are an increase by a factor of 7.3, so the requirements would be
2.8GW by 2030 (in addition to the national target of 8GW under CAP 2023).
108. The NHS forms an integral part of the CAP 2023. Where the Decision expressly
relies upon a use of hydrogen which is inconsistent with the NHS (and the wording of CAP
2023 itself), such reliance is inconsistent with Section 15(1).
109. Furthermore, in relation to biomethane the developer used an assumption of
biomethane mix of 18% in 2030 (approximately 10 TWh) which assumption was derived
from a brochure produced by Gas Networks Ireland, whereas the then in force Climate Action
Plan 21 factored in only 3% of biomethane in the gas network in 2030 (1.6TWh). There was
no evidence that biomethane would, in fact, lead to the quantity of GHG emissions reductions
identified by the Commission.
110. The legal point here is simple – the Commission reached a conclusion that the
proposed development would be fuelled by biomethane (§7.3) where there was no evidence
before the Commission to support that proposition.
Commission’s Position
111. Again, there are multiple points here.
• First, they say use of renewable gas being directly excluded by 13.3.3 of CAP 2023
and say the NHS 2023 is preclusive of it.
• Second, they say the legal point here is simple – the Commission reached a
conclusion that the proposed development would be fuelled by biomethane (§7.3) where
there was no evidence before the Commission to support that proposition.
• Third, they say furthermore, in relation to biomethane the developer used an
assumption of biomethane mix of 18% in 2030 (approximately 10 TWh) which assumption
was derived from a brochure produced by Gas Networks Ireland, whereas the then in force
Climate Action Plan 21 factored in only 3% of biomethane in the gas network in 2030
(1.6TWh). There was no evidence that biomethane would, in fact, lead to the quantity of
GHG emissions reductions identified by the Commission.
112. As to the first point, the reading of policy is simply wrong here. It is not correct that
CAP23 nor the NHS is preclusive of a developer proposing that its future needs may be met
by such sources and proposing a development designed to be able to take advantage of
that. CAP23 simply does not support that reading where it actually says ‘[t]o facilitate
investment, we will bring forward policies and regulatory frameworks to stimulate domestic
biomethane production and use, and the development of a sizeable hydrogen sector’. To
propose that the NHS should be read as precluding the approach here is equally difficult to
understand. Certainly, one can see the notion that it is a low priority end-use for large
electricity uses as other renewable provision will be more efficient. None of this precludes
reference to the potentially positive effect of using this fuel if and when it becomes possible.
However, at no point all, has the Commission premised its conclusions on some assumption
that the PDC is only acceptable because it may ultimately be hydrogen fuelled. Indeed, it
does indeed require some careful pause before accepting an argument that it is contrary to
national policy for a proposed development to describe itself as hydrogen or biomethane
ready.
113. As to the second point, and related to this whereas the Inspector referred to the
‘potentially positive environmental impacts’ involved with ‘the future switch to the use of
sustainable / renewable gas supplies in the energy centre for energy generation’, this is one
aspect of a host of considerations reached under the heading of EIA whereby many impacts,
including obviously negative impacts were addressed and relevant mitigation discussed. The
Commission was not, on any fair reading relying on ‘the future switch to the use of
sustainable / renewable gas supplies’ as being a deal-breaker. It was an observation on
likely environmental effects that if that occurs, it is positive. Indeed, the positive impact is
described as ‘potentially’ positive and is part of the general notion that the PDC was informed
by decarbonisation agenda (as CAP 2023 requires) – i.e. there may be some developments
that simply cannot ever accommodate hydrogen. In short, the Applicant characterises the
Commission Decision as premising its view on the acceptability of the PDC, including from a
climate point of view, on the basis that ultimately there would be a ‘future switch to the use
of sustainable / renewable gas supplies’ when this is not the case. So, simply because it
may not arise that hydrogen or biomethane can fuel the whole development, does not mean
it was unreasonable to take into account both the State’s policy commitments to hydrogen
and green methane and the stated willingness of the Notice Party to accommodate that if it
arises. That is different, for example, from a proposed development where a developer
states that they don’t intend to make provision for future proofing in this way.
114. Third, this point is somewhat more technical but the response is straight forward.
The Applicants say there will only be 3% biomethane in the gas system by 2030, not 18%.
However, even if correct, this does not have the legal effect the Applicant relies on. As the
Applicant itself points out, the shift to hydrogen or the increased mix percent of biomethane
is not certain and it was not relied on as certain by the Commission nor relied on as de facto
and certain reduction on emissions. The Notice Party expressly said in the AWN Report
(AWN Appeal Response, dated September 2022 (Appendix 3 of Appeal document) that (at
Section 1.23) ‘In order to be conservative, the predicted penetration of hydrogen and natural
gas with carbon capture has been ignored in these calculations (i.e. it has been assumed
that neither of these sources will be available.’
Developer’s Position
115. The Applicants’ argument attributes to the Inspector a finding that was not in fact
made. The Inspector did not conclude that the proposed development would be fuelled by
hydrogen at commencement, nor that renewable gas would be available in sufficient
quantities at any defined point. Rather, the Inspector recognised that the energy centre
was designed to be compatible with future renewable gas supplies as and when commercially
and physically available. That is materially different from finding that hydrogen would in
fact be deployed as a primary fuel source in the near term.
116. The Inspector’s conclusion that the development had the potential for positive
environmental impact over time was expressly framed in prospective and conditional terms.
It reflected adaptability and transition capacity, not guaranteed hydrogen deployment.
117. The Applicants rely on §13.3.3 of CAP 2023, which indicates that green hydrogen
will be prioritised for end-uses where direct electrification is not feasible. That provision
does not prohibit hydrogen use in electricity generation. Nor does it preclude co-location of
hydrogen-ready generation with large energy users. CAP 2023 is a strategic policy
document setting priorities and trajectories. It does not establish an enforceable statutory
rule barring hydrogen use for electricity generation in all contexts. The relevant question
under section 15 is whether the decision is consistent, in so far as practicable, with the CAP’s
overall objectives, not whether every possible future hydrogen allocation is resolved at
consent stage.
118. The Applicants also pray in aid §3.2 of the National Hydrogen Strategy, which notes
that hydrogen use by large electricity users is a ‘low priority end-use’ compared to direct
renewable electricity supply. A low priority designation is not a prohibition. The NHS
recognises that hydrogen will be required for system balancing, dispatchable generation,
and grid support functions. The proposed development’s generation is dispatchable and
located adjacent to demand. That is not inconsistent with the strategic framework.
119. The Applicants’ output arithmetic (70% efficiency × 45% generation = 31.5%) is a
policy argument. Even if accepted at its highest, such modelling does not transform CAP
2023 into a prohibition on hydrogen-ready generation. Furthermore, this is not pleaded in
the Statement of Grounds and cannot permissibly be advanced via a Statement of Case. In
any event, section 15 does not require the Commission to endorse or reject hydrogen based
on a developer’s hypothetical efficiency modelling. The Inspector was entitled to accept that
compatibility with renewable gas infrastructure supports long-term decarbonisation
potential, even if hydrogen remains nascent.
120. Moreover, the AWN modelling expressly assumed, conservatively, that hydrogen and
carbon capture would not be available up to 2030. The emissions assessment did not depend
on hydrogen penetration. The Applicants’ suggestion that the Board’s conclusion rested on
speculative hydrogen use is therefore incorrect on the record.
121. The Applicants’ multiplication exercise (offshore wind × intermittency × hydrogen
inefficiency), impermissibly deployed here for the first time, attempts to convert high-level
policy modelling into a project-specific prohibition. The Government Statement on the Role
of Data Centres is a strategic framework; it does not require the Commission to secure a
quantified like for like renewable installation at the planning stage.
122. The Commission was entitled to consider renewable procurement mechanisms,
energy flexibility, and system integration features as relevant factors. Section 15 does not
mandate that the Board calculate national renewable build-out requirements for each
individual development.
123. The Applicants contend that the developer relied upon an 18% biomethane mix
assumption for 2030 derived from Gas Networks Ireland material, rather than the 3%
referenced in CAP 2021. First, the modelling assumption was clearly identified as a scenario
and was not presented as a guaranteed outcome. Secondly, biomethane penetration is a
dynamic policy area reflected in evolving national strategies. The Board was entitled to
consider credible projections from relevant national infrastructure bodies. Thirdly, and
critically, the Board did not grant permission on the basis that biomethane would definitively
fuel the development. The Inspector recognised compatibility with renewable gas supply as
part of a transition pathway. That is an evaluative judgment grounded in the evidence
before the Board.
124. The Applicants’ submission that ‘there was no evidence’ to support biomethane-
related reductions overstates the position. There was evidence of projected biomethane
development, renewable gas integration strategies, and adaptive design readiness. Whether
the Applicants agree with that evidence is immaterial to legality.
125. The Applicants assert that the Commission ‘reached a conclusion that the proposed
development would be fuelled by biomethane’. That is not an accurate reading of the
Inspector’s report. The Inspector acknowledged renewable gas compatibility and the
potential for transition. There was no definitive finding that biomethane would supply the
energy centre at a specified level or date. To read the decision as making such a categorical
commitment is precisely the form of over-parsing cautioned against in Killymooney (No.1).
The decision must be read in the round. When so read, it reflects an acknowledgment of
present fossil-based operation with transitional adaptability; not a speculative assumption
presented as fact.
126. The Applicants’ argument effectively imposes a standard of technological certainty
and future fuel allocation proof at the date of consent. Section 15 does not require that level
of determinism. The statutory obligation is to perform functions in a manner consistent, in
so far as practicable, with the relevant climate instruments. The Inspector considered CAP
2023 and the wider climate policy framework. She assessed emissions on a conservative
basis and recognised ETS coverage. She evaluated mitigation and renewable procurement
and noted adaptability to renewable gas supply. That analysis falls within the lawful
spectrum of evaluative outcomes contemplated by the Supreme Court in Coolglass.
Disagreement with hydrogen prioritisation or biomethane penetration assumptions does not
convert a policy judgment into a justiciable legal defect.”
99. Again the applicants are conveniently misreading policy documents as giving rise to
mandatory requirements to refuse permission, whereas a proper reading of for example para. 13.3.3
of CAP23 allows flexibility.
100. Insofar as it is alleged that there is a lack of evidence that the proposed development would
be fuelled by biomethane, that is again a convenient misreading of the decision as over-promising
something, whereas in fact it is expressly phrased in merely potential terms. The possibility of future
use of biomethane was assessed as part of the EIA. That does not equate to the commission granting
permission on the basis of a bedrock premise that this would 100% certainly happen.
101. Any argument about percentages fails for similar reasons – biomethane use at particular
percentages were presented, as the notice party says, “as a scenario”, not as something guaranteed.
102. The problem with this ground overall is that it does not have regard to the range of lawful
approaches recognised in Coolglass. It erects a particular approach into a mandatory one contrary
to the Supreme Court’s decision. The correct question is whether the applicant has shown that the
range of lawful decisions was exceeded – the answer here is that they have not.
103. Overall the applicants are reading the decision as erroneous when a non-erroneous reading
is available. This is an instance of the general applicant’s fallacy that deems anything said by a
decision-taker to be ratio and fundamental to the reasoning, so any possible infirmity in anything
whatsoever results in a reflexive hand out for certiorari, normally accompanied by thundering
rhetoric about fundamental error and so on. A similar appellant’s fallacy deems everything said by
a trial judge to be part of the ratio and regards anything debatable as nullifying the whole decision.
This is another aspect of the point made by O’Donnell J. in Rooney v. Minister for Agriculture and
Food [2016] IESC 1 (Unreported, Supreme Court, 28 January 2016) at para. 3: “Some litigants, and
not just those who represent themselves, prefer the comfort of focusing exclusively on the debatable
ruling or judicial comment reinforcing a sense of grievance rather than recognise the forest of
problems in the overall case. The cycle continues and becomes almost a form of litigious perpetual
motion”.
Sub-grounds 22 to 32 (issue (f)) – 2015 Act overall emissions and ETS
104. The parties’ positions as recorded in the statement of case are summarised as follows:
“(f) The PDC will be one of the main sources of GHG emissions in the State when
operational/non-consistency with 2015 Act
Applicants’ Position
127. The projected PDC emissions will be almost 10% of the indicative projected
emissions ceiling for the electricity sector in 2030, leaving aside the fact that there is no
spare budget to allocate to new projects outside the framework of the climate action plans.
128. The PDC would be powered by continuously drawing 80MW from the national grid,
and by producing 120MW of electricity in natural gas powered generators. Back-up demand
is to be met through the use of 66 diesel generators.
129. Despite this, the initial EIAR submitted on behalf of the Notice Party, considered the
effect of the emissions from the PDC as ‘slight’; and the Notice Party response to the Appeals
characterised the effect of the emissions as either ‘Minor Adverse’ (Appendix 3, Table 6) or
‘Moderate Adverse’ (before mitigation) and ‘Minor Adverse’ (after mitigation) (Appendix 3,
Table 7). These conclusions in Table 6 appear to be based on the EU Emissions Trading
System (ETS).
130. As will be addressed further below, the conclusion of ‘minor adverse’ in Table 7 is
based on operation using renewable electricity through a power purchase agreement.
However, the Commission did not set a condition for such a renewables power purchase
agreement to create additional renewable electricity. In the circumstances, the PDC would
directly undermine decarbonisation of the electricity network, by diverting renewable
electricity to the PDC. Nor is reliance on Emissions Trading Scheme (‘ETS’). Neither the
Climate Action Plan 2021 nor the Climate Action Plan 2023 make reference to ETS in respect
of the national reduction targets for the electricity sector.
131. All development participating in the ETS, including the proposed development, must
comply with all EU ETS rules but this does not in any way imply that a development is
consistent with national climate action policy, as there is no mechanism within the ETS to
implement national targets. Operating within the ETS therefore did not exempt the
development from assessment of its impact on national GHG emissions as defined in the
Climate Act, and in Climate Action Plan 2023 or in any way ensure compliance with those
targets.
132. If the Commission and other public authorities were entitled to use the Climate
Action Plan 2023, in order to permit significant increases in GHG emissions, without any
mitigation, and without any recognition of the cumulative effects of such decisions, all
climate action plans would be fundamentally undermined and the national climate objective
would be rendered impossible.
Commission’s Position
133. Stating this is simply not enough to show that the Commission Decision is unlawful.
Insofar as this is the argument that says reliance on the ETS is unlawful, that is not correct.
The generation of power can create GHG, that much is well known. However, the ability to
actually do that is regulated by the ETS. This is the specific methodology designed and
adopted to specifically control emissions from power generation across the European Union
to specific levels with a set ‘cap’ on the GHG permitted.
134. In this respect, at a European level, the acceptability of emission levels from power
generation is dealt with, so insofar as the point is made in this case that the Commission
simply did not look enough at emissions arising from the power generation needed for the
PDC, that is addressed at the ETS level. In short, to borrow a phrase from the Court recently
in McGowan v An Coimisiún Pleanala [2025] IEHC 727 at [92], the Commission does not
have to reinvent the wheel each time when it comes to a contention not that the PDC itself
causes direct emissions, but that the power generation (i.e. those participating in the ETS)
will create too much emissions.
135. Interestingly, the Applicants say that CAP 2021 and 2023 take no cognisance of the
ETS. This is plainly wrong. Simply referring to CAP 2023, Section 13.1.1, 13.3.5 and Box
2.1 are to the contrary of this point a point which the Applicant made in the AWN report at
Section 3.17-18, 3.24 and which was accepted by the Inspector and Commission.
136. And further, nothing about the ETS demonstrates a lack of awareness of the relevant
national targets and ceilings, all of which were clearly dealt with the Notice Party in the AWN
Report, e.g. at Table 7. Those projected emissions were before the Inspector and were not
rejected or recalculated by the Board.
Developer’s Position
137. The Applicants proceeds on the erroneous premise that section 15 of the 2015 Act
imposes a project-level carbon ceiling or prohibits the grant of permission for emissions-
generating development of scale and makes the decisions in the present case unlawful. It
does not and Coolglass makes that clear. Section 15 requires a relevant body to perform
its functions, in so far as practicable, in a manner consistent with the matters therein
specified. As confirmed by the Supreme Court in Coolglass, it operates within the statutory
planning function and does not supplant or override it.
138. The ‘almost 10% of the electricity ceiling’ assertion is a modelling construct based
on worst-case operational assumptions. Neither the 2015 Act, CAP 2023 nor the Carbon
Budgets establish any mechanism requiring the Board to allocate portions of a sectoral
ceiling to individual projects. The Board was not required to conduct a sectoral arithmetic
exercise.
139. The development’s electricity-related emissions fall within the EU Emissions Trading
System (ETS). The Board was entitled to consider that regulatory architecture when
assessing magnitude and significance. CAP 2023 expressly recognises the ETS as a central
mechanism for emissions reduction in electricity generation and large industry.
Consideration of the ETS was lawful and relevant: see Coyne.
140. The characterisation of residual climate effects as ‘minor adverse’ post-mitigation
reflects the expert assessment contained in the EIAR and appeal documentation, undertaken
in accordance with accepted methodology. It was an evaluative scientific judgment. Judicial
review does not permit substitution of the Court’s view for that of the decision-maker.
141. The absence of a specific CPPA condition does not establish failure to require
mitigation. The Applicants are reading the permission in the most erroneous manner
possible. Commitments regarding corporate power purchase agreements and energy
efficiency measures formed part of the mitigation framework before the Board and are
secured through Condition 3. Section 15 does not mandate any particular mitigation
mechanism. It requires evaluative consistency with national climate instruments, not the
imposition of any specific contractual device. A holistic reading of the permission and the
planning application documentation, including the John Spain Associates appeal response
and its appendices make clear that the developer must enter into CPPAs.
142. The Applicants’ contention that reliance on the ETS is irrelevant because it does not
implement national targets is legally incorrect. Section 2 of the 2015 Act preserves the
State’s obligations under Directive 2003/87/EC. The Board was entitled to assess emissions
within the national and EU regulatory context.
143. The assertion that granting permission ‘fundamentally undermines’ climate policy is
rhetorical and does not identify any specific inconsistency with CAP 2023. CAP 2023 does
not prohibit new large electricity users and the Applicants haven’t so identified. The Board
considered climate policy, carbon budgets, sectoral ceilings, ETS regulation and mitigation
measures and was entitled to conclude that the development did not undermine the national
climate objective.
144. These are impermissible merits-based complaints to the Board’s planning
judgment.”
105. Insofar as concerns the emission trading system (ETS), the commission sets out some of
the context in submissions as follows (see by way of a summary of the system the EPA’s public
domain information at https://www.epa.ie/our-services/licensing/climate-change/eu-emissions-
trading-system-/):
“8. The Emissions Trading System (‘ETS’) is summarised in Coyne v An Bord Pleanála
[2023] IEHC 412 (inter alia, §117 et seq). In this case, Chapter 1 of the EIAR also addresses
same:
‘The EU is committed to achieving a reduction of greenhouse gas emissions; this is being
implemented by the EU Emissions Trading Directive (Directive 2003/87/EC). The EPA has
been given the responsibility for implementing the Emissions Trading Directive in Ireland.
The Directive establishes an allowance-trading scheme for emissions to promote reductions
of greenhouse gases, in particular carbon dioxide.’
9. The ETS is further explained in the Developer’s appeal submission to the Commission
(AWN Appeal Response, dated September 2022 (Appendix 3 of Appeal document), §1.4 et
seq), including insofar as same applies to the development and the GHG emissions
emanating from same:
‘…the energy generated and associated GHG emissions to serve the proposed development
will fall within the scope of the EU Emissions Trading System (ETS) either as a result of
electricity from the national grid (with diesel generators as an emergency measure) (for
Phase 1) or as a result of onsite generation of electrical power using gas generators (Phase
2 & 3) with all phases requiring a Greenhouse Gas Permit in order to operate…’ (§1.4)
‘The ETS is a “cap and trade” system where an EU-wide limit, or cap, is set for participating
installations. Thus, the geographical location of a given development within the EU is not
relevant as there is only one EU-wide target which is applicable to the ETS and thus the
cumulative direct and indirect climate assessment of relevance in this context is the GHG
emissions associated with the EU under the ETS. When viewed in this context, on an EU-
wide basis, where the ETS market in 2021 was approximately 1,307 million tonnes CO2eq,
the impact of the emissions from the proposed development, either from electricity
generation from the national grid or from onsite generation, will be less than 0.05% of the
total EU-wide ETS market. Thus, where there is a medium sensitivity environment and the
magnitude of impact of the project is small, this equates to a slight impact.’ (§1.10)
‘In terms of the specific references to CO2 emissions within the third party appeals, the
emissions associated the development (either directly or indirectly) will be within the ETS
mechanisms as outlined in Section 8.7.2.2 of the EIAR’ (§1.15)
10. The ETS is also expressly addressed in the CAP, which notes that ‘Emissions from
electricity generation and large industry in the ETS are subject to EU-wide targets which
require that emissions from these sectors be reduced by 43% by 2030, relative to 2005
levels…’ (Box 2.1). The CAP also refers to the ETS in the context of highlighting the central
role of carbon taxing to reduce GHG emissions (§11.2) and measures identified to deliver
on the sectoral emissions ceilings – for example, it is identified as a ‘measure’ to deliver
sectoral emissions ceilings in industry (§13.3 and §13.3.5).
11. The ETS is also identified in the Development Plan as an important component of
the EU Climate Framework ‘to enable progress on the mitigation of emissions’ (Chapter 2,
pg.26). The ETS thus informs the policy context relevant to the assessment of data centre
proposals – which policy acknowledges same as relevant to the mitigation of emissions.
12. Moreover, in the context of EIA, the Court outlined in Coyne v An Bord Pleanála
[2023] IEHC 412 that the ETS was a relevant consideration in the assessment of climate
impacts (§57):
‘Notably, by Annex IV of the EIA Directive and Schedule 6 PDR 2001 the description in an
EIAR shall take “into account the environmental protection objectives established at
European Union level or by a Member State of the European Union which are relevant to the
proposed development”. It follows that that the Board is entitled to take them into account
in EIA. It appears to me that this implies that it is permissible in EIA of a project to consider
schemes such as the Emissions Trading System described later in this judgment.’”
106. The commission highlights the following aspects of the inspector’s report:
“- Assessed the data centre development by reference to ‘local planning policy’ (pg.46
et seq), noting ‘the extensive plan-led approach to the zoning of the site at Toureen for data
centre uses, and I am satisfied that the proposed development is compatible with the zoning,
policies and objectives for this site’. In this respect, noting the requirements of Objective
CDP6.27, the Inspector outlined:
‘I note that the applicant has submitted all the required information under CDP6.27 and
ENT3 (TS9) for the site. This information will assist in the identification of potential impacts
on climate and the environment which will be assessed in the following sections of this report
(Planning Assessment, EIA & AA).’
Thus, the Inspector and the Commission were satisfied that the information presented
complied with the requirements of the Development Plan insofar as same allowed for the
assessment of potential impacts on climate.
- The Inspector proceeded to consider ‘compliance with climate change policies’
(pg.48 et seq), noting that third parties had raised issues with sectoral emissions reduction
and climate change targets. In this respect, the Inspector noted the balance to be struck
between ‘the supply of energy from the national grid which will be increasingly powered by
renewables in the future, and from the proposed on-site energy centre which would initially
be fuelled by natural gas from the nearby gas pipeline, and potentially by renewable gas
supplies in the near future’.
- The Inspector also outlined that as renewable energy sources increase, this will
balance out any short-term emissions arising from the data centre development – stating:
‘In relation to resultant CO2 emissions, the applicant has confirmed that the existing
electricity providers (to the national grid) form part of the EU-wide Emission Trading Scheme
(ETS). I am satisfied that any greenhouse gas emissions from these electricity generators
are not included when determining compliance with the targeted reductions in the non-ETS
sector, with no adverse impacts on the overall EU reduction targets anticipated.
Notwithstanding the anticipated demand for energy to serve the data centre project and
taking account of the EU-wide Emission Trading Scheme (ETS), I am satisfied that this issue
will be ultimately addressed as Ireland moves towards meeting its objective of providing
most of its energy from renewable sources by 2030 and beyond, in accordance with the
Climate Action Plan, 2023.’”
107. As regards the claim of irrelevance, the basic problem with that argument is that,
consistently with Coyne v. An Bord Pleanála [2023] IEHC 412 (Unreported, High Court, Holland J.,
21 July 2023), the ETS is obviously relevant at least to some aspects of climate assessment under
the 2015 Act, as a corner-stone of EU and national policy in this area. It is absurd to suggest that
such a primary climate instrument cannot be considered.
108. So being subject to ETS is relevant, but it is sufficient for the purposes of the 2015 Act?
109. The commission’s central position as noted above is that “insofar as the point is made in this
case that the Commission simply did not look enough at emissions arising from the power generation
needed for the PDC, that is addressed at the ETS level”.
110. While that is not an argument obviously without merit, I have to admit that unfortunately I
don’t find it quite as self-evidently immediately and unquestionably conclusive as the commission
does. The fact that Problem X is addressed by System A doesn’t automatically mean that there is
always going to be complete consistency with System B also, even if the latter recognises that the
former may be relevant in some respects. If all the commission had going for it was the ETS, then
the matter might need to be considered in further detail, albeit that the present case is pleaded
exclusively as a matter of domestic law in this respect.
111. But the commission also has other matters going for it, particularly (a) the developer’s
material quantifying emissions and (b) the agreement to CPPAs.
112. For the purposes of the 2015 Act, a conclusion regarding impacts must be viewed by
reference not to the gross emissions involved but the net impacts as conditioned, mitigated and
offset.
113. Conditions 1 and 3 must be read as requiring compliance with the documentation submitted,
including the requirement to enter into a CPPA. The lack of an express condition is irrelevant and
such a condition would be repetitive and superfluous given the general obligation under conditions
1 and 3, as discussed further below.
114. The underlying problem with the applicants’ categorisation of the project as causing
emissions is its misunderstanding that the lack of an express condition about CPPAs equates to a
lack of a condition arising from the documentation submitted. I deal with this further below.
115. Ultimately, the false premise of the applicants’ budgeting/ sectoral ceilings argument is the
failure to recognise that mitigation is conditioned.
116. In such circumstances the applicants have not demonstrated that the spectrum of
permissible options has been exceeded.
Sub-grounds 33 to 45 (issue (g)) – irrationality – positive effects
117. The parties’ positions as recorded in the statement of case are summarised as follows:
“(g) The finding of the Commission that the PDC could have potentially positive
environmental impacts is irrational and/or is contrary to the Climate Action Plan 2023
145. The Notice Party estimates the GHG emissions from the PDC being used at 80%
capacity at 292,704 tonnes of CO2 equivalent. This amounts to 0.87% of the national ceiling
for GHG emissions for 2030, from all sectors, or 9.8% of the ceiling for GHG emissions for
2030 in the electricity sector.
146. At full capacity, for which the Decision grants permission, GHG emissions from the
PDC amount to 1.1% of the national ceiling for GHG emissions for 2030, from all sectors, or
12.3% of the ceiling for GHG emissions for 2030 in the electricity sector.
147. The finding of the Commission that the PDC could have potentially positive
environmental impacts is irrational in respect of the effect of carbon emissions. Even if the
120MW of gas generated electricity were entirely powered by hydrogen from the start of its
operational phase, (something which is universally accepted as impossible), the PDC would
not result in a net reduction in national emissions and in that scenario would divert renewable
energy away from the decarbonisation of other sectors in the economy.
Commission’s Position
148. This has been dealt with above.
149. The Commission was not, on any fair reading relying on ‘the future switch to the use
of sustainable / renewable gas supplies’ as being a deal-breaker. It was an observation on
likely environmental effects that if that occurs, it is positive. Indeed, the positive impact is
described as ‘potentially’ positive and is part of the general notion that the PDC was informed
by decarbonisation agenda (as CAP 2023 requires).
Developer’s Position
150. Core Ground 2, pleads that the ‘Data Centre Decision is invalid in that the Board
acted irrationally, erred in law and/or failed to provide reasons and/or adequate reasons, in
finding that the PDC would have potentially positive environmental impacts, based on a
future switch to the use of sustainable/renewable gas supplies, which do not exist in
sufficient volumes’ (emphasis added). The Applicant has misdescribed the Reasons and
considerations of the Board in this regard. The basis for the Board’s finding ‘that the PDC
would have potentially positive environmental impacts’ was based on two factors (as
reflected in its wording on p.9 of the Decision), the first being ‘the undergrounding of the
existing overhead transmission cables’. In effect, what the Commission/Board was saying
was that there were elements or aspects of the project that would have ‘potentially positive
impacts’ rather than suggesting that the project would not have potentially negative impacts
on the environment arising from the emission of greenhouse gases.
151. The Applicants incorrectly characterise the Commission’s finding as one that the PDC
produces a net positive climate impact. That is not what the Decision states.
152. The Inspector’s reference to a ‘potentially positive environmental impact’ was
confined to the future capacity of the energy centre to transition to sustainable/renewable
gas supplies. It was expressly framed as contingent and prospective. It was not relied upon
as a determinative justification for the grant of permission.
153. The Commission did not find - nor was it required to find - that the PDC would result
in a net reduction in national GHG emissions. The EIA identified emissions impacts
transparently. The Decision records those impacts and assesses them within the statutory
framework, including the ETS, carbon budgets and sectoral ceilings.
154. The Applicants’ arithmetic does not establish irrationality. Magnitude alone does not
determine unlawfulness under s.15. Coolglass confirms that ‘consistency’ admits a range of
outcomes and does not require zero emissions or sectoral neutrality at project level.
155. The Applicants’ assertion that even a full hydrogen switch would divert renewables
from other sectors is speculative and not the basis of the Decision. The Commission did not
assume universal hydrogen fuelling. It noted only that future decarbonisation pathways
(hydrogen/biomethane readiness) could reduce lifecycle emissions if realised. CAP 2023
does not prohibit such future-proofing. Nor does the NHS preclude infrastructure being
hydrogen-ready. The Decision reflects alignment with national policy encouraging regulatory
frameworks for biomethane and hydrogen development.
156. Within the EIA, the ‘potentially positive’ reference sits alongside identified adverse
effects and mitigation measures. It is one factor in a multi-factor environmental assessment.
It is not irrational to recognise that technological flexibility consistent with national
decarbonisation strategy may carry prospective environmental benefit.”
118. The problem with this argument is that the applicants have not shown that the decision is
irrational. The applicants are reading the decision as invalid and nonsensical where a valid and
sensible reading is available. The decision can readily be construed in a manner that avoids the
alleged or any irrationality, as the opposing parties submit. This point fails by analogy with the
biomethane point above, and it is unnecessary to repeat that discussion which applies mutatis
mutandis.
Sub-grounds 46 to 55 (issue (h)) – irrationality – reliance on PAS 2050
119. The parties’ positions as recorded in the statement of case are summarised as follows:
“(h) The Commission’s reliance on the PAS 2050 is irrational
Applicants’ Position
157. PAS 2050 allows businesses to disregard a source of GHG in one of their products,
if it accounts for less than 1% of the emissions of that product, so long as various other
conditions are met.
158. The Notice Party has used this exemption and applied it to national emissions, in
order to determine that the PDC would have a minor adverse impact on the national level
(Table 6). This analysis was accepted by the Inspector and Commission. A number of clear
errors apply to this analysis.
159. PAS 2050 does not apply to national emissions. It is a specification for the
assessment of life cycle emissions of goods and services. The PDC is neither. It is used for
the analysis of the climate effect of individual products. The exemption applies to elements
of a product which represent less than 1% of the GHG emissions of that product.
160. Secondly, the calculations are based on the use of the PDC at 80% capacity, rather
than at 100% capacity, for which the Decision grants permission. If calculations were based
on the use of the PDC at the full level permitted by the Decision, the (nonsensical) 1%
threshold would be breached and a significant adverse impact would be found.
161. Thirdly, even if PAS 2050 were to apply, it does not allow for mitigation or offsetting
before analysing whether a contribution comes below the 1% threshold. The Notice Party is
clear that the PDC breaches the 1% threshold, prior to proposed mitigation measures. As
such those GHG emissions cannot be discounted as minor under PAS 2050.
162. The Commission, relied on this irrational application of the PAS 2050 to find the PDC
would have a minor adverse impact. This fatally undermines the environmental analysis of
the PDC.
Commission’s Position
163. The point appears to be that the Commission is said, effectively, to have been misled
by an approach (PAS 2050). In essence, that document offers a view as to how one can
understand a carbon footprint of any given product, at least in terms of GHG. That standard
says, in effect, in calculating a footprint, one can exclude the contributions from parts of the
footprint that make up less than 1% of the anticipated life cycle GHG emissions associated
with the product in question. In essence, for that sort of analysis, it says less than 1%
contribution to an overall footprint can be excluded in reckoning up that footprint – i.e. see
per page 13, that one considers ‘all sources of emissions anticipated to make a material
contribution (more than 1%) to the life cycle GHG emissions of the functional unit.
164. So, the case goes, if the Notice Party presented the view that it was under the 1%,
then it was attempting to argue that this de jure meant it was acceptable under a standard
which does not apply, which the Commission must have accepted.
165. The Notice Party has explained why it was dealing with PAS 2050 and they say it
was because Mr. Doyle had positively argued that the approach in the EIAR was wrong and
that the approach which had been taken to the Shannon Technology and Energy Park
(‘STEP’) was to be preferred. That approach, however, had used the PAS 2050 to reason by
analogy that ‘that where emissions were greater than 1% of Irish GHG emissions then the
impact of the proposed development would be considered as of major adverse significance’
(see as explained in Section 1.17 of the AWN Report). Thus, the approach taken in the STEP
application was set out at Section 1.17 and 1.18 which involved (in that application) a view
being urged that a magnitude should be viewed as ‘high’ when emissions exceed 1% of the
Irish GHG inventory in the year they arise and ‘low’ when its less than 1%.
166. The Notice Party then, in Table 4 set out the expected values in emission tons and
then set out the relevant percent contributions to targets, ceilings and the ETS cap in Table
5. Save, of course, through their point about 80% versus 100%, none of this is challenged.
So, what is perfectly clear is whereas PAS 2050 may, for a very different type of analysis,
give one a 1% test basis, the actual percentages are set out and there is no evidence that
the Commission determined that any sub 1% aspect of this in terms of national targets,
meant it was prima facie acceptable. Indeed, PAS 2050 is not referred by the Inspector and
where the Notice Party (see Section 1.27 in the AWN Report) entered into an ‘Assessment
of Significance’ it did not apply the ‘high’ and ‘low’ approach apparently based on PAS 2050
in the STEPS application, but applied IEMA Guidance from 2022 in modelling what they
described as minor adverse effects.
167. The point here is that the percents of involvement are set out which are correct, and
insofar as 100% required to be understood, was clearly understandable by basic maths, and
for detailed substantive reasons a characterisation of that impact is offered in Table 6 and
7. There is simply no basis to the case that the Commission has somehow adopted an
approach which de jure says anything below 1% is automatically acceptable nor could it
because it's beyond any doubt at all (see Table 7) that more than 1% of the 2030 ceiling is
taken by the development even on the 80% basis.
Developer’s Position
168. The Applicants’ case proceeds on a false premise: that the Commission treated PAS
2050 as legally determinative of acceptability or as establishing a binding ‘1% rule’ for
national emissions. It did not. PAS 2050 was referenced in the AWN appeal response in
order to address an argument previously advanced by the Applicants in another case (STEP)
where a 1% threshold had been used by analogy. It was not relied upon as a statutory
test, nor as a legal basis governing national emissions assessment.
169. The Commission did not apply PAS 2050 to national emissions ceilings.
170. The Applicants contend that PAS 2050 cannot apply to national emissions; yet if
applied at 100% capacity, the 1% threshold would be breached. However, Table 7 in the
AWN appeal response makes clear that even on the 80% operational basis, the development
exceeds 1% of the electricity sector ceiling. It was therefore not ‘discounted’ on the basis
that it fell below 1%. The premise of concealment or exclusion is factually wrong.
171. The 80% utilisation assumption reflects realistic operational modelling and was
transparently explained.
172. Planning permission does not require modelling based on theoretical maximum
instantaneous output where evidence demonstrates phased ramp-up and typical load
factors. The Inspector was entitled to accept the evidence presented. In any event, the
100% figure is arithmetically obvious and was readily inferable.
173. The Applicants assert that PAS 2050 prohibits mitigation being considered before
applying a 1% threshold. That misunderstands both the role of PAS 2050 and the EIA
process. Significance in EIA is routinely assessed pre-mitigation; and post-mitigation. That
is normal practice. The Inspector assessed impacts before and after mitigation. There is
nothing irrational in that approach.
174. Even if PAS 2050 were misapplied (which is denied), that would not render the
Decision unlawful unless the Commission adopted it as a binding legal standard (which it
didn’t) or the assessment materially depended on a legally impermissible threshold.
120. PAS 2050 is the British Standards Institution (BSI) Publicly Available Specification (PAS)
2050:2011, Specification for the assessment of the life cycle greenhouse gas emissions of goods
and services, 30 September 2011. It is a form of industry standard, albeit that in any scientific
discipline there is normally room for debate about the value, relevance, exact meaning and correct
use of standards. But any argument ambitiously claiming that a public body erred by considering
an industry standard starts from a fairly major implausibility on its face.
121. The overall problem with this ground is that the applicants have not demonstrated that the
commission’s approach falls outside the range of permissible options that constitute compatibility
with 2015 Act considerations. This point is going nowhere in the light of Coolglass.
122. The more specific problem was that the reliance on PAS 2050 did not have the effect that
relevant information was ignored and overlooked. The information was put before the commission,
even if not presented as the applicants say they would have preferred.
Sub-grounds 56 to 66 (issue (i)) – lack of mitigation – CPPAs
123. The parties’ positions as recorded in the statement of case are summarised as follows:
“(i) Failure to ensure mitigation of GHG emissions.
Applicants’ Position
175. It is a standalone obligation under Section 15(1)(e), that the Commission ensure:
i. The mitigation of GHG resulting from its decision
ii. That its decisions (including any mitigation measures) do not run contrary to national
policies for mitigation of GHG.
176. In its response to the first Applicant’s appeal to the Commission, the Notice Party,
in order to mitigate the negative climate effect of the PDC, indicated (Response, p.13, para
4.4.8) that it was willing to accept a condition on the grant of permission, which would
require the Notice Party to enter a Corporate Power Purchasing Agreement (CPPA) for the
purchase of renewable energy equal to the power use of the PDC. ‘3.23 III. … the applicant
has confirmed that they would accept a condition on any grant of permission by the Board,
requiring the submission of details to the Planning Authority prior to the operation of
development, confirming that a CPPA has been entered into in respect of the proposed
development.’
177. The Notice Party presumed a CPPA condition would be imposed in its analysis. At
1.37 in the September 2022 submission: ‘Also presented in Table 7 is the impact post
mitigation. As outlined above the project will use “best practice” adaptive design measures
(solar panels, vertical farm, facilitating district heating) and by using long term power
purchase agreements. With the implementation of these measures the impact of the
proposed project … is reduced to a minor adverse, non-significant impact.’
178. However, there is no requirement that the CPPA in question requires additionality of
renewables which would not otherwise occur, which is equal to the energy to be used by
that data centre and which is not otherwise subsidised by government.
179. In fact, despite the suggestion of a condition by the Notice Party requiring a CPPA
and the reliance of the Notice Party of such a condition to find that the PDC would have a
minor adverse climate effect, the Decision does not place any condition requiring a CPPA to
provide additional renewable energy on the Notice Party. This can be seen from the
documentation submitted to the Commission, pointing to wind farms which were already at
various stages of the planning process, in other words not only are they not ‘additional’, they
are not even ‘new’.
180. The absence of such a condition fundamentally undermines the analysis of the Notice
Party, the Inspector and the Commission, though it must be noted that such a condition
could not, in any event, make the granting of permission for the PDC consistent with the
Climate Action Plan 2023.
181. As such, where, on every analysis, the GHG emissions from the PDC will not be
mitigated by the Commission’s Decision, the Commission has failed to perform its functions
in a manner consistent with the objective of mitigating greenhouse gas emissions in the
State, as required by 15(1)(e). The Commission has offered no evidence of how it was not
practicable to do so. As such the Decision is in breach of its obligations under 15(1)(e).
Commission’s Position
182. This is the CPPA point but now they say one must have one that requires additional
renewable energy. The additionality point has been dealt with above.
183. As to the CPPA the Notice Party specifically sought to ‘mitigate’ greenhouse gas
emissions in the ways described in Section 3.23. One of the manners proposed as mitigation
was that the immediate energy need (i.e. Phase 1) would be offset and that there is ‘there
is potential for CPPAs to offset the entire energy usage of the proposed development.’ The
Notice Party said:
‘Additionally, as set out within the JSA response document, the applicant has confirmed that
they would accept a condition on any grant of permission by the Board, requiring the
submission of details to the Planning Authority prior to the operation of development,
confirming that a CPPA has been entered into in respect of the proposed development.’
184. So, the Notice Party proposed this and did not, for example, outline any particular
difficulties or explain any reasons why this could not be done. And, they proposed this by
way of mitigation.
185. Condition 3 requires the mitigation. Condition 1 requires the development to be as
proposed. It is a requirement of the development consent that, in fact, the draw is offset
and the Commission relies on Fahybeg Windfarm Opposition Group v An Bord Pleanála
[2025] IEHC 310 (§43) and Rural Residents (No.1) [2025] IEHC 600 at §88-95 here in terms
of construction of the Decision.
186. This point sub-tends a lot of the Applicant’s case and insofar as the Applicant’s
concern is that this was not required, the Commission says it is, and the Notice Party indeed
offered it. In real terms, this should meet any concerns the Applicants have.
Developer’s Position
187. Section 15(1)(e) does not impose a project-level obligation to eliminate or fully
offset emissions, nor does it require ‘additional’ renewable generation. The statutory test is
whether the Commission acted consistently, insofar as practicable, with national mitigation
policy. It is not a net-zero requirement for individual developments.
188. The Notice Party expressly proposed mitigation measures, including phased
development and ramp-up, adaptive design (solar PV, district heating facilitation, vertical
farming) and long-term CPPAs to offset operational demand. The CPPA proposal was clearly
before the Commission and formed part of the environmental assessment.
189. The Applicants’ argument rests on the assertion that no CPPA requirement forms
part of the permission. That is incorrect as a matter of construction because Condition 1
requires the development to be carried out in accordance with the documentation before the
Board and Condition 3 requires implementation of mitigation measures and the CPPA
commitment was expressly advanced as mitigation.
190. On orthodox principles of construction (see Fahybeg Windfarm Opposition Group
[2025] IEHC 310; Rural Residents (No.1) [2025] IEHC 600), the permission must be read
as a whole and in light of the material before the decision-maker. The mitigation
commitments form part of the permitted scheme.
191. The Applicants introduce a new gloss that that any CPPA must secure additional
renewable generation not otherwise occurring. But there is no requirement in s.15 for
‘additionality’ in that sense and no mandatory CAP 2023 provision requiring project-specific
renewable surplus. There is no legal basis converting a policy aspiration into a binding
precondition. CAP 2023 speaks to energy matching and system decarbonisation at sectoral
level. It does not mandate that every large user create net new renewable capacity equal
to its draw.
192. The Applicants’ real complaint is that a high-emitting development cannot be
permitted unless it is rendered net-neutral or additional-renewable-positive. That is not the
law.
193. The Applicants introduce an ‘additionality’ requirement not found in s.15 or CAP
2023. There is no statutory or policy obligation that a data centre must generate renewable
capacity surplus to its own demand. CAP 2023 addresses sectoral decarbonisation, not
project-specific renewable surplus.”
124. CPPAs are addressed in the government statement:
“A corporate power purchase agreements (CPPA) is an arrangement whereby renewable
electricity is procured through a direct contractual agreement with a renewable electricity
generator. CPPAs have a role to play in decarbonising the electricity sector and ensuring
demand growth from large energy users, such as data centres, reduces the cost of reaching
renewable energy targets. Outside of the Renewable Electricity Support Scheme (RESS), a
number of CPPAs have been executed by data centres in Ireland in recent years to finance
renewable electricity generation projects. Data centre operators purchasing CPPAs that add
additional renewables, and use our electricity grid efficiently, can play a positive role in
Ireland’s renewable energy transformation. However, the location of data centre demand
in proximity to renewable generation will be key to this objective.”
125. The main problem with this ground is that the 2015 Act doesn’t require refusal of
developments that have gross GHG emissions. It is well within the range of options open to a
decision-taker to alternatively have regard to net emissions. The notice party is expressly accepting
that the conditions require CPPAs which means that the project will be powered by renewables.
Much of the applicants’ argument ignores this premise.
126. Insofar as concerns the question of whether the commission erred in conditioning CPPAs (via
the general conditions that the development must be in accordance with the documentation
submitted) without ensuring that the renewable energy would be additional to existing or stimulated
further demand, these are not pleaded points.
127. The essential point that a general condition about compliance with particulars encompasses
specific requirements in particular documents is not in doubt. As the Court of Appeal put it in Kelly
Dunne & Ors v. Guessford Limited [2022] IECA 223 (Unreported, Court of Appeal, Costello J., 14
October 2022) at 64:
“Where, as here, the grant incorporates by reference the plans and particulars lodged with
it, then the grant of planning permission must be construed by reference not only to the
contents of the grant of planning permission but also to the application and the plans lodged.
In determining the proper scope of the permission, it is the combined effect of the permission
and the documents incorporated by reference which must be looked at...”
128. I took a similar approach in Fahybeg Windfarm Opposition Group v. An Bord Pleanála [2025]
IEHC 310 (Unreported, High Court, 30 May 2025) at §43 and Rural Residents v. An Coimisiún
Pleanála (No. 1) [2025] IEHC 600 (Unreported, High Court, 6 November 2025) at §88-95, including
by way of a recital in the order clarifying matters if appropriate, on the clear basis that such a recital
does not give rise to a right to costs that would not otherwise exist.
129. Conditions 1 and 3 provide:
“Conditions
1. The proposed development shall be carried out and completed in accordance with
the plans and particulars lodged with the application, as amended by the further plans and
particulars received by the planning authority on the 25th day of February, 2022, the 10th
day of June, 2022 and by An Bord Pleanala on the 26th day of September, 2022, except as
may otherwise be required in order to comply with the following conditions. Where such
conditions require details to be agreed with the planning authority, the developer shall agree
such details in writing with the planning authority prior to commencement of development
and the proposed development shall be carried out and completed in accordance with the
agreed particulars.
Reason: In the interest of clarity.
3. The mitigation measures identified in the Environmental Impact Assessment Report,
the Natura Impact Statement and other plans and particulars submitted with the planning
application and appeal shall be implemented in full by the developer, except as may
otherwise be required in order to comply with the conditions of this permission.
Reason: In the interest of clarity and the protection of the environment during the
construction and operational phases of the proposed development.”
130. These clearly have the effect that the development is conditioned in accordance with the
documentation submitted with the application. This includes the agreement to a condition requiring
CPPAs as set out in para. 4.48 of the John Spain Associates response document. The absence of an
express condition doesn’t nullify that.
131. This is such a central point that it shouldn’t be open to even unreasonable doubt, so I am
going to include a recital in the order to clarify it. That does not create any costs implications that
would not otherwise exist.
132. The pleaded claim that conditions 1 and 3 couldn’t have the effect of rendering the grant of
permission consistent with the matters referred to in s. 15, when viewed in the light of what was
put before the decision-taker, misunderstands the correct procedure and the spectrum of options as
set out in Coolglass.
Sub-grounds 67 to 71 (issue (j)) – reasons
133. The parties’ positions as recorded in the statement of case are summarised as follows:
“(j) Failure to provide reasons and failure to take account of submissions
194. The first named Applicant drew the attention of the Commission to the flawed and
inaccurate nature of the information provided by the Notice Party, in an extremely detailed
further submission. Dr. Doyle holds a BA (mod) in Physics, an MSc in Physics, a Postgraduate
Diploma in Environmental Pollution, and a PhD in Climate Science. He has over twenty-five
years of experience in environmental science in Ireland, including consultancy in the
preparation of environmental impact assessments and emissions monitoring for a wide range
of industrial and commercial projects.
195. The following is a brief summary of the submission:
a) Critique of Environmental Impact Assessment (EIAR)
b) Failure to Address National Climate Targets
c) Misapplication of Assessment Standards
d) Inadequate Mitigation Measures
e) Unrealistic Assumptions on Renewable Energy and Biomethane
f) Impact on National Emissions and Renewable Targets
g) Contravention of Local Development Plan Objectives
h) Lack of Additionality in Renewable Energy Sourcing
196. Regarding further submissions from the appellants, the Inspector stated at p. 41:
‘The responses did not raise any new issues of substance.’
197. It is impossible to reconcile dismissal of the second submission of the first named
Applicant with the obligation of the Commission to perform its functions consistently with
the 2015 Act. Evident new issues of substance in the submission included a detailed critique
of the completely new climate assessment presented in the developer’s Appendix 3,
identification of serious new errors in the developer’s assessment, and fundamental flaws in
the claimed mitigation. The Commission was required, in order to demonstrate its obligation
of consistency with the 2015 Act, to engage with and address such an expert submission
critiquing the material placed before the Commission by the developer concerning the
matters upon which the Commission were required to be consistent with under the 2015
Act.
Commission’s Position
198. Reasons to the appropriate standard were given. This will be for the Court to
ascertain and the law is well known. Further, whereas the Inspector said responses did not
raise any new issues of substance, the key word here against the backdrop of what came
before is ‘new’. If the Court examines the extent of the information and submission during
the planning authority stage and on appeal, it can be seen that very clearly the issues were
joined. Indeed, the Applicants brought an Appeal to the Commission and the Notice Party
prepared a response to same and the Applicants were given a chance to respond to that.
There were no ‘new issues’ of substance. That does not mean the issues were not of
substance, but there was nothing new. There were responses and argument about the
points, but it is completely reasonable to have said nothing new in the context of the file
arose at this point.
199. Further, it is not correct that s.15 requires the Court to apply a standard requiring
issue by issue treatise of the submissions. Once the law on reasons is satisfied (and it was)
that suffices.
Developer’s Position
200. The applicable standard on reasons is well established. The decision must enable
the parties and the Court to understand what was decided and why it was decided: see
Connelly. There is no obligation to produce a point-by-point rebuttal of each submission,
nor to engage in an ‘issue-by-issue treatise’. Section 15 does not elevate the standard of
reasons beyond orthodox administrative law principles.
201. The Inspector’s statement that the further submissions raised ‘no new issues of
substance’ must be read in context. The key word is ‘new’. The climate issues were raised
at planning authority stage and advanced on appeal. They were responded to by the Notice
Party and replied to by the Applicants. The debate was already fully joined. The further
submission elaborated on existing arguments; it did not introduce a distinct, legally novel
issue requiring fresh analysis.
202. The qualifications of Dr. Doyle are not in issue. However, the weight to be afforded
to competing expert views is a matter for the decision-maker. The existence of a detailed
critique does not require a line-by-line rebuttal. The Commission was entitled to prefer the
EIAR and associated material before it.
203. The Applicants assert that consistency with the 2015 Act required express
engagement with each alleged flaw in Appendix 3. That is incorrect. The Board recorded
that it had regard to CAP 2023 and the Climate Act 2021 (which amended section 15(1)).
It assessed emissions and mitigation and reached a reasoned planning conclusion. Section
15 does not require a separate analytical appendix demonstrating mathematical
reconciliation with national targets.
204. There is no evidence that the submission was ignored. The Inspector expressly
referred to it. The fact that she concluded it raised nothing new does not equate to failure
to consider it. At its height, this ground amounts to disagreement with the weight afforded
to the Applicants’ critique. That is not a failure of reasons.”
134. We need to put the complaint about the response Dr Doyle’s submission in context.
135. The applicants have another try at litigation-by-snippet, and read the “no new issues”
comment as being a dismissal of major points of substance. But that is a grotesque misreading.
136. Section 6.0 of the inspector’s report deals with the appeals and responses, under the
following headings:
(i) 6.1 Third party appeals;
(ii) 6.2 Planning authority response No. 1 (to third parties);
(iii) 6.3 Applicant (for permission) response to third party appeals;
(iv) 6.4 Planning authority response No. 2 (to first party response); and
(v) 6.5 Further correspondence, described as “Further submissions were received from
the following Prescribed Bodies, Groups and individuals in relation to the Applicant’s
response to the grounds of appeal and the submission of additional technical
reports”.
137. By the time we get to stage (v) (which is where Dr Doyle’s allegedly trivialised document
comes in), the inspector has already set out 16 pages of summary of issues raised. Put in that
context, all she means by saying there are no new issues of substance is that the issues raised come
in under one or more headings already set out in the previous 16 pages.
138. The basic reason why this point fails is that the applicants are reading the decision in a way
that renders it unreasonable and invalid. But a valid reading is available – indeed a valid reading is
the obvious reading. What she means is that the points made in the fifth round of material come
within the headings (listed at enormous length) of issues raised in the first four rounds. There are
no new headings of substance that warrant a 17th page of points – it is screamingly obvious that
that’s what she means by no new issues of substance.
139. The applicants have not demonstrated that the commission acted unreasonably in that
regard or failed to give the main reasons on the main issues having regard to the law in that respect.
Sub-grounds 72 to 76 (issue (b) – irrationality regarding government statement
140. The parties’ positions as recorded in the statement of case are summarised as follows:
“(b) Failure to perform functions in a manner consistent with the 2015 Act
Applicants’ Position
20. Per the approach of the Supreme Court in Coolglass, planning permission for a
development that generates substantial GHG emissions and relies primarily on fossil fuels
cannot be regarded as consistent with the CAP in the absence of a clear demonstration by
the Commission of how consistency is achieved; or alternatively, a clear demonstration by
the Commission of why consistency was not practicable.
21. The Commission’s Inspector failed to make any determination as to what the actual
emissions from the proposed data centre (‘PDC’) would be. This failure is fatal to the legality
of the Decision. The Commission and Inspector cannot possibly demonstrate that the
Decision falls within the range of options that are consistent with Section 15(1) objectives
unless they first determine what the emissions actually are.
22. At full capacity, for which the Decision grants permission, GHG emissions from the
PDC would amount to 1.1% of the national ceiling for GHG emissions for 2030 from all
sectors, or 12.3% of the ceiling for GHG emissions for 2030 in the electricity sector. The
failure to determine actual emissions, in the face of such significant projected figures,
demonstrates that the Commission failed to conduct the analysis necessary to establish that
the Decision was within the range of options available to it.
23. Furthermore, even if it were sufficient, the proposed development is not consistent
with the Government Statement on the Role of Data Centres in Ireland – for example, the
Government Statement requires that developments ‘should provide clear additionality in
renewable energy delivery in Ireland’. Contrary to that principle, the Decision does not
require any additionality of renewables, nor any condition requiring a Corporate Power
Purchase Agreement that would create additional renewable energy.
24. The 2023 CAP says ‘In the short- and medium-term, new demand growth from large
energy users, such as data centres, will have to be moderated to protect security of supply
and ensure consistency with the carbon budget programme’. This was not addressed or
achieved by the Commission.
25. Nor is the Clare County Development Plan of any assistance to the Commission –
Objective CDP6.27 requires precisely the calculation of emissions, which is absent. The
Development Plan therefore explicitly contemplates that the assessment of climate impacts
and Section 15 compliance must be undertaken at the planning application stage for this
specific site. The presumption identified in Coolglass – that compliance with the
development plan will itself be compliant with the Section 15(1) duty – simply cannot apply
where the development plan itself requires an analysis of GHG emissions and climate impacts
to be undertaken at the application stage.
Commission’s Position
26. There are four separate arguments made here. To frame the Commissions reply,
they are set out with the Commission’s reply thereunder.
27. However, as a preliminary statement of the Commission’s position, the Commission
did not fail to act in a manner consistent with, in so far as practicable, s.15 of the 2015 Act
– including by reference to the CAP. The Applicants’ various contentions in this regard,
including by reference to the CAP, the Government’s Statement on the Role of Data Centres
in Enterprise Strategy (July 2022) and the Development Plan, are premised on a failure to
properly understand and apply the rationale of the Supreme Court in Coolglass to this case
and on a failure to acknowledge that the approach to the assessment of GHG emissions in
this case was one which was lawful and one which the Commission was entitled to accept.
As outlined in Coolglass, climate considerations are already woven into the planning process
– through, for example, existing policies and objectives, such as those contained in a
development plan. In this respect, the Supreme Court outlined (§112):
‘It follows that a planning authority is entitled to approach its task on a presumption
that any strategy or development plan adopted is consistent with climate objectives,
and that any decision consistent with such a plan and strategy will itself be consistent with
those objectives, and therefore in compliance with s. 15(1). That is so particularly having
regard to the range of outcomes implied by the concepts of consistency, and practicability.’
28. In this case there is no pleaded complaint that conformity with the Development
Plan is insufficient to achieve compliance with the requirements of s.15 of the 2015 Act –
this is noteworthy in circumstances where the Council, the Inspector and the Commission
all considered, in light of the evidence presented, that the development was in conformity
with the objectives in the Development Plan (which objectives expressly support the
development of a data centre).
29. As to the specific points set out by the Applicant:-
30. First, their case is stark and clear – ‘planning permission for a development that
generates substantial GHG emissions and relies primarily on fossil fuels cannot be regarded
as consistent with the CAP in the absence of a clear demonstration by the Commission of
how consistency is achieved; or alternatively, a clear demonstration by the Commission of
why consistency was not practicable’.
31. In reply, it is largely impossible to engage on the merits with the Applicants as the
premise of the case is simply that CAP23 is preclusive of the development because of how
the Applicant characterizes both the policy context and the process before ACP. Consistency
within the meaning of what is required as set out in Coolglass was demonstrated, permission
was granted, and the Inspector’s Report and Decision read in light of the material before the
Commission demonstrate this.
32. Second, they say the Commission’s Inspector failed to make any determination as
to what the actual emissions from the proposed data centre (‘PDC’) would be. This failure,
they say, is fatal to the legality of the Decision given.
33. In reply to this point, the Commission says this is effectively a species of a point
rejected many, many times by the Irish Courts. There is no case even made that the Notice
Party did not set out the actual emissions from the proposed development. They did in very
clear terms in (just to take one source) the AWN Report at, inter alia, Tables 6 and 7.
Neither the Inspector nor ACP disagreed over the projected emissions, all of which were
described and understood. The Inspector and ACP here clearly accepted the Notice Party’s
information and there is no need for ACP (on pain of a finding of non-
compliance/inconsistency with s.15) to recite that which it is accepting as a description of
the proposed development which it is assessing.
34. Third, they say ‘the proposed development is not consistent with the Government
Statement on the Role of Data Centres in Ireland – for example, the Government Statement
requires that developments “should provide clear additionality in renewable energy delivery
in Ireland”.’
35. In reply, even assuming that the Government Statement of the Role of Data Centre’s
in Ireland’s Enterprise Strategy requires a data centre development to offer ‘more’ renewable
energy back than the draw it will take, CAP 23 (as the Applicant itself says and relies on per
Section 12.1.3) speaks about energy matching not ‘additionality’ in the sense the Applicant
uses it here. Obviously, the Court will take into account the response to the CPPA point
made below, but in accordance with Coolglass, it is not just legally correct to read the
reference in CAP23 to the Government Statement of the Role of Data Centre’s in Ireland’s
Enterprise Strategy as mandating a CAP23 requirement that more-than-use is required. In
any event, insofar as the Applicant says the Government Statement of the Role of Data
Centre’s in Ireland’s Enterprise Strategy requires more-than-use, the concept of
‘additionality’ described therein refers to that arising ‘proportionate’ to the impact of energy
demand and can include repowering. The consistent reading of both policies together
indicates that the Government Statement of the Role of Data Centre’s in Ireland’s Enterprise
Strategy is speaking of matching impact, not requiring a more-than-use approach. In any
event, all of this is sub-tended by the Applicants’ case about CPPAs which is dealt with below.
36. Fourth, they say ‘the 2023 CAP says “In the short- and medium-term, new demand
growth from large energy users, such as data centres, will have to be moderated to protect
security of supply and ensure consistency with the carbon budget programme”. They
contend this was not addressed or achieved by the Commission.’
37. As to this, this is clearly a point in CAP23 taken into account in the preparation of
the CDP which carefully (in line with the Government Statement of the Role of Data Centre’s
in Ireland’s Enterprise Strategy) adopted a plan led approach to data centre development.
In any event, in terms of moderation of impact, this is built-into the development. It is
phased and no effort has been made by the Applicant to explain in its pleadings, submissions
or statement of case, how this aspect of CAP23 is said to be offended save citation at the
most generic level.
Developer’s Position
38. The Applicants’ submission that planning permission for a development generating
substantial greenhouse gas emissions ‘cannot be regarded as consistent with the CAP in the
absence of a clear demonstration of how consistency is achieved’ misstates both the
statutory test and the Supreme Court’s approach in Coolglass.
39. Section 15(1) does not impose a requirement that the Commission prove positive
consistency by way of quantified reconciliation against national ceilings, nor does it require
an express statement explaining why consistency was “not practicable”. The statutory
obligation is to perform the function in a manner consistent, in so far as practicable, with
the specified instruments. As the Supreme Court made clear in Coolglass, the Court’s task
is to determine whether the impugned decision falls within the “spectrum of possible
outcomes” that could lawfully be regarded as consistent (§78), not to require the decision-
maker to demonstrate mathematical alignment with national carbon budgets at project level.
40. The Applicants’ argument effectively converts section 15 into a project-level carbon
allocation regime. That is not what the Oireachtas enacted. Carbon budgets and sectoral
ceilings operate at national and sectoral level and are implemented through a suite of policy
measures. They are not transformed by section 15 into enforceable numerical caps
applicable to individual planning applications.
Alleged Failure to Determine ‘Actual Emissions’
41. The contention that the Inspector failed to determine projected operational
emissions does not reflect the record. The EIAR quantified projected operational emissions,
including worst-case scenarios. The AWN assessment (Appendix 3 to the appeal response)
modelled emissions on a conservative basis and expressly stated that hydrogen penetration
was not assumed in the calculations. The emissions figures relied upon by the Applicants
themselves are derived from the material before the Board. It is therefore untenable to
suggest that emissions were not determined.
42. What the Inspector did not do – because she was not required to do so – was to
treat those quantified emissions as a dispositive legal threshold. The assessment addressed:
(a) the projected emissions;
(b) the regulatory context, including EU ETS coverage;
(c) mitigation and efficiency measures;
(d) the adaptive capacity of the energy centre; and
(e) the broader planning and policy framework.
43. The Applicants’ reliance on the figures of ‘1.1% of the national ceiling’ or ‘12.3% of
the electricity sector ceiling’ illustrates the difficulty with their case. These percentages are
not statutory limits. Section 15 does not require the refusal of any development exceeding
a particular percentage of a sectoral ceiling. The statutory question remains whether the
grant of permission is consistent, in so far as practicable, with the CAP and the national
climate objective. The Inspector’s structured assessment addressed precisely that issue.
Alleged Inconsistency with the Government Statement on the Role of Data Centres
44. The Applicants’ reliance on the Government Statement on the Role of Data Centres
in Ireland is misplaced.
45. First, the Government Statement is not itself one of the instruments enumerated in
section 15(1). The statutory obligation concerns CAP 2023, the national long-term strategy,
adaptation framework, and the national climate objective.
46. Second, even taking the Government Statement into account, the Notice Party
demonstrated in the JSA Response to the Appeals that the principles set under the Statement
were met and, in particular, that the proposed development complied with the following
criteria:
(a) Mitigation of GHG emissions by entering long-term Corporate Power Purchase
Agreements … (CPPAs);
(b) compatible with renewable gas transition;
(c) incorporating energy efficiency measures (as set out at §90 of the Notice Party’s
Amended Statement of Opposition; and
(d) aligned with plan-led zoning for data centre development.
47. The Applicants’ submission that no ‘additionality’ was required overlooks the fact
that the mitigation commitments in the EIAR and appeal documentation formed part of the
material before the Board and were secured through the conditions attaching to the
permission. The fact that a CPPA condition was not framed in the precise wording suggested
by the Notice Party does not mean that renewable procurement commitments are absent.
Nor does the Government Statement create a legally enforceable additionality threshold as
a precondition to permission.
48. The Applicants reliance on the CAP 2023 statement that ‘new demand growth from
large energy users… will have to be moderated to protect security of supply and ensure
consistency with the carbon budget programme’ is misplaced. That statement is a policy
expression at national level. It does not constitute a prohibition on new large energy users.
CAP 2023 does not establish a moratorium on data centres, nor does it assign quantitative
allocations at project level.
49. The Inspector addressed security of supply, grid context, and energy strategy. The
development was assessed within the national electricity and regulatory framework,
including ETS coverage and EirGrid’s role. The Applicants’ argument again seeks to elevate
general policy language into a rigid legal rule.
The Development Plan and Objective CDP6.27
50. The Applicants contend that Objective CDP6.27 required a specific emissions
calculation which was ‘absent’. That is incorrect. The EIAR quantified emissions and
assessed climate impacts. The Development Plan objective contemplates precisely that such
analysis be undertaken at application stage, which is what occurred.
51. The presumption identified in Coolglass, that compliance with a lawfully adopted
Development Plan is ordinarily consistent with section 15, is not displaced merely because
the Plan requires climate assessment at project stage. On the contrary, the requirement for
such assessment reinforces the structured integration of climate considerations into the
planning code. The site was specifically identified for data centre use within the
Development Plan framework. That strategic zoning decision stands unchallenged. The
Commission was entitled to approach the application on the basis that the principle of data
centre development at this location had been determined at plan level, subject to detailed
assessment of environmental effects, which was carried out.
52. The Applicants’ case proceeds on the erroneous premise that any substantial GHG-
emitting project is presumptively inconsistent with section 15 unless accompanied by a
quantified demonstration of national budget compliance or project-level carbon neutrality.
That is not the law per Coolglass. When assessed through the lens identified in Coolglass,
the Decision plainly falls within the lawful spectrum of outcomes that could be regarded as
consistent, in so far as practicable, with section 15(1). The Applicants’ disagreement with
the evaluative planning judgment does not convert that judgment into legal error.”
141. The commission highlights the following from the inspector’s report:
“47. The Inspector also addressed the concerns raised by third parties regarding the
projected carbon emissions by reference to the proposed back-up generators – stating:
‘I note that varying estimates were submitted by the applicant and some of the Third Parties
in relation to the calculation of projected carbon emissions and/or savings for the project
relative to the various energy sources (incl. electricity, gas & diesel). As previously stated,
I am satisfied that the diesel-powered back-up generators would only operate in emergency
situations when there is a power outage. The proposed data centre would be connected to
the national grid via the Ennis 110kV substation to the W, and the on-site energy centre
would be connected to the natural gas pipeline to the E, however final approval to connect
to these utilities’ rests with the CRU, who will ultimately determine if adequate network
capacity exists.’
48. The Inspector concluded by stating that:
‘The proposed development, which would be located to the W of the Shannon and far away
from the Dublin metropolitan area and any other areas where there is a more intense
demand for data centres, would comprise a plan-led approach which complies with current
national, regional and local energy, planning and data centre locational policy.’
49. In relation to climate policies, the Inspector concludes that the data centre
development ‘would comprise a plan-led approach which complies with current national,
regional and local energy, planning and data centre locational policy’ (pg.49). In terms of
future gas supplies to the data centre development, the Inspector also noted (pg.57):
‘The on-site energy centre would be fuelled by natural gas via the nearby natural gas
pipeline, and it is possible that the 120:80 MW balance could shift in favour of the on-site
energy centre in the future. It is also anticipated that the energy centre would operate on
renewable gas supplies (incl. hydrogen & biomethane) depending on emerging technologies
at some stage in the future.’”
142. The overarching problem with this ground is that in the light of what was before the decision-
taker, the applicants have not demonstrated that the decision fell outside the range of options open
to the commission.
143. More specifically:
(i) It is not the law that planning permission for a development that generates
substantial GHG emissions and relies primarily on fossil fuels is automatically
precluded by s. 15. That said, such a situation does require the decision-taker to
validly arrive at a conclusion of either consistency or lack of practicability. The
applicants haven’t displaced the commission’s attempt to do that here.
(ii) It follows from the flexibility in s. 15 that a decision-taker is not mandatorily obliged
to quantify the amount of emissions from a development in every case. For example,
if no issue is raised in the process that requires such quantification, then a more
general conclusion may suffice. Or alternatively, if conditions are to be applied
requiring full mitigation or offsetting, then the actual quantum of emissions is not
legally determinative so there is no obvious need to engage in such quantification.
(iii) In any event, the notice party did quantify the emissions, in calculations which were
implicitly accepted by the commission. So any point about a duty to quantify doesn’t
arise in the present case.
(iv) The applicants are conveniently reading CAP23 as being more prescriptive than it in
fact is. As the commission submits, “even assuming that the Government Statement
of the Role of Data Centre’s in Ireland’s Enterprise Strategy requires a data centre
development to offer ‘more’ renewable energy back than the draw it will take, CAP
23 (as the Applicant itself says and relies on per Section 12.1.3) speaks about energy
matching not ‘additionality’ in the sense the Applicant uses it here”. That opens up
potential options on the spectrum which the applicants haven’t shown to be
exceeded here, based on what was before the decision-taker.
(v) This conveniently over-determined reading also applies to the moderation issue. The
statement in CAP23 regarding moderation of large energy users is too general to
warrant quashing the permission here, but in any event is a good example of a
climate principle “woven in” at a programmatic level, because the CDP here adopts
a firmly plan-led approach to data centre development at the development site.
EU law issues
Core ground 6 – EIA and the potential derogation licence
144. Core ground 6 is:
“6. The Data Centre Decision and the Substation Decision are invalid as the Board failed
to consider adequately or at all the environmental effects of the proposed development on
the environment in terms of impacts on bat fauna for the purposes of the EIA assessment
carried out by the Board and/or had no objective information before it to support a conclusion
of no significant effects on the environment for the purposes of the Board's EIA assessment
and/or impermissibly granted development consent prior to a decision granting a derogation
licence authorising bat roost removals and/or disturbance to bat species, further particulars
of which are contained below.”
145. The parties’ positions as recorded in the statement of case are summarised as follows:
“Core Ground 6 – Derogation
Applicants’ Position
205. There is no subjective or discretionary circumvention for the established legal
position that where a bat roost was identified in building 6C, a derogation licence must be
obtained by the developer, in advance of consent being granted.
206. Reliance in this regard is placed on the explicit finding of the Court of Justice of the
European Union in Namur Est (Case 463/20) that where a Member State confers power to
assess some of the environmental effects of a project and to take a decision upon the
conclusion of that partial assessment on an authority other than the one on which it confers
power to give development consent for the project, that decision must necessarily be
adopted before development consent is given (as concurred by Advocate General Medina in
her Opinion in O’Donnell v An Bord Pleanala (Case C-58/24) (delivered 11th September
2025).
207. Mr Clarke’s Affidavit sworn on behalf of the Developer helpfully makes this clear. He
says:
‘In reply to paragraph 28, I say and believe that planning permission and derogation
licensing are distinct processes under Irish law. It is my professional opinion that no works
can lawfully proceed without derogation, but that the absence of a licence at the date of
decision does not invalidate the permission. If the results of subsequent surveys require a
derogation licence to be obtained, the planning permission cannot be implemented in the
absence of same, meaning that no interference with roosting sites can occur unless or until
a bat derogation licence has been obtained.’
208. This contrives to ignore both that a derogation licence certainly was required prior
to the grant of planning permission as a result of an identified loss of a bat roost but also,
most particularly, this is precisely what the CJEU has identified as incompatible with the
requirements of the EIA Directive – the whole point is that no assessment of the
environmental effects is possible unless that assessment is made as part of the development
consent process and not post hoc as advocated by Mr Clarke.
209. There is no doubt that the Commission’s decision is incompatible with Namur Est.
The Commission, to its credit don’t seriously suggest that it is. This would be true if the
derogation licence requirement was limited to the roost in Building 6C but is irresistible in
circumstances where the Developer clearly could have, but opted not to, carry out the
relevant surveys in respect of other trees which may or may not contain roosts that are
specially protected for the purposes of Article 12. Rather it will carry out those surveys and
apply for any necessary derogation licences only after the development consent process has
concluded. This may suit the Developer’s purpose but it is a blatant breach of European law.
210. As pointed out by AG Medina in O’Donnell part of the rationale for the derogation
pre-ceding the grant of planning permission is to benefit developers by finding out at an
early stage whether they need to modify their development or whether it can go ahead at
all. The Developer chose not to apply for this determination in advance and therefore should
live with the consequences of its choice.
Commission’s Position
211. Their point is a derogation licence was required, by law, to be in place before ACP
could grant planning permission.
212. There are two responses to this point which the Applicant says is ‘unanswerable’.
213. First, it is not a proper reading of the Notice Party’s material to say a derogation
licence was necessary. In this respect, the Court’s finding of fact is very clear at paragraph
84(ix) which includes findings of fact which is that a single roosting bat from March 2022 is
‘almost certainly’ not to be at the same location if the development were to happen now.
The Notice Party’s material was clearly saying that whereas no roosting had been seen in
Building 6C at one point, a bat was seen in a crack at a later point and that insofar as a
derogation licence would be needed if it arose when the time came, it would – by law - have
to be sought.
214. To deal with this the Applicants have filed an affidavit from Mr. Marchant seemingly
in reply to the Court’s judgment, to urge the thesis that ‘once a roost always a roost’. In
this respect, the Court’s finding of fact is very clear at paragraph 84(ix) which includes
findings of fact which is that a single roosting bat from March 2022 is ‘almost certainly’ not
to be at the same location if the development were to happen now. In any event, leaving
aside how this deponent can swear as to what is ‘inferred’ into Regulation 51(2) of the EC
(Birds and Natural Habitats) Regulations 2011 (as amended), the very CJEU judgment he
relies on (IE v Magistrat der Stadt Wien Case C‑477/19) to ground that inference doesn’t
actually support the point he makes. The very paragraphs cited say that protection extends
to once but no longer occupied resting places ‘where there is a sufficiently high probability
that that species will return to such places, which is a matter for the referring court to
determine.’ The Court has already determined that probability doesn’t exist and Mr.
Marchant, choosing to deploy his expertise to aver about law, doesn’t actually make any
averments about this probability and this whole point falls away as a result. In short, the
way the Applicant has chosen to join issue with the Court over its findings, shows that the
Applicant accepts that a former roost can only be viewed as ‘still’ a roost if there is a
‘sufficiently high probability that that species will return to such place’ and that isn’t the case
here.
215. Second, more fundamentally, the case made completely misunderstands Namur Est
(Case C-463/20). In Namur Est (Case C-463/20) what was at issue was a single permit
which, if granted, authorised a predicted (and certain) disturbance. In Ireland it has …
always been accepted that a grant of planning permission cannot authorise what is otherwise
Article 12 harm, so the whole issue that arose in Namur Est just doesn’t arise in Ireland
because the harm-of-concern (i.e. Article 12 harm) is never authorised by a grant of
permission (see e.g. Redmond v An Bord Pleanála [2020] IEHC 151). That was the whole
problem in Namur-Est being that the single permit system would permit the harm. The
secondary problem arises due to the consequences of this – i.e. that if an Article 16
derogation was obtained first, the CJEU was alert to that foreclosing any debate under the
EIA banner about the relevant impact. Hence the CJEU was keen to point out, in effect, that
EIA remains supreme. Again, feeding all that back into the Irish system and the case here
one sees the reverse of Namur – i.e. you see a developer predicting a possible (even if
movable) impact, describing it as part of the EIA process (and not screening out EIA because
harm is avoided via a derogation licence). Indeed, that would enable the planning decision
maker – if it felt this was just too prejudicial – to even refuse permission for any works
remotely connected to the candidate-harm (i.e. in a given case where it is just too concerning
to even permit it, thus avoiding the harm and the derogation) which is precisely the sort of
inclusion-in-the-EIA which the CJEU was concerned to secure with its judgment. Indeed,
whereas the Applicant says all this is ‘unanswerable’ one can see it even in AG Medina’s
summary of the case in the later opinion in Case C-58/26 O’Donnell v An Bord Pleanala. In
the passage highlighted by the Applicant the AG pointed out how the CJEU concluded that
an Article 16 derogation can only be viewed as a partial assessment or preliminary decision
because, of course, the point was that EIA is supreme. Derogation is required first to enable
those identified effects be properly considered in the EIA process. Where everything is
considered in the EIA process, this just doesn’t arise. The concern of the CJEU in these
cases is to ensure that actual intervention is not permitted before derogation can be sought,
while, at the same time, ensuring that this doesn’t foreclose aspects of the EIA process.
And, in this respect, Ireland fares quite well. No intervention is permitted by planning
permission and certainly in this case, the issues were all out there for public comment and
participation for those who were concerned which, of course, doesn’t include the Applicants
as they weren’t concerned enough to make it. In short, Namur-Est says you can’t authorise
Article 12 harm before you’ve gone through the Article 16 process. Nothing of the sort
occurs in the Irish legal system as guarded by the jurisprudence of the High Court. Planning
permission simply doesn’t do this, and it's pretty simple and not remarkable to say in Ireland
you don’t have development consent (i.e. an ability to execute the project) until you have
all relevant consents.
216. In any event, the Court doesn’t need to address the second point, because the
Applicants here simply fail on the facts.
Developer’s Position
217. The Applicants raised no complaints about the matters which subtend Core Ground
6 during the planning process. The Notice Party says that this disentitles them to pursue
the issues raised now. The following is without prejudice to that position.
218. The Applicants’ case proceeds on the assertion that a derogation licence was
definitively required prior to the grant of permission. That is not borne out by the evidence.
As found by the Court in Doyle (No. 1) at §84(ix), the single bat observed in March 2022
was ‘almost certainly’ not going to be at the same location at the time of implementation.
The ecological evidence was that bats are highly mobile and frequently switch roosts.
219. Accordingly, it was not established that Article 12 harm would inevitably arise.
Furthermore, it was not established that a derogation licence was certainly required at the
date of decision. The position was conditional and contingent upon future surveys. That
factual finding is dispositive.
220. The Applicants now attempt to circumvent that finding by advancing a ‘once a roost,
always a roost’ theory. However, as recognised in IE v Magistrat der Stadt Wien (C-477/19),
protection extends to formerly occupied resting places only where there is a ‘sufficiently high
probability’ of return. The Court has already determined that such probability does not exist
on these facts. The Applicants’ expert affidavit, sworn by Mr Marchant, who was not
deployed as an expert in the planning process, does not establish otherwise. The premise
of automatic ongoing roost status therefore fails.
221. The Applicants fundamentally misread Namur Est (C-463/20). In Namur, the issue
arose because a single integrated permit would authorise certain disturbance of protected
species and the derogation decision operated as a partial environmental assessment outside
the EIA framework. The CJEU’s concern was to ensure that Article 12 harm is not authorised
before Article 16 assessment and EIA is not fragmented or bypassed. That situation does
not arise in Ireland.
222. Under Irish law, planning permission does not authorise Article 12 harm. Any
disturbance without derogation would constitute a criminal offence (see Redmond).
Implementation cannot proceed without all necessary consents. There is no ‘single permit’
system authorising protected harm.
223. The updated EIAR identified the single Leisler’s bat roost in Building 6C. It assessed
the environmental implications of its disturbance. It provided mitigation and recognised that
a derogation would be required if Article 12 harm arose at implementation stage. Thus, the
environmental effects were assessed within the development consent process. Nothing was
postponed ‘post hoc’.
224. Namur-Est does not establish a rigid rule that any possible need for derogation must
be resolved before planning permission. It establishes that where disturbance is certain and
authorised by the development consent, derogation must precede consent. Here
disturbance was not certain, harm was not authorised and the derogation regime remains
fully operative prior to works, with an entire brake on the permission being implemented
until a derogation licence is required, if found to be needed.
225. Even if the Court were to consider the sequencing issue abstractly, it need not do so
here. The Applicants fail because it was not established that a derogation licence was
definitively required at the time of consent and the Court has already made clear factual
findings on this point in Doyle (No.1).
226. Accordingly, Core Ground 6 discloses no incompatibility with EU law and no error of
law in the grant of permission.
227. Even if, contrary to the foregoing, it were established that an error arose in
conducting the EIA prior to the obtaining of a derogation licence, the Court retains a
discretion as to relief. On the uncontradicted ecological evidence before the Board, including
the conclusion that no significant adverse effect on bat populations would arise, subject to
mitigation and compensatory measures, any such error would be harmless and immaterial
in its practical effect. In those circumstances, and applying the proportionality principles
recognised in Save Cork and Pembroke Road, it would be neither necessary nor appropriate
to quash the decision.”
146. The basic reason why this point fails is that as explained in the No. 1 judgment by reference
to the notice party’s evidence, Bats are highly mobile. The once-a-roost-always-a-roost argument
impermissibly put forward by Mr Marchant comes one module too late. Modularisation is not a
mechanism for a party to “attempt to use module 2 to confound the court’s findings in order to
mend its hand to improve its chances on appeal” (as phrased in a submission quoted by Egan J. in
Webster v. Meenacloghspar (Wind) Ltd [2025] IEHC 587 (Unreported, High Court, 31 October 2025)
(see also Rural Residents (I) [2025] IEHC 600 at 137).
147. But even if that affidavit had been put forward originally, the argument is unfounded. All
there is is a possible need for a derogation licence, not a probable need. Admittedly the developer’s
EIA material originally was phrased in unconditional terms about derogation being required – but
that goes back a long way and we have had further evidence and debate on the matter since then
culminating in a finding in the No. 1 judgment in that regard. The judgment of 6 July 2023, Hellfire
Massy Residents Association v An Bord Pleanála and Others, C-166/22, ECLI:EU:C:2023:545 only
comes into play when we cross the threshold of probability. So I don’t need to consider the
commission’s argument that the Irish system does not render the absence of a derogation licence
fatal to EIA. That argument might even have required a further reference had it been decisive but
for the reasons explained there is no factual basis for that – we don’t get to that point here because
there is realistically zero chance of our bat still being in the crack in the wall in Building 6C, or indeed
of any of the bats being where they were when surveyed years ago. Bats typically remain in specific
locations for periods measured in days, not weeks, months or years. It is up to the applicant to
show that a derogation licence is probable as opposed to possible. They haven’t demonstrated that.
So the commission’s further defence is academic.
148. If I am wrong about everything else under this heading, I would be provisionally inclined to
exercise discretion against the applicants due to their having participated in the process and having
totally failed to make any submissions regarding the bat roost. However I appreciate that that would
raise some more general and possibly even referrable issues so I would prefer not to make any
definitive finding unless it were necessary to do so.
Summary
149. From the notice party’s perspective these proceedings have merely brought about delay and
uncompensatable financial prejudice. Obviously I sympathise with that point of view. From the
applicants’ perspective, the bringing of the proceedings has been the lawful expression of an urgent
and principled desire to take personal responsibility for addressing the climate emergency in a
context where across the world institutions have failed to meet the crisis with anything like the
radical action required. I sympathise with that point of view also. Despite the outcome, the
applicants’ efforts have not been entirely in vain as a careful reading of the judgment should indicate.
The practical albeit to an extent obiter takeaway in that regard is that the primary responsibility is
on planning decision-takers to appropriately scrutinise projects causing net emissions, and on the
OPR, as the only institutional actor meaningfully able to take the initiative in this respect, to ensure
that individually and independently adopted city and county plans are woven together with national
goals and instruments into a coherent and climate-objective-compatible whole.
150. In outline summary, without taking from the more specific terms of this judgment:
(i) it is settled law that the applicant’s point must be properly pleaded with the
requisite specificity;
(ii) applying such law to the facts here, certain of the applicants’ issues are not properly
pleaded as set out in the judgment;
(iii) it is settled law that, apart from autonomous-type obligations, material capable of
sustaining the point must have been properly before the decision-taker at the
relevant time such as to give rise to a duty to consider it, and in particular the
extent to which climate issues were raised in the process is of major
importance, such that a failure to raise such issues may have the effect of limiting
the obligations on the decision-taker and correspondingly limiting the scope for relief
to be granted by the court;
(iv) applying such law to the facts here, the applicants’ failure to raise some of the
pleaded issues in the process (as set out in the judgment) makes it implausible and
inappropriate to grant relief on the basis of alleged failure to observe the duties
imposed by the 2015 Act on the basis of those issues, in circumstances where there
was a clear engagement with the autonomous duty under the 2015 Act;
(v) it is settled law that the applicant must have discharged the onus of proof to
establish all facts necessary for relief and to demonstrate that the performance of
the functions of the relevant body falls within outside the spectrum of possible
outcomes that could be said to be consistent, in so far as is practicable, with the
objective of s. 15, bearing in mind that much of the policy is phrased at a
general level;
(vi) applying such law to the facts here, the applicants have not discharged that onus
here, and have misread policy documents as being mandatory and prescriptive when
on a proper reading they are flexible;
(vii) it is settled law that a decision should be read as valid and as making sense where
such a reading is reasonably available;
(viii) applying such law to the facts here, this decision is capable of being read as valid
and rational;
(ix) it is settled law that a general condition that the development be carried out in
accordance with the plans and particulars submitted includes any specific
documentation submitted by the developer during the process;
(x) applying such law to the facts here, the agreement to power the project with
renewables via CPPAs is included in the general condition;
(xi) it is settled law that a derogation licence should be obtained before a development
consent if derogation is probable as opposed to being a mere possibility; and
(xii) applying such law to the facts here, the applicants haven’t shown that a derogation
licence here is more than a possibility.
Order
151. For the foregoing reasons, it is ordered that:
(i) the proceedings be dismissed;
(ii) there be a recital in the order noting that by consent of the notice party and the
commission, the court is satisfied that conditions 1 and 3 collectively have the effect
that the development is conditioned in accordance with the documentation
submitted with the application which therefore has the effect of requiring CPPAs as
set out in para. 4.48 of the John Spain Associates response document;
(iii) unless any party makes any consequential application otherwise by the time and in
the manner set out below, the foregoing order be perfected forthwith thereafter on
the basis of no order as to costs (including no order as to the costs of any previous
module or application in the proceedings having regard inter alia to O. 103 r.
38(1)(b) and/or (c) RSC, or any reserved or adjourned costs not otherwise dealt
with);
(iv) the foregoing proposed orders as to costs, directions or the form of the order be
perfected immediately following the mention date below unless consequential or
contrary written legal submission are filed by that time, with replies by other parties
within a similar period thereafter;
(v) for the avoidance of doubt, any unsuccessful application to vary any provisional
order as to costs proposed in this judgment may be addressed pursuant to O. 103
r. 40(4) RSC; and
(vi) the matter be listed at 09:30 on Thursday 19 March 2026 to confirm the foregoing.