High Court extends time and quashes planning decision due to developer's notice defects affecting applicant.
Legislator summary
AI generatedThe High Court extended the time limit for proceedings and granted certiorari to quash the respondent's decision. The applicant argued that the developer's defective newspaper notice and failure to remove the old site notice breached public participation requirements, despite the applicant being innocent of these defaults. The court held that while the defects were technical, they required relief to prevent the applicant from suffering the consequences of the developer's errors, thus extending time and quashing the decision.
Legislator headnote
AI generateds. 50(8) of the Planning and Development Act 2000; s. 30 of the Planning and Development Act 2000: Where a planning applicant is innocent of a legal breach caused by the developer, the court may extend time limits and grant certiorari to quash a decision to prevent the applicant from suffering the consequences of the developer's defaults.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
[2025] IEHC 656
THE HIGH COURT
PLANNING & ENVIRONMENT
[H.JR.2025.0000089]
BETWEEN
IAN CROFT
APPLICANT
AND
DUBLIN CITY COUNCIL
RESPONDENT
AND
AIDEEN WHELAN
NOTICE PARTY
Date of impugned decision: 30 September 2024
Date proceedings commenced: 22 January 2025
Date of main hearing: 20 May 2025 & 1 October 2025
Date draft judgment circulated: 21 October 2025 & 17 November
2025
JUDGMENT of Humphreys J. delivered on Friday the 28th day of November 2025
1. There is a big difference between a breach of public participation and notification
requirements that doesn’t adversely affect a given judicial review applicant and a breach that does.
Barring some catastrophic failure in the process, the former type of essentially ius tertii complaint
normally warrants either declaratory relief only or (especially now that there has been so much
clarification in caselaw as to what the requirements are) no relief at all. The latter type is a genuinely
proper ground for certiorari. To put it another way, the former tends to be a bit of an academic
technicality (save in an unusual case of some really fundamental failure in public notice
requirements) whereas typically the latter genuinely affects rights that the court should protect.
Contrary to an extraordinarily popular delusion these days, courts don’t tend to quash things on the
basis of mere technicities. There has to be a point of genuine substance that makes a real difference
to an objective interest that warrants protection. Bearing that distinction in mind, planning caselaw
going back 50 years has emphasised the importance of compliance with statutory provisions on
public notification. The criticality of such matters has been supercharged by the right of public
participation under the Aarhus Convention, now incorporated in EU law. The developer here
published a defective newspaper notice with the effect that her application was declared invalid. The
defect, rather forebodingly, was the omission of wording about public participation in the decision-
making process. The council then wrote to the developer in accordance with the Planning and
Development Regulations 2001 (S.I. No. 600 of 2001) to have the site notice taken down in respect
of the invalid application. The developer then made the second and fatal error in failing to do that.
Instead, a fresh application was made without erecting a fresh site notice. There is no evidential
explanation for that. The applicant’s evidence that he relied on the site notice and was unaware of
there being a fresh application has not been displaced. It is perhaps prudent to emphasise one thing
– this matter is not about a €7.5 million sale being put at risk over a typographical error that made
no difference. It is about a permission that was obtained despite two breaches of planning
regulations that on the evidence had the actual cumulative effect of disadvantaging the applicant
and shutting him out of the process. Among other consequences, not participating at council level
meant he would have been ineligible to appeal the grant of permission. That isn’t harmless error, it
isn’t de minimis and it isn’t something that should be ignored as a matter of discretion. It is not the
law that the size of a proposed transaction or a proposed development overwhelms the need for the
right to public participation to have been afforded in accordance with law. While commerciality is
relevant to the court’s consideration in many situations, including to the right to have proceedings
advanced at pace where parties so request, the court, if it is to hold the scales equally at all as
between the various interests involved in this area, must also be vigilant to protect the procedural
rights of less powerful stakeholders in the planning process, including giving real and meaningful
effect to the right to public participation in environmental decision-making, and to wide access to
justice in environmental matters, as enshrined in the Aarhus Convention and in EU law. The council
has conceded certiorari and, in the circumstances outlined below, the developer is not in a position
to continue to defend the proceedings. The purpose of this judgment is therefore to explain why I
am satisfied to make the order sought by the applicant. I appreciate that 20 pages and 15,000
words to explain an unopposed order will seem like overkill, but the notice party has requested
written reasons, and one has to lean towards facilitating such a request, all other things being equal.
Geographical context
2. The notice party sought permission as follows:
“Planning permission for development of a Large-scale Residential Development (LRD) at a
c. 0.24 ha site on lands at Church Lane and Swords Road, Santry, Dublin 9.
The proposals comprise the demolition of existing buildings and structures on site and the
construction of a mixed-use development comprising a single block including 268 no.
purpose-built student accommodation bedspaces and café.
The development will consist of:
- Demolition of existing buildings and structures on site (c. 1,476 sq.m)
- Construction of 268 no. purpose-built student accommodation bedspaces (251 no.
standard rooms, 5 no. studios and 12 no. accessible rooms) across a single block ranging in
height from 5 storeys (17.25 metres above ground level) to 8 storeys (26.19 metres above
ground level) to parapet height, with plant enclosure at roof level (total height 27.95
metres), accessed from Swords Road and Church Lane.
- Café unit at northwest corner (c. 71 sq.m) at ground floor with outdoor seating area
adjacent to northern and western elevations accessed from Church Lane, enclosed with
reconstructed stone wall at Swords Road elevation.
- Provision of c. 631 sq.m of student amenities and services at ground floor level
consisting of gym, library, coworking space, games area, reception and lobby, laundry,
office/ admin, refuse and parcel rooms.
- Provision of c. 891 sq.m of external amenity space comprising central courtyard and
roof terraces at fifth, sixth and seventh floor levels.
- A total of 332 no. bicycle parking spaces: 122 no. internally at ground floor level
(accessed from Church Lane and central courtyard), 202 no. within split-level sheltered
bicycle store in the southern part of the central courtyard, 4 no. serving the café at northern
elevation and 4 no. located adjacent to the main entrance at the western elevation to Swords
Road.
- Landscaping, planting and seating along the northern elevation at Church Lane, with
reconfigured public footpath.
- Plant, ESB substation and refuse store accessed from eastern elevation at Church
Lane.
- Access via double height archway from Swords Road at southwest corner of the site,
with hard landscaping.
- All associated infrastructure, landscaping, open space, PV panels (roof level),
green/blue roof, access, lighting and works to facilitate the proposed development.
The development may be used for short-term temporary tourist accommodation outside the
normal academic year in accordance with the definition of student accommodation set out
in Section 13 of the Planning and Development (Housing) and Residential Tenancies Act
2016.”
3. The application documents were also available at www.churchlanelrd.ie (not currently
online).
Facts
4. Dublin City Council's published external checklist, adopted in February 2021, (downloadable
at https://www.dublincity.ie/sites/default/files/2021-02/external-checklist-february-2021.doc)
states that where an application is deemed invalid, any resubmission must be accompanied by new
and compliant notices.
5. A site notice (placed at four locations) was erected on 31 July 2024.
6. On 1 August 2024, the notice party made an application to the council for the proposed
development, under reference LRD6053/24-S3. That planning application was invalidated by the
council by way of a letter dated 6 August 2024. The reason for the invalidation of the application
was that the newspaper notice for the application was missing part of the statutory wording, namely
the words “and a submission or observation in relation to the application may be made to the
authority in writing on payment of the prescribed fee within the period of 5 weeks beginning on the
date of receipt by the authority of the application” were missing from the newspaper notice.
7. A notice was issued under art. 26(5) of the 2001 regulations by the council in relation to the
original invalid application. The letter explicitly required removal of the original site notice and
confirmed that any re-lodged application must include a new site notice and newspaper notice, both
dated within two weeks of submission. The evidence in relation to this letter is as follows:
“22. On 6th August 2024 (5 days after the submission of the first planning application)
the Council wrote to the Notice Party pursuant to the provisions of Article 26(5) (a copy of
which is at TAB 1 to ‘BP1’). The said Notice under Article 26(5) states, inter alia, as follows:
‘I wish to inform you that the above planning application is invalid and cannot be considered
by this Planning Authority. Set out below are the requirements of the Planning &
Development Regulations 2001 (as amended) that have not been complied with.
You are hereby requested to remove the site notice(s) erected or fixed in respect of the
above application.
I return herewith the planning application including all particulars, plans, drawings and
maps.
Arrangements are being made to refund the planning fee in respect of this application to
you.
Please note that any resubmitted planning application must be accompanied by the
appropriate fee, the required number of particulars, plans, drawings, maps, etc, a newspaper
notice, which must have been published not more than TWO WEEKS prior to the date of re-
lodgement. Also, please note that any resubmitted planning application must be
accompanied by a copy of site notice, which must have been erected not more than TWO
WEEKS prior to date of re-lodgement.
Any planning application resubmitted must be in full accordance with the Planning &
Development Regulations 2001 (as amended), and Dublin City Council reserves the right to
declare such resubmitted application invalid if all the requirements are not complied with.
In order to facilitate the validation of this application the applicant is advised on resubmission
to quote the previous invalid planning application number or enclose a copy of this letter
with the resubmitted application
[…]
REQUIREMENTS NOT COMPLIED WITH
1. Part of the statutory wording is missing from the Newspaper Notice.
‘and a submission or observation in relation to the application may be made to the authority
in writing on payment of the prescribed fee within the period of 5 weeks beginning on the
date of receipt by the authority of the application.’
Note: The applicant is advised that the Planning Registry Section (Block 4, Ground Floor,
Civic Offices, Wood Quay, Dublin 8) have retained 3 boxes of drawings and reports pending
resubmission or collection. Please contact the Planning Registry Section 01 22 23114 to
confirm.”
8. It is common case that the site notice was not so removed.
9. A newspaper notice, namely the newspaper notice that was published in the Irish Daily Star
on 7 August 2024 (which contained the correct statutory wording), was lodged with the relevant
planning application (bearing reference LRD6053/24-S3A).
10. The second planning application, which bears reference LRD6053/24-S3A, for precisely the
same development as LRD6053/24-S3, was lodged with the respondent on 7 August 2024, that
application was validated by the respondent and the newspaper notice submitted as part of that
application contained the correct statutory wording (i.e. it contained the statutory wording that had
been missing from the newspaper notice submitted with the previous application under reference
LRD6053/24-S3). In short, in substance, the same planning application was made for the same
large-scale residential development (LRD), but with a newspaper notice that contained the correct
wording.
11. The application included an environmental impact assessment (EIA) screening report
concluding that an EIAR was not required:
https://webapps.dublincity.ie/PublicAccess_Live/Document/ViewDocument?id=3830716A5A2611E
F8183005056B85853 and
https://webapps.dublincity.ie/PublicAccess_Live/Document/ViewDocument?id=3830716C5A2611E
F8183005056B85853.
12. An appropriate assessment (AA) screening report considered that stage 2 AA was not
required:
https://churchlanelrd.ie/data/files/Other%20Reports/Appropriate%20Assessment%20Screening%
20Report.pdf (currently offline).
13. In response to an email received from the applicant (sent on 7 August 2024 at 20.12 pm)
regarding the invalidation of the planning application bearing reference LRD6053/24-S3, the
respondent’s Planning & Property Development Department, by email to the applicant, sent at
9.55 am on 8 August 2024, informed the applicant that (i) if the application he was interested in
making a submission on had been declared invalid he would be unable to make a submission on it;
(ii) he was advised to wait for if/when a new application is lodged which he could then submit an
observation on; and (iii) he was advised that in relation to new planning applications that he could
search for them online at a link to the respondent’s website provided in that same email (namely a
link to the Citizen Portal Planning page through which planning observations by third parties can be
submitted online and which also contains a direct link to the ‘search application’ of the respondent’s
website).
14. The applicant’s email of 7 August 2024 states:
“From: Ian croft <…>
Sent: 07 August 2024 20:12
To: Planning <planning@dublincity.ie>
Subject: Planning Reference: Church Lane LRD6053/24-S3
A chara,
I note from the planning portal that the above planning application has been declared invalid.
Would you be able to advise what this means as I am unsure if it is necessary to continue
with my observation at this point. Many thanks.
Best regards
Ian”
15. The respondent’s first email of 8 August 2024 states:
“From: Planning <planning@dublincity.ie>
Sent: Thursday, August 8, 2024 9:55:27 AM
To: 'Ian croft' <…>
Subject: RE: Planning Reference: Church Lane LRD6053/24-S3
Hi Ian,
If an application that you were interested in submitting an observation on has been declared
invalid,
You are unable to submit an observation on it.
I would advise that you wait for if/when a new application is lodged,
Which you could then submit an observation on.
You can search for new applications online via the link below.
https://planning.agileapplications.ie/dublincity
Kind regards,
…
Planning & Property Development Department
Civic Offices ¦ Block 4 ¦ Floor 3 ¦ Wood Quay ¦ Dublin 8
E: planning@dublincity.ie
An Roinn Pleanála & Forbairt Maoine
Oifigí Na Cathrach ¦ an Ché Adhmaid ¦ Bloc 4 ¦ Urlár 3 ¦ Baile Átha Cliath 8
E: planning@dublincity.ie”
16. The applicant’s email of 8 August 2024 states:
“From: Ian croft <…>
Sent: 08 August 2024 15:23
To: Planning <planning@dublincity.ie>
Subject: Re: Planning Reference: Church Lane LRD6053/24-S3
Hi …,
Thanks for the update. Appreciate that, it is good know. Would the reason why the planning
application be declared invalid be information that could become available to the public on
the dashboard within the current list of documents? Thanks again
Best regards
Ian
Sent from Outlook for Android”
17. The final email of 8 August 2024 states:
“From: Planning <planning@dublincity.ie>
Sent: Thursday, August 8, 2024 3:32:02 PM
To: 'Ian croft' <…>
Subject: RE: Planning Reference: Church Lane LRD6053/24-S3
Hi Ian,
If an application is declared invalid,
The reason usually is uploaded to the website under the conditions tab.
Please see the below link to the reason for invalidation.
Citizen Portal Planning (agileapplications.ie)
Kind regards,
…
Planning & Property Development Department
Civic Offices ¦ Block 4 ¦ Floor 3 ¦ Wood Quay ¦ Dublin 8
E: planning@dublincity.ie
An Roinn Pleanála & Forbairt Maoine
Oifigí Na Cathrach ¦ an Ché Adhmaid ¦ Bloc 4 ¦ Urlár 3 ¦ Baile Átha Cliath 8
E: planning@dublincity.ie”
18. It is the case that channels other than inspection of site notices were available – as the
foregoing correspondence pointed out to the applicant. As regards the search application page on
the respondent’s website, following the making of the application bearing reference LRD6053/24-
S3A, had the applicant, for example, typed the reference “LRD6053/24-S3” into the ‘Planning
Reference’ box, or “Church Lane” into the ‘Location’ box, or the notice party’s name “Aideen Whelan”
into the ‘Applicant’ box, a search by any of those terms would have and continues to return the
result of producing a link to both application LRD6053/24-S3 and to the subsequent application
bearing reference LRD6053/24-S3A. At all material times the relevant planning application (bearing
reference LRD6053/24-S3A) was available (and remains available) for inspection on the
respondent’s website (at https://planning.agileapplications.ie/dublincity/application-
details/162941).
19. It is common case that site notices had been erected at four locations in connection with the
invalid application. One of the site notices was positioned on Church Lane, one of the site notices
was on a pillar at the end of Church Lane, and the other two site notices were on the Swords Road.
Each site notice was on a white background.
20. It is also common case that the same site notice was availed of for LRD6053/24-S3 and
LRD6053/24-S3A. The notices relied on for the permission now impugned were erected in
connection with the original invalid application and prior to the take-down notice from the
respondent, and it is common case that the developer did not take down the original site notices as
required by that notice.
21. The respondent inspected the site notices at around 2 pm on 13 August 2024, and
photographs were taken and exhibited.
22. Third-party observers made observations on the relevant planning application LRD6053/24-
S3A (including Santry Forum, but there is no evidential basis to conclude that the applicant’s
evidence as to his unawareness is incorrect). The respondent received five third-party observations
on the relevant application for permission.
23. The decision of the respondent, dated 30 September 2024 (reg. ref. LRD6053/24-S3A), was
to grant planning permission, subject to 26 conditions to the notice party for a proposed development
comprising a LRD (consisting, inter alia, of the demolition of existing buildings and structures on site
and the construction of a mixed-use development comprising a single block including 221 purpose-
built student accommodation bedspaces and café) at a c. 0.24 ha site on lands at Church Lane and
Swords Road, Santry, Dublin 9. The planning application had sought permission for 268 bedspaces
but Condition 4 of the respondent’s decision, which relates to the omission of the fourth floor of the
development, will result in the omission of 47 bedspaces, therefore reducing the number of
bedspaces in the permitted development to 221.
24. A first-party appeal was lodged with the board on or about 1 November 2024 by the notice
party (seeking the omission of Condition 4), however that appeal was withdrawn on or about 7
November 2024, and thereafter, a final grant of permission was issued by the respondent on or
about 25 November 2024.
25. A news article relating to the development was published in the Irish Times on 15 January
2025 (https://www.irishtimes.com/property/commercial-property/2025/01/15/santry-site-for-
with-planning-permission-for-a-student-scheme-for-75m/). The applicant’s evidence that he was
not aware of the application up to that point, which has not been rebutted and which I accept, is
(emphasis added):
“7. I also note that I, like many members of the public, rely on physical site notices to
stay informed of planning activity. It is well documented in my submissions that I do
not routinely check the online planning portal and that no obligation exists for me to do so.
I was never placed on notice of the second application through proper channels.
8. I discovered the planning permission on 15 January 2025 when I viewed a property
listing which stated the site had ‘full planning permission.’ I prepared and submitted my
original Grounding Affidavit on 22 January 2025, within one week of that discovery.”
Procedural history
26. The applicant, appearing pro se, filed his statement of grounds and verifying affidavit on 22
January 2025. The applicant was granted leave to apply for judicial review on 17 February 2025
(by order perfected on 19 February 2025), without prejudice to any point the opposing parties could
have made, and the developer, Aideen Whelan, was joined as a notice party to the proceedings.
27. The applicant served and uploaded to ShareFile a supplemental affidavit on 3 March 2025.
By email dated 7 March 2025, the respondent confirmed it accepted that the present proceedings
are covered by s. 50B of the Planning and Development Act 2000 (the 2000 Act). (The applicant
had served a motion dated 14 February 2025 seeking costs protection).
28. The originating notice of motion was filed on 10 March 2025, and the matter came before
the court on 24 March 2025, when it was assigned a hearing date of two hours on Tuesday 20 May
2025, and was then adjourned to 12 May 2025 for callover to allow filing of statements of opposition
and closing of the pleadings and delivery of written submissions and preparation of a statement of
case in accordance with a schedule of directions proposed by the respondent and agreed to by the
applicant and notice party developer. The respondent filed its statement of opposition and two
affidavits on 17 April 2025. The notice party developer filed its statement of opposition and an
affidavit on 23 April 2025. The applicant filed a replying affidavit on 25 April 2025.
29. The applicant filed written submissions on 6 May 2025. The matter was called over on 12
May 2025. The respondent filed written submissions on 15 May 2025. The case was listed for
hearing at 9.30 am (two hours) on 20 May 2025.
30. At an early stage in that hearing there was an objection to the extent to which the applicant’s
point under art. 26 of the 2001 regulations was pleaded. In essence, the applicant pleaded that
there should have been a new site notice following the invalidation of the original notice, but relied
in his statement of grounds on the wrong articles of the 2001 regulations (phrasing the claim in
terms of arts. 19 and 20 instead of 26). I did outline to the parties that the fact that there was such
an acute pleading issue wasn’t totally clear to me in advance. Had this been clearer at an earlier
stage the question of amendment could have been discussed in a less pressurised manner and
addressed in advance. At the hearing the applicant also clarified that he was not pursuing the point
about the yellow site notice (art. 19(4)).
31. On the question of whether the applicant’s point now being made was acceptably clear from
the original pleadings, I ruled that the answer to that has to be No. The original pleading only makes
a point relating to arts. 19 and 20 in terms that focused on whether the notice should be on a white
or yellow background. Therefore if the art. 26(5) point was to be pursued it had to be by way of
amendment. The applicant said he wanted to “resubmit” (i.e., amend) the statement of grounds to
include the art. 26 basis for the proposition that the original notice should have been removed.
32. While it was argued that the question of extension of time should be dealt with before
amendment, I determined that in the circumstances that would be a meaningless exercise given
that the extension only arises where we know what point the applicant wants to make, so the
amendment needs to be at least considered first.
33. Insofar as other objections were raised, I considered that those matters could be dealt with
at the hearing. The developer also objected on the grounds of prejudice, but insofar as delay would
cause prejudice, I considered that that was arguably attributable to default on the developer’s side:
(i) the developer/ her servants or agents failed to publish a valid newspaper notice
conforming to the legislation;
(ii) this inevitably led to the invalidation of the application thus causing or contributing
to the situation we are now dealing with whereby the applicant contended that he
was prejudiced having wanted to engage with the original application; and
(iii) the applicant argued (which I didn’t need to decide at that point, and the respondent
didn’t want it decided then in any event) that there was also breach of art. 26(5) in
not removing the original site notice.
34. In the circumstances I considered that the prejudice of delay was, at that stage, arguably
sufficiently of the developer’s own making (i.e., including the developer’s servants or agents) as not
to be an overwhelming reason against allowing the question of amendment to be considered in an
orderly fashion.
35. Accordingly on 20 May 2025, I gave the applicant liberty to bring a motion grounded on an
explanatory affidavit seeking an amendment dropping the art. 19(4) point and adding the art. 26(5)
point. That did not prejudice the right of the opposing parties to oppose the application on any
grounds they might have advanced at the liberty-to-issue-the-motion stage. It was explained that
the affidavit needed to exhibit an amended statement of grounds with strike-through and underlining
and explain not including the point originally.
36. The opposing parties requested a formal notice of motion which was directed. The developer
asked for the earliest return date which was Monday 26 May 2025.
37. On that date, the amendment application was listed before Nolan J., who heard the
amendment application and allowed the amendment.
38. The matter returned to the List to Fix Dates on 30 June 2025. The notice party asked for
the earliest date, which was provided by listing the matter on Monday 14 July 2025 at the end of
the list rather than being given a regular hearing date. Unfortunately due to pressure of business
the matter was not reached on that date and was adjourned for hearing to 29 September 2025, with
supplemental written submissions being permitted. The attempt to shoehorn the case into a Monday
list rather than wait for a more regular hearing date was thwarted for a second time on the latter
date but the case was accommodated as soon as possible thereafter on Wednesday 1 October 2025
and heard then, with all parties being commendably economical.
39. Judgment was reserved at the end of that hearing. I would like to record my thanks to the
applicant and all of the lawyers involved for their unfailingly courteous, professional (in the case of
the lawyers) and helpful assistance. As I have previously sought to make clear, insofar as any points
advanced are not being accepted in this or any other given judgment, that is solely to do with the
inherent merits of such points and is no reflection on those conveying or instructed to convey such
points, a distinction that most certainly should be, and I believe generally is in fact, self-evident to
all concerned.
40. On 21 October 2025, a draft of the present judgment was sent to the parties to give an
opportunity to identify any errors. The applicant appears to have misunderstood the need to keep
a draft judgment under wraps, and may have incorrectly let some information slip on a private
residents’ Facebook group, which is something to avoid for future reference. While a draft sets out
the court’s thinking (subject to limited error-correcting submission) it does not have any status until
judgment is delivered. The applicant has thus indirectly achieved a small but important footprint in
the sands of procedure, in the sense that this little faux pas has resulted in a tightening of the
wording in draft judgments in that regard, something that may also have to be considered at wider
practice direction/guidance level in due course.
41. Following correspondence between the parties a second draft of the present judgment was,
exceptionally, circulated to parties on 17 November 2025.
42. The rules of engagement in such a situation are that the draft is without prejudice to the
right of the court ultimately to issue a judgment in whatever form or with whatever content it
considers appropriate.
43. Any comments must be emailed to the relevant judicial assistant and uploaded to ShareFile
in writing within 7 days or by the mention date whichever first occurs and should not be to reargue
the substance (submissions to that effect will be disregarded) but are confined to matters such as:
(a) informing the court as to whether a formal judgment is required, and if so on what
issues;
(b) informing the court as to whether a judgment might be oral or written or partly in
both modes;
(c) any typographical, factual or legal errors in the decision;
(d) any redaction of personal information that the party wishes to request;
(e) in the event that the court proposes to place pivotal reliance on any authority or
material not previously adverted to, as opposed to where such material merely
reinforces a point that the court was making in any event, any comment as to why
such material should not lead to the proposed conclusion; identifying points that the
court proposes to address but that the parties consider it unnecessary to address;
(f) requesting the court to decide a point that, while unnecessary to decide, is one the
party considers could beneficially be decided;
(g) identifying significant procedural, factual or legal points that the party considers that
the court was required to address but has not addressed or not provided reasons
for; and
(h) any other suggestions as to the wording (as opposed to substance) of the decision
if the proposed wording causes any significant issue for a party for any identified
reason.
44. It is then entirely a matter for the court as to whether to list the matter for mention, or
whether to simply give judgment with or without amendment to respond to any such comments or
for any other reason that appears appropriate to the court. Any judgment may be given without
further notice following the expiry of the specified period, whether comments are made or not. That
period will not be extended save in exceptional circumstances. All parties involved are requested to
positively confirm to the court the position including if they have no observations on the draft
legitimately falling within the foregoing parameters. Overall the draft judgment procedure is a
concession which parties can engage with but must do so with immediate dispatch, discipline and
focus – it is not the opening of a new phase of the litigation that gives rise to “an entitlement to
elaborate procedures at every point” (to use a phrase of O’Donnell C.J. (Dunne, Charleton and Baker
JJ. concurring) in O’Sullivan v. HSE [2023] IESC 11 (Unreported, Supreme Court, 10 May 2023) at
para. 39); and still less should the procedure invite the perhaps “serious error, to which lawyers are
prone, to approach any such case on the tacit assumption that only procedures which approximate
to a criminal trial are fair, and anything which departs from that is somehow dubious" (O’Donnell J.
in O'Sullivan v. Sea Fisheries Protection Authority [2017] IESC 75, [2017] 3 I.R. 751, [2018] 1
I.L.R.M. 245, 780).
45. For the avoidance of doubt, draft judgments are not public domain materials and, while they
can be shared between the lawyers concerned and their clients, they are not intended for publication
(indeed given their lack of status it is impracticable to refer to them, even in the context of
considering such drafts in other litigation, until the judgment is formally issued) or for any other
transmission save for the legitimate purposes of the litigation. Therefore anyone with information
as to the text, content or proposed outcome of any draft is required not to transmit such information
to others save solely by way of private transmission for the legitimate purposes of the litigation and
subject to a similar restriction on any recipient (see Attorney General v. Crosland (No. 2) [2021]
UKSC 58, [2022] 1 W.L.R. 367, [24/01/2022] T.L.R. 1 which discusses why restriction on publication
of draft judgments is in the interests of the administration of justice). The contents of this paragraph
constitute an immediately effective direction of the court to the parties and anyone having notice of
the draft judgment with effect from the date of circulation of the draft.
46. The mention date to review matters following the foregoing was to be 24 November 2025
and a modest clarification (which I have endeavoured to address in para. 69) was suggested by the
notice party.
Relief sought
47. The reliefs sought in the statement of grounds are as follows:
“1. An order for leave to apply for judicial review, challenging the decision of Dublin City
Council to approve planning application LRD6053/24-S3A.
2. An order of Certiorari, quashing the decision to grant planning permission for
LRD6053/24-S3A.
3. An extension of the statutory time limit for bringing judicial review proceedings due
to exceptional circumstances, including late discovery caused by procedural irregularities.
4. Any other relief this Honourable Court considers just and appropriate.
5. An undertaking by the Applicant to comply with any directions of this Honourable
Court, including the provision of further documentation or participation in a formal hearing,
as required.”
Grounds of challenge
48. The grounds of challenge are as follows:
“1. Failure to Post a New Site Notice:
o The original planning application (LRD6053/24-S3) was deemed invalid by Dublin
City Council.
o The subsequent application (LRD6053/24-S3A) relied on the same site notice
without erecting a new one, in breach of Articles 19 and 20 of the Planning and Development
Regulations 2001 (as amended), specifically Article 19(4), which states:
"Where a planning application is made in respect of any land or structure, and a subsequent
application is made within 6 months from the date of making the first application in respect
of land substantially consisting of the site or part of the site to which the first application
related, in lieu of the requirements of sub-article (1)(b), the site notice shall be inscribed or
printed in indelible ink on a yellow background and affixed on rigid, durable material and be
secured against damage from bad weather and other causes."
• The subsequent application (LRD6053/24-S3A) relied on the same site notice
without erecting a new one, in breach of Article 26(5) of the Planning and
Development Regulations 2001 (as amended), which provides that where a planning
application is deemed invalid, the planning authority shall notify the applicant in
writing and request the removal of any site notice erected under Article 17(1)(b).
• The Applicant contends that a fresh site notice should have been erected for the new
application, with a new date, regardless of whether the content was the same, in
order to provide proper and transparent public notice and allow for public
participation.
• The failure to erect a new site notice deprived the Applicant and the community of
their statutory right to be informed of, and to participate in, the planning process.
o The Applicant asserts that Dublin City Council failed to ensure compliance with this
statutory requirement, resulting in the community, including the Applicant, being deprived
of their statutory right to be informed of and participate in the planning process.
2. Late Discovery of Approval:
o The Applicant only became aware of the planning approval through a news article
published on 15th January 2025 in the Irish Times which was offering the site for sale with
Full Planning Permission.
o This delay resulted directly from the procedural flaws outlined above, which
undermined public transparency and prevented timely objections.
3. Comparison to Similar Applications:
o Other planning applications in the area have usually seen higher numbers of
observations, highlighting the lack of public awareness in this case due to the absence of a
new site notice.
4. Breach of Natural Justice:
o The procedural irregularities violated principles of natural justice by denying the
Applicant and the local community a fair opportunity to object or participate in the planning
process.”
Relevant statutory provisions on planning applications
49. Article 17 of the 2001 regulations (substituted by art. 8 of S.I. No. 685 of 2006 Planning and
Development Regulations 2006) requires notice within the two weeks in advance of a planning
application:
“17. (1) The planning authority shall, when issuing a notice under section 32D of the Act,
send its record of the section 247(1A) LRD consultation and the section 32C LRD meeting
concerned to the prospective LRD applicant. An applicant shall within the period of 2 weeks
before the making of a planning application—
(a) give notice of the intention to make the application in a newspaper in accordance with
article 18, and
(b) give notice of the intention to make the application by the erection or fixing of a site
notice in accordance with article 19.
(2) Where the last day of the 2 week period referred to in sub-article (1) is a Saturday,
Sunday, a public holiday (within the meaning of the Organisation of Working Time Act 1997
(No. 20 of 1997)), or any other day on which the offices of the planning authority are closed,
the application shall be valid if received on the next following day on which the offices of the
planning authority are open.
(3) The requirement of sub-article (1)(b) shall not apply in relation to a planning application
for development consisting of the construction or erection by an electricity undertaking of
overhead transmission or distribution lines for conducting electricity, or development
consisting of the construction or erection by any statutory undertaker authorised to provide
a telecommunications service of overhead telecommunications lines.”
50. The art. 17 notices don’t involve a planning reference number – they are notices of intention
to apply. In isolation that suggests that as long as a valid application is lodged within two weeks of
the notice it doesn’t matter if an invalid notice is so lodged. But that reads the provision in isolation
from art. 26(5).
51. Article 19 of the 2001 regulations (as substituted by art. 8 of S.I. No. 685 of 2006 Planning
and Development Regulations 2006) provides (emphasis added):
“Site Notice.
19. (1) A site notice erected or fixed on any land or structure in accordance with article
17(1)(b) shall be—
(a) in the form set out at Form No. 1 of Schedule 3, or a form substantially to the like effect,
(b) subject to sub-article (4), inscribed or printed in indelible ink on a white background,
affixed on rigid, durable material and secured against damage from bad weather and other
causes, and
(c) subject to sub-article (2), securely erected or fixed in a conspicuous position on or near
the main entrance to the land or structure concerned from a public road, or where there is
more than one entrance from public roads, on or near all such entrances, or on any other
part of the land or structure adjoining a public road, so as to be easily visible and legible by
persons using the public road, and shall not be obscured or concealed at any time.
(2) Where the land or structure to which a planning application relates does not adjoin a
public road, a site notice shall be erected or fixed in a conspicuous position on the land or
structure so as to be easily visible and legible by persons outside the land or structure, and
shall not be obscured or concealed at any time.
(3) Where a planning authority considers that the erection or fixing of a single site notice is
not sufficient to comply with the requirements of subarticles (1) and (2), or does not
adequately inform the public, the authority may require the applicant to erect or fix such
further site notice or notices in such a manner and in such terms as it may specify and to
submit to the authority such evidence as it may specify in relation to compliance with any
such requirements.
(4) Where a valid planning application is made in respect of any land or structure,
and a subsequent application is made within 6 months from the date of making the
first-mentioned application in respect of land substantially consisting of the site or part
of the site to which the first-mentioned application related, in lieu of the requirements of
sub-article (1)(b), the site notice for the subsequent application shall be inscribed or printed
in indelible ink on a yellow background and affixed on rigid, durable material and be secured
against damage from bad weather and other causes.”
52. What can be said immediately is that art. 19(4) does not apply here because there was no
valid first planning application.
53. Form No. 1 in sch. 3 (substituted by art. 99(a) of S.I. No. 296 of 2018 European Union
(Planning and Development) (Environmental Impact Assessment) Regulations 2018) (subsequently
amended by the European Union (Planning and Development) (Renewable Energy) Regulations
2025 (S.I. No. 274 of 2025) and then by reg. 5 of the European Union (Planning and Development)
(Renewable Energy) (No. 2) Regulations 2025 (S.I. No. 426 of 2025), but that doesn’t affect the
present case) was as follows:
“Form no. 1 Article 19
Site notice
NAME OF PLANNING AUTHORITY1
SITE NOTICE
I, ...........................................2, intend to apply for permission/retention permission
/outline permission/permission consequent on the grant of outline permission (Ref. No. of
outline permission)3 for development at this
site................................................................................. 4
The development will consist/consists5 of ..................................................................6
The planning application may be inspected, or purchased at a fee not exceeding the
reasonable cost of making a copy, at the offices of the planning authority during its public
opening hours.
A submission or observation in relation to the application may be made in writing to the
planning authority on payment of the prescribed fee, €20, within the period of 5 weeks
beginning on the date of receipt by the authority of the application, and such submissions
or observations will be considered by the planning authority in making a decision on the
application. The planning authority may grant permission subject to or without conditions,
or may refuse to grant permission.
Signed:.......................................................................... 7
Date of erection of site notice.....................................8”
54. The notes to the form (as amended most recently by art. 7 of S.I. No. 655 of 2023 Planning
and Development (Amendment) (No. 3) Regulations 2023) are as follows:
“Directions for completing this notice
1. The name of the planning authority to which the planning application will be made should
be inserted here
2. The name of the applicant for permission (and not his or her agent) should be inserted
here
3. Delete as appropriate. The types of permission which may be sought are—
(a) permission,
(b) retention permission,
(c) outline permission,
(d) permission consequent on the grant of outline permission. If this type of
permission is being sought, the reference number on the planning register of the
relevant outline permission should be included
4. The location, townland or postal address of the land or structure to which the application
relates should be inserted here
5. Delete as appropriate. The present tense should be used where retention permission is
being sought
6. A brief description of the nature and extent of the development should be inserted here.
The description should include—
(a) where the application relates to development consisting of or comprising the
provision of houses, the number of houses to be provided. ‘Houses’ includes
buildings designed as 2 or more dwellings or flats, apartments or other dwellings
within a building,
(b) where the application relates to the retention of a structure, the nature of the
proposed use of the structure and, where appropriate, the period for which it is
proposed to retain the structure,
(c) where the application relates to development which would consist of or comprise
the carrying out of works to a protected structure or proposed protected structure,
an indication of that fact,
(d) where an environmental impact assessment report or Natura impact statement
has been prepared in respect of the planning application, an indication of that fact
(e) where the application relates to development which comprises or is for the
purposes of an activity requiring an integrated pollution control licence or a waste
licence, an indication of that fact,
(f) where a planning application relates to development consisting of the provision
of, or modifications to an establishment within the meaning of Part 11 of these
Regulations (Major Accidents Directive), an indication of that fact,
(g) where the application is accompanied by an opinion on unconfirmed details an
indication of that fact.
7. Either the signature of the applicant or the signature and contact address of the person
acting on behalf of the applicant should be inserted here
8. The date that the notice is erected or fixed at the site should be inserted here”
55. Article 20 (substituted by art. 8 of S.I. No. 685 of 2006 Planning and Development
Regulations 2006) provides:
“In addition to the requirements of article 17(1)(b), a site notice shall be maintained in
position on the land or structure concerned for a period of 5 weeks from the date of receipt
of the planning application by the planning authority, shall be renewed or replaced if it is
removed or becomes defaced or illegible within that period and shall be removed by the
applicant following the notification of the planning authority decision under article 31.”
56. Article 26 of the 2001 regulations (as amended most recently by art. 5 of S.I. No. 655 of
2023 Planning and Development (Amendment) (No. 3) Regulations 2023) provides (emphasis
added):
“Procedure on receipt of planning application.
26. (1) On receipt of a planning application, a planning authority shall consider whether the
applicant has complied with the requirements of articles 18, 19(1)(a) and 22 and, as may
be appropriate, of article 15J, 24 or 25.
(2) Where a planning authority considers that a planning application complies with the
requirements of articles 18, 19(1)(a) and 22 and, as may be appropriate, of article 24 or
25, it shall stamp each document with the date of its receipt
and—
(a) send to the applicant an acknowledgement stating the date of receipt of the application,
and
(b) if the application was accompanied by an EIAR, send to the EIA portal in electronic form
in the manner set out on the portal—
(i) a copy of the confirmation notice received in accordance with article 22(2)(ga),
(ii) the reference number of the application on the register, and
(iii) the URL to the documents placed on its website pursuant to section 38(3)(b) of
the Act.
(3) Where, following consideration of an application under sub-article (1), a planning
authority considers that-
(a) any of the requirements of articles 18, 19(1)(a) or 22 and, as may be appropriate, of
article 15J, 24 or 25 has not been complied with, or
(b) the notice in the newspaper or the site notice, because of its content or for any other
reason, is misleading or inadequate for the information of the public, the planning application
shall be invalid.
(4) Where, on inspection of the land to which the application relates, the planning authority
considers that the requirements of articles 17(1)(b), 19 or 20 have not been met, or the
information submitted in the planning application is substantially incorrect or substantial
information has been omitted, the planning application shall, notwithstanding the fact that
an acknowledgement has been sent to an applicant in accordance with sub-article (2), be
invalid.
(5) A planning authority shall as soon as may be after receipt of an invalid application-
(a) by notice in writing-
(i) inform the applicant that the application is invalid and cannot be considered by
the planning authority,
(ii) indicate which requirements of the permission regulations have not been
complied with, and
(iii) request the applicant to remove the site notice or notices erected or
fixed pursuant to article 17(1)(b).
(b) return to the applicant the planning application, including all particulars, plans, drawings
and maps, and
(c) enter an indication on the register that an invalid application has been made.
(6) Where a notice is served in accordance with subarticle (5) on an applicant, the planning
authority shall return to the applicant any fee paid with the application
(7) Sub-articles (3) and (4) shall not apply where the planning authority is satisfied that the
applicant complied with the provisions of articles 17, 18 and 19 but that any site notice
erected by the applicant has been maliciously defaced or destroyed by any person other
than the applicant.
(8) Where a notice is served in accordance with subarticle (5) on an applicant, the planning
authority shall by notice in writing—
(a) inform any person or body who has made a submission or observation in accordance
with article 29(1) of that fact and return any fee paid in respect of any such submission or
observation, and
(b) inform any body to whom notice was sent in accordance with article 28(2) of that fact.
(9) On receipt of a planning application, a planning authority shall make the planning
application available for inspection, or purchased at a fee not exceeding the reasonable cost
of making a copy at the offices of the planning authority during its public opening hours.”
Whether there was a legal breach in failure to remove the site notice and/or the failure
to erect a new notice
57. For reasons that will become apparent, there is a compelling logic in starting with the legal
merits before turning to whether time should be extended to bring the proceedings. The reason for
this is in essence:
(i) If the point has no merit, then whether time is extended or not makes no difference
to anything.
(ii) If the point has merit, then this is a case where the merits are directly relevant to
whether time is extended. This is not a case where one is saying that a dilatory
applicant should be given a chance to make what they say is an independently good
point. It is a case where the merits directly go to issues about whether delay was
outside the control of the applicant and/or there is good and sufficient reason for
extension of time.
58. The issue of whether there was a legal breach is not, in reality, a particularly complicated
one. It follows from art. 26(5) of the 2001 regulations that when an invalid application is made, the
site notice should be removed.
59. While the legislation uses the word “request”, any words in law have to be construed within
the generally imperative nature of the provision concerned. For example, judges are appointed on
the “advice” of the Government – but it isn’t mere advice. The Government’s proposal is imperative.
60. Thus when a council issues an art. 26(5) notice, that isn’t the end of their obligations. They
should also ensure that that notice is complied with by the taking down of the old site notice (which
is what the notification calls for) and by the erection of a new notice.
61. The requirement to remove the notice following an invalid application inevitably means that
when a valid application is made, there must then be a notice erected in place of the removed one.
Since the form of the notice includes the date of erection of the notice then that inevitably means
that the notice must be a new one (since the date of erection of the old notice is no longer operative
following its removal).
62. If one considers the context and intention of the regulations, they reinforce this conclusion.
The overarching context is the EU right to public participation, and the clear logic of the requirement
to remove the old notice is to alert the public concerned to the making of a new application, if one
is made, by requiring the putting in place of a new site notice.
63. Stress-testing this by asking what would happen if an old notice can remain in place results
in a clearly objectionable outcome – a person who has been made aware that the application is
invalid will have no reason, based on the continued display of the old invalid site notice, to think
anything other than that the application is at an end. That would be totally misleading – and on the
basis of the applicant’s affidavit was so misleading here. I appreciate the point that we are talking
about only a limited sub-set of the public here – those who are aware of the invalidity but unaware
of the new application – but the regulations don’t envisage that the provisions concerning public
notification can be disregarded if only a sub-set of the public would be thereby disadvantaged.
64. The inevitable conclusion is that the old site notice should have been removed and a fresh
one erected, and a planning authority in such a situation should ensure that this happens before
validating an application. The non-carrying out of these steps here meant that the process went
fundamentally wrong at that point.
65. Once we appreciate that the notice regarding removal of the invalid notice is not a mere
suggestion, it follows that the law requires such removal. That means there needs to be a new
notice. The form of the notice requires a statement of the date of erection, and a new notice
inherently must have a different and later date of erection. So it follows by inexorable logic from
the statutory scheme that a new site notice requires to be erected where a planning application has
been invalidated.
66. That is the flaw in the argument that the invalid site notice was fine because it was erected
within two weeks before the application. The notice party says:
“44. Without prejudice to the foregoing, no legal error has been identified in relation to
the site notice at all. No challenge has been brought in relation to the contents of the notice.
The Council were satisfied that the notice requirements were met, as is apparent from the
Affidavit of [the] Planner, who carried out an inspection.”
67. The problem with the notice was that it was not a new notice – that’s the critical pleaded
complaint. That complaint is correct because removal and erection of a second notice inherently
involves a new notice for the reasons outlined above.
68. Given that the failure to remove the invalid notice was an error, the onus is on the opposing
parties to show that any error was harmless: see e.g. H.A. v. Minister for Justice [2022] IECA 166,
[2022] 7 JIC 2201 (Unreported, Court of Appeal, Donnelly J., 22 July 2022) at para. 48. The onus
to do so has not been discharged here. An attempt to put the onus on the applicant to give further
details of prejudice would unfortunately misunderstand the law in this regard.
69. While also complaining about being misled by the notice himself, the applicant makes a
general argument on behalf of the public overall. But that is a ius tertii in the circumstances. In
general terms an applicant can’t have a decision quashed for an error that did not actually affect
herself (see for example O’Shea v. Kerry County Council [2003] IEHC 51, [2003] 4 I.R. 143, [2003]
9 JIC 0101 (Ó Caoimh J.) where the issue was the location of a site notice, but the applicant did not
suggest that she would have seen the notice had it been somewhere more visible). If there is some
fundamental absence of opportunity for public participation – say a site notice removed immediately
after a council’s site visit, or omitted altogether from an entrance adjoining a public road, then there
would be a case for relief on rule of law grounds, notwithstanding lack of proof of personal impact.
The logic of that is that if a problem is fundamental enough, then there is a probability rather than
a mere speculative possibility of the whole process having been compromised. But if the complaint
is something more nuanced than a catastrophic failure of notice, then a mere speculative possibility
that someone may have been disadvantaged isn’t enough, and an applicant has to show that they
themselves were affected by the breach. The applicant has done that here.
70. Insofar as there was a pleading objection in that regard, this is misconceived. The point
being made by the applicant is acceptably clear. Insofar as it is said that art. 19 is not expressly
pleaded, but if one reads the complaint in context it arises by necessary implication.
71. The applicant’s first, but crucially not only, pleaded complaint is breach of art. 26(5), which
required removal of the old notice. It axiomatically followed that if that had been complied with
then there would have had to be a new notice – something the applicant pleads expressly in the
next bullet point. The fact that the applicant hasn’t pleaded breach of art. 19(1) in relation to not
putting up a new notice doesn’t subtract anything of substance and doesn’t make the point
unacceptably unclear. Nobody could be in any doubt about the point being made by the applicant
on the existing pleadings.
72. The argument that pleadings have to cite chapter and verse in terms of statutory references
has already been rejected: Eco Advocacy v. An Bord Pleanála [2023] IEHC 713 (Unreported, High
Court, 18 December 2023) where it was described as “a fictitious standard confected by the applicant
to create an appeal – a standard which, as the developer points out, is being maintained despite the
fiction having already been exposed” (para 30). The standard is as to whether the point is acceptably
clear. To their credit, the other parties accepted that they could understand the point the applicant
was making in the second bullet point. Such an objection therefore would not have substance. The
omission of a reference to arts. 17 or 19(1) in the second bullet point of the grounds pleaded doesn’t
mean that the applicant can’t rely on that because the application of that provision is not only
acceptably clear but totally obvious by necessary implication.
73. The applicant’s pleaded case is not limited to art. 26(5). As adverted to above, he goes on
to say:
“• The Applicant contends that a fresh site notice should have been erected for the new
application, with a new date, regardless of whether the content was the same, in order to
provide proper and transparent public notice and allow for public participation.
• The failure to erect a new site notice deprived the Applicant and the community of
their statutory right to be informed of, and to participate in, the planning process.”
74. While these complaints are not accompanied by specific reference to the relevant articles of
the 2001 regulations, the references are obvious and not in doubt. The duty to erect a fresh site
notice arises under arts. 17(1)(b) and 19(1), and indeed by definition on the art. 26(5) notice being
complied with.
75. It is not the law that an applicant must provide exact statutory citations – the requirement
is to make the point with acceptable clarity. That has been done, and the other parties don’t claim
not to know under what provision there would have been an obligation to erect a fresh notice. The
objection is that that plea is not accompanied by a specific statutory reference. That is not a valid
objection if the actual point is acceptably clear. The applicant’s case, in short, is not just limited to
art. 26(5).
76. As regards the alleged disproportionality of relief, certiorari would not be disproportionate.
The process of public participation was undermined in a way that affected the applicant. It would
be disproportionate to make the applicant bear the responsibility of that by losing the opportunity
to participate in any fresh application following the potential quashing of the decision (remittal
couldn’t be lawful where the whole basis of potential certiorari is the lack of a valid site notice).
77. As regards discretion, insofar as it could be argued that the present challenge is technical in
nature, that is inherent in the fact that the applicant is challenging being shut out of the process so
inevitably the challenge will be technical in focus. As to the argument that none of this makes any
difference because Mr Croft’s objections to the development were raised by other participants in the
process, that is speculative and inadequate as a response. Had Mr Croft been aware of the
application and had the opportunity to participate he would have had additional procedural rights
such as appeal to the commission for example, let alone judicial review of the substance. So this is
not a satisfactory answer to the claim, and I deal later with whether this position is in doubt as a
matter of EU law.
78. The importance of the giving of proper notice of planning applications has been emphasised
since the early days of planning law. All of the above is reinforced (but I came to these conclusions
anyway) by two authorities that helpfully came to my attention subsequent to the hearing.
79. Firstly there is the decision in Keleghan v. Corby and Dublin Corporation (1976) 111 I.L.T.R.
144, where McMahon J. quashed a permission granted by the city council where the notice originally
given had been inadequate, the inadequacy relating in that case to the omission of reference to
access changes that would have been involved in the project. McMahon J. noted and relied on the
provisions of the relevant legislation (s. 26 of the Local Government (Planning and Development)
Act 1963) to the effect that an application for permission had to be made in accordance with the
regulations – now s. 34(1) of the 2000 Act, to which I will shortly come.
80. Secondly there is the decision of Peart J. in Marshall v. Arklow Town Council [2004] IEHC
313, [2004] 4 I.R. 92 in which he said the following about failure by a council to strictly comply with
the site notice procedures (worth quoting at length):
“It is beyond any dispute that the planning authority did not during the 5 week period
concerned carry out any inspection of the site which enabled them to be satisfied that the
site notice was in place and that it conformed to the regulations. That fact if [sic] admitted.
All we know is that on the 4th February 2004, some 12 days or so after the expiration of the
5 week period, the side notice was not in place, and that fact was reported to the appropriate
officer within the Respondent, and that he or she misinterpreted the standard form and
believed that the form showed that a site notice was in place when the inspection took place.
That misinterpretation is also a matter not in dispute.
Mr Dunne has stated that inspections are carried out on a random basis, but that between
80% and 90% of sites are in fact inspected. That means that 10% to 20% of sites do not
get inspected and there is therefore a possibility, however long the odds, that the absence
of any site notice will not be spotted before an application is granted. In those circumstances
the persons whose interests are protected by the requirement to erect a site notice have
received no protection at all. It is true that Article 17(1)(a) of the Regulations requires the
insertion in a newspaper of an intention to apply for permission, but for that to be a failsafe
method, or even a reasonable method of protecting the interests of persons likely to be
affected. It would be necessary for citizens each day to purchase a copy of each newspaper
in which such a notice might appear. It was presumably to give added protection to citizens
likely to be affected by a planning permission, that the legislature introduced the additional
safeguard of requiring a site notice to be put into position in a conspicuous manner at the
proposed site.
It follows that the requirement of having a site notice in place and in conformity with the
Regulations is a very important requirement. The purpose which it serves is a vital one, if
the intention of the legislature that each person likely to be affected by a planning decision
shall have the right to lodge an objection and have their views heard before a planning
decision is made, is to be achieved. The Regulations themselves, to which I have referred,
reflect the importance which is attached to the right of such persons to be on notice of an
intended application. Firstly in Article 17(1) there is the requirement upon the applicant for
permission to give notice in the newspaper and by the erection of the site notice. These
notices must conform to strictly defined specifications as to clarity, visibility and content, as
provided in Article 18 in respect of the newspaper notice, and as provided in Article 19(a)(b)
and (c) in respect of the site notice. Article 19(3) goes on to provide that where the authority
considers that a single site notice at a site is insufficient or ‘does not adequately inform the
public’, the authority may require further steps to be taken as set forth therein. Article 20
proceeds to state that the site notice must be in place and maintained for a period of 5
weeks from the date of the application. That is a lengthy period from which the importance
attached to the site notice can be gleaned.
Turning then to Article 26 it is apparent immediately that there are certain powers given to
or duties imposed upon a planning authority in relation to applications made to it for planning
permission. It sets out what shall happen on receipt of an application, such as sub-article
(1) which provides that each document received will be stamped with the date of its receipt,
and sub-article (2) which provides that the authority shall consider at that stage whether
the applicant has complied with the requirements as to the content of the newspaper notice
(Article 18) and whether the copy site notice submitted with the application conforms with
Form No. 1 of Schedule 3 of the Regulations (Article 19(1)(a) ), and whether the application
documentation complies with Article 22, and possibly also Articles 24 or 25.
Once the authority is satisfied that the documents comply with these requirements, it is
mandated by Article 26(2) then to send a receipt of same to the applicant. Where on the
other hand having so considered the documents, the authority considers that any of these
requirements as to the newspaper notice, the copy of the site notice intended to be erected,
or the documents generally do not comply, then it is provided that the application ‘shall be
invalid’.
Importantly for the present case, Article 26(4) then provides, as I have already set forth,
that where on inspection of the land, the planning authority considers that the requirements
of Article 17(1)(b) or 19 (the erection of an appropriate site notice, but not its maintenance
for 5 weeks which is a requirement of Article 20), have not been complied with, the
application ‘shall be invalid’, notwithstanding that it has been acknowledged pursuant to the
provisions of sub-article (2) of Article 26. It is only where the authority is satisfied, as stated
in sub-article (7) that the reason for the non-existence of the site notice on the date of
inspection is due to malicious defacing or destruction that the provisions of Article 26( 3) or
(4) shall not apply.
I have set out these provisions in some detail again in order to highlight the care which has
been taken to create a structured procedure for dealing with planning applications. Each
step is clearly set out. It is clearly envisaged that the planning authority shall (not ‘may’ or
shall to the best of its ability’ or ‘shall, as far as may be practicable’) on inspection of the
land consider whether the requirements of the Regulations as far as the site notice is
concerned have been complied with. The only matter left in some doubt is how the authority
ought to ensure that the notice has been maintained in place for the five week period and
not just for a period which happened to include the actual date of inspection. But in my
view there is no room whatsoever to conclude that, because that matter is not clearly spelt
out, there is no obligation as such to carry out an inspection at all within that five week
period. The intention is clear from the wording of the Regulations themselves and the
particular provisions to which I have referred. It is perhaps clearest in Article 26(4) of the
Regulations. If no inspection is carried out within that five week period, and that is the
admitted situation in this case, then the Decision subsequently contains a legal infirmity and
must be quashed, since there has not been compliance with provisions of s. 34(1) of the
2000 Act which provides:
‘Where —'
(a) an application is made to a planning authority in accordance with permission regulations
for permission for the development of land, and
(b) all requirements of the regulations are complied with
the authority may decide to grant the permission subject to or without conditions, or to
refuse it.’ (my emphasis)
In the instant case, ‘all requirements of the regulation’ have not been complied with, and it
follows that the interests intended and sought to be protected by the existence of these
regulations have not been protected by the planning authority. The consequences of non-
compliance with Article 26(4) are spelt out in that article—the application ‘shall be invalid.’
Since all the regulations were not complied with, this application for permission was invalid,
and it follows therefore that the Respondent had no power to make the Decision to Grant
Planning Permission dated the 18th February 2004, and I therefore grant the relief sought
at paragraph (a) in the Statement of Grounds filed herein on the 28th April 2004.”
81. Section 34(1) of the 2000 Act retains the same form at the material time for the purposes
of this case (emphasis added):
“34.—(1) Where—
(a) an application is made to a planning authority in accordance with permission
regulations for permission for the development of land, and
(b) all requirements of the regulations are complied with,
the authority may decide to grant the permission subject to or without conditions, or to
refuse it.”
82. The letter from the respondent calling on the developer to remove the site notice for the
invalid application is not a suggestion – compliance with that letter is compliance with one of the
requirements of the regulations. The application was not made in accordance with permission
regulations, and all requirements of the regulations were not complied with. Non-compliance
deprived the respondent of jurisdiction to grant the permission by reason of s. 34(1)(a) and (b) of
the 2000 Act.
83. Admittedly, the applicant didn’t expressly refer to s. 34(1), but in context I prefer to see the
section as reinforcing a legal consequence that flows from a breach that the applicant has pleaded,
so it is more in the nature of a matter that the court can take into account as part of the legal
analysis than a matter which cannot be weighed at all unless expressly adverted to in a statement
of grounds.
84. The overall conclusion is that the permission should be quashed if time is extended. As to
discretion, it is one thing to exercise discretion against relief for technical slip-ups that don’t make
much of a difference to much of anything (that type of situation is a classic case of what discretion
is designed for), but it would be generally inappropriate for that be exercised against an applicant
who was actually disadvantaged in a tangible way as a result of a breach.
85. While I appreciate this is not the conclusion they argued for, nobody could have put the case
more persuasively or effectively than the notice party’s lawyers here.
86. With the foregoing firmly in mind we can now turn to the application for the extension of
time.
Extension of time – legal context
87. The legal context for extension of time has been set out in Thompson v. An Bord Pleanála
(No. 4) [2025] IEHC 161 (Unreported, High Court, 21 March 2025) and I can repeat some of that
discussion here.
European Union law
88. Articles 41 and 47 of the EU Charter of Fundamental Rights of the European Union (2000/C
364/01) provide:
“Article 41
Right to good administration
1. Every person has the right to have his or her affairs handled impartially, fairly and within
a reasonable time by the institutions and bodies of the Union.
2. This right includes:
– the right of every person to be heard, before any individual measure which would
affect him or her adversely is taken;
– the right of every person to have access to his or her file, while respecting the
legitimate interests of confidentiality and of professional and business secrecy;
– the obligation of the administration to give reasons for its decisions.
3. Every person has the right to have the Community make good any damage caused by its
institutions or by its servants in the performance of their duties, in accordance with the
general principles common to the laws of the Member States.
4. Every person may write to the institutions of the Union in one of the languages of the
Treaties and must have an answer in the same language.
…
Article 47
Right to an effective remedy and to a fair trial
Everyone whose rights and freedoms guaranteed by the law of the Union are violated has
the right to an effective remedy before a tribunal in compliance with the conditions laid down
in this Article.
Everyone is entitled to a fair and public hearing within a reasonable time by an independent
and impartial tribunal previously established by law. Everyone shall have the possibility of
being advised, defended and represented.
Legal aid shall be made available to those who lack sufficient resources in so far as such aid
is necessary to ensure effective access to justice.”
89. Article 6 of Directive 2011/92/EU of the European Parliament and of the Council of 13
December 2011 on the assessment of the effects of certain public and private projects on the
environment (the EIA directive) provides:
“1. Member States shall take the measures necessary to ensure that the authorities
likely to be concerned by the project by reason of their specific environmental responsibilities
or local and regional competences are given an opportunity to express their opinion on the
information supplied by the developer and on the request for development consent, taking
into account, where appropriate, the cases referred to in Article 8a(3). To that end, Member
States shall designate the authorities to be consulted, either in general terms or on a case-
by-case basis. The information gathered pursuant to Article 5 shall be forwarded to those
authorities. Detailed arrangements for consultation shall be laid down by the Member
States.
2. In order to ensure the effective participation of the public concerned in the decision-
making procedures, the public shall be informed electronically and by public notices or by
other appropriate means, of the following matters early in the environmental decision-
making procedures referred to in Article 2(2) and, at the latest, as soon as information can
reasonably be provided:
(a) the request for development consent;
(b) the fact that the project is subject to an environmental impact assessment procedure
and, where relevant, the fact that Article 7 applies;
(c) details of the competent authorities responsible for taking the decision, those from which
relevant information can be obtained, those to which comments or questions can be
submitted, and details of the time schedule for transmitting comments or questions;
(d) the nature of possible decisions or, where there is one, the draft decision;
(e) an indication of the availability of the information gathered pursuant to Article 5;
(f) an indication of the times and places at which, and the means by which, the relevant
information will be made available;
(g) details of the arrangements for public participation made pursuant to paragraph 5 of this
Article.
3. Member States shall ensure that, within reasonable time-frames, the following is
made available to the public concerned:
(a) any information gathered pursuant to Article 5;
(b) in accordance with national legislation, the main reports and advice issued to the
competent authority or authorities at the time when the public concerned is informed in
accordance with paragraph 2 of this Article;
(c) in accordance with the provisions of Directive 2003/4/EC of the European Parliament and
of the Council of 28 January 2003 on public access to environmental information ( 7 ),
information other than that referred to in paragraph 2 of this Article which is relevant for the
decision in accordance with Article 8 of this Directive and which only becomes available after
the time the public concerned was informed in accordance with paragraph 2 of this Article.
4. The public concerned shall be given early and effective opportunities to participate
in the environmental decision-making procedures referred to in Article 2(2) and shall, for
that purpose, be entitled to express comments and opinions when all options are open to
the competent authority or authorities before the decision on the request for development
consent is taken.
5. The detailed arrangements for informing the public, for example by bill posting within
a certain radius or publication in local newspapers, and for consulting the public concerned,
for example by written submissions or by way of a public inquiry, shall be determined by the
Member States. Member States shall take the necessary measures to ensure that the
relevant information is electronically accessible to the public, through at least a central portal
or easily accessible points of access, at the appropriate administrative level.
6. Reasonable time-frames for the different phases shall be provided for, allowing
sufficient time for:
(a) informing the authorities referred to in paragraph 1 and the public; and
(b) the authorities referred to in paragraph 1 and the public concerned to prepare and
participate effectively in the environmental decision-making, subject to the provisions of this
Article.
7. The time-frames for consulting the public concerned on the environmental impact
assessment report referred to in Article 5(1) shall not be shorter than 30 days.”
90. Article 11 of the EIA directive provides:
“1. Member States shall ensure that, in accordance with the relevant national legal
system, members of the public concerned:
(a) having a sufficient interest, or alternatively;
(b) maintaining the impairment of a right, where administrative procedural law of a Member
State requires this as a precondition;
have access to a review procedure before a court of law or another independent and impartial
body established by law to challenge the substantive or procedural legality of decisions, acts
or omissions subject to the public participation provisions of this Directive.
2. Member States shall determine at what stage the decisions, acts or omissions may
be challenged.
3. What constitutes a sufficient interest and impairment of a right shall be determined
by the Member States, consistently with the objective of giving the public concerned wide
access to justice. To that end, the interest of any non-governmental organisation meeting
the requirements referred to in Article 1(2) shall be deemed sufficient for the purpose of
point (a) of paragraph 1 of this Article. Such organisations shall also be deemed to have
rights capable of being impaired for the purpose of point (b) of paragraph 1 of this Article.
4. The provisions of this Article shall not exclude the possibility of a preliminary review
procedure before an administrative authority and shall not affect the requirement of
exhaustion of administrative review procedures prior to recourse to judicial review
procedures, where such a requirement exists under national law.
Any such procedure shall be fair, equitable, timely and not prohibitively expensive.
5. In order to further the effectiveness of the provisions of this Article, Member States
shall ensure that practical information is made available to the public on access to
administrative and judicial review procedures.”
91. Article 6(1) and (9) of the Convention on Access to Information, Public Participation in
Decision-Making and Access to Justice in Environmental Matters (done at Aarhus on 25 June 1998,
entered into force 30 October 2001) 2161 UNTS 447 (the Aarhus Convention), approved on behalf
of the European Community by Council Decision 2005/370 of 17 February 2005 provides:
“1. Each Party: (a) Shall apply the provisions of this article with respect to decisions on
whether to permit proposed activities listed in annex I;
(b) Shall, in accordance with its national law, also apply the provisions of this article to
decisions on proposed activities not listed in annex I which may have a significant effect on
the environment. To this end, Parties shall determine whether such a proposed activity is
subject to these provisions; and
(c) May decide, on a case-by-case basis if so provided under national law, not to apply the
provisions of this article to proposed activities serving national defence purposes, if that
Party deems that such application would have an adverse effect on these purposes.
…
9. Each Party shall ensure that, when the decision has been taken by the public authority,
the public is promptly informed of the decision in accordance with the appropriate
procedures. Each Party shall make accessible to the public the text of the decision along
with the reasons and considerations on which the decision is based.”
92. Article 9(3) of the Aarhus Convention provides:
“3. In addition and without prejudice to the review procedures referred to in paragraphs 1
and 2 above, each Party shall ensure that, where they meet the criteria, if any, laid down in
its national law, members of the public have access to administrative or judicial procedures
to challenge acts and omissions by private persons and public authorities which contravene
provisions of its national law relating to the environment.”
Domestic law
93. Section 50(6) to (8) of the 2000 Act provides:
“(6) Subject to subsection (8), an application for leave to apply for judicial review under the
Order in respect of a decision or other act to which subsection (2)(a) applies shall be made
within the period of 8 weeks beginning on the date of the decision or, as the case may be,
the date of the doing of the act by the planning authority, the local authority or the Board,
as appropriate.
(7) [not applicable]
(8) The High Court may extend the period provided for in subsection (6) or (7) within which
an application for leave referred to in that subsection may be made but shall only do so if it
is satisfied that—
(a) there is good and sufficient reason for doing so, and
(b) the circumstances that resulted in the failure to make the application for leave within
the period so provided were outside the control of the applicant for the extension.”
94. Reference to “the Order” means O. 84 of the Rules of the Superior Courts.
95. As far as the test in the judgment of 18 October 2012, Pelati v Republika Slovenija, C-
603/10, ECLI:EU:C:2012:639 is concerned, the starting point for the running of time is
unambiguously and foreseeably set out in domestic law as being the date of the decision itself.
Under domestic law, time runs from that date even if that is not known to anyone at the time other
than to the decision-taker.
96. Order 84 r. 21(1) RSC which applies to judicial review generally is consistent with the special
rule in s. 50(6) of the 2000 Act. It provides:
“(2) Where the relief sought is an order of certiorari in respect of any judgement, order,
conviction or other proceeding, the date when grounds for the application first arose shall
be taken to be the date of that judgement, order, conviction or proceeding.”
97. The term “proceeding” is in practice normally applied to administrative proceedings, so that
time for a challenge runs from the date of the decision rather than notification.
98. The way the domestic legislation operates (subject to any contrary requirement of EU law)
is that:
(i) if the applicant does not know of the decision at the outset of the eight weeks, but
learns of it during that period in sufficient time to be capable of bringing a challenge
before the expiry of the period, then they have the balance of the eight weeks but
no more and are not eligible for an extension of time if they fail to do so, because
that failure was not outside their control (that is the effect of the mandatory and
cumulative nature of section 50(8)(a) and (b) of the 2000 Act); and
(ii) if the applicant learns or was only capable of learning with reasonable diligence of
the decision either so late in the eight-week period that it is not possible to challenge
the decision by the end of that period, or after the expiry of that period, then not
only are they eligible for an extension of time but they should be given an extension
equivalent to a full period of eight weeks running from the date they knew or ought
to have known of the decision: see Arthropharm (Europe) Ltd v. The Health Products
Regulatory Authority [2022] IECA 109, [2022] 5 JIC 1003 (Unreported, Court of
Appeal, Murray J., 10 May 2022); Marshall v. Kildare County Council [2023] IEHC
73, [2023] 2 JIC 1705 (Unreported, High Court, 17 February 2023).
Application of the foregoing to the facts here
99. The first leg of the test for extension of time is whether the failure to act within eight weeks
of the decision is outside the control of the applicant. Only if that is satisfied do we go on to consider
whether there is good and sufficient reason for an extension.
100. The issue here is whether a failure to understand that a planning decision has been made is
outside an applicant’s control if the applicant has been subjectively unaware of the application due
to the lack of compliance with the site notice provisions of the regulations, even if there were other
channels of notification he could have availed of.
101. If such unawareness satisfies that test, then it axiomatically would constitute good and
sufficient reason for an extension for any proceedings brought within eight weeks of knowledge:
Arthropharm. Much of the opposing submissions regarding extension of time merely involved
plucking cases where extensions were refused out of context and attempting to hold them against
this applicant in radically different circumstances.
102. The upshot is that had the matter been contested further I would have referred it to the
CJEU. In the light of that, the notice party stated that she was not in a position to shoulder the
defence of the proceedings given the respondent’s concession and the court’s decision to consult the
CJEU. For the record, the questions of EU law regarding time that would have arisen had the
opposition to extension of time been pursued were along the following lines:
First question
Do Articles 41 and/or 47 of the EU Charter of Fundamental Rights and/or Articles
6 and/or 11 of Directive 2011/92 read in the light of the general EU law principle
of legal certainty and/or of Articles 6 and/or 9 the Aarhus Convention as approved
on behalf of the European Community by Council Decision 2005/370, have the
effect, in the context of a challenge to a decision to authorise a project where the
need for environmental impact assessment under Directive 2011/92 was
considered and rejected at screening stage and where the need for appropriate
assessment under Directive 92/43 was screened out, that domestic law on the
extension of time to bring a challenge should be read to the extent possible in a
sense favourable to an extension of time where the failure of an applicant to
challenge such a decision within the ordinary time for such challenge was
contributed to by a failure by the developer to comply with the law of the Member
State concerned regarding any given channel of notification of the application for
such authorisation, in particular where the breach relates to a failure regarding
removal of a site notice associated with an invalid application and the erection of
a new notice for a subsequent fresh application?
Second question
If the answer to the first question is in general No, do those provisions have that
effect where the relevant competent authority of the Member State was or ought
to have been aware of facts sufficient to demonstrate the failure in compliance
with domestic law by the developer but failed to ensure compliance with the
requirements of the law of the Member State concerned regarding the relevant
channel of notification of the application for such authorisation?
Third question
If the answer to the first and/or second questions is Yes, is that answer affected
by the existence of other channels for the provision of information regarding the
making of a new application which an applicant could have availed of but did not
(for example online information), in circumstances where the domestic law of the
Member State concerned provides for independent channels of notification
including a site notice as one channel for such information, and where the domestic
legal recruitments in relation to such a channel were breached in a manner that as
a matter of fact impaired the applicant in bringing proceedings within the ordinary
time fixed by domestic law of the Member State concerned?
103. I was considering a further question on the scope of discretion in EU law matters but we
never got to the stage of parties’ submissions on it. Since the original draft judgment, my attention
has been drawn to a number of CJEU decisions (for example the judgment of 25 June 2020, A and
Others v Gewestelijke stedenbouwkundige ambtenaar van het departement Ruimte Vlaanderen,
afdeling Oost-Vlaanderen, C-24/19, ECLI:EU:C:2020:503 (Grand Chamber)) which in effect have
already given an answer to this question – the role of discretion following a breach of EU law is
extremely limited. So my current view is that any argument for the exercise of discretion is acte
clair (against the developer).
104. I appreciate that the developer was concerned at losing a potential purchaser for the site.
If one considers that as an isolated complaint, divorced from how the issue arose, that sounds
extremely weighty. However what the developer was not highlighting is that this was unfortunately
a self-induced problem due to a combination of:
(i) The initial breach of law by failing to use a correct wording for the newspaper notice
– the developer (and/or her servants or agents) is 100% responsible for that, and
the respondent commendably picked that up.
(ii) The further breach of law by or on behalf of the developer by not removing the old
site notice as stated in the notice received from the respondent – the developer
(and/or her servants or agents) is 100% responsible for that breach happening in
the first place also. The respondent commendably sent the notice about removal as
required by the permission regulations, but unfortunately the logical consequence of
that was that the new application should not have been validated unless and until
the respondent’s notice had actually been complied with.
105. It would have been unfair to the applicant to visit the consequences of the developer’s
defaults (including her servants or agents) on him for present purposes. Hardship to a party innocent
of a legal breach is generally, and is here, of greater weight than the hardship of requiring a party
to bear the interlocutory consequences of their own defaults.
106. Also, given the already-noted clear potential jurisprudential overlap with the issues to be
debated in Thompson, I would have proposed to invite the CJEU to consider joinder of the two cases
had the reference gone ahead.
107. To conclude on this and leaving counterfactual what-ifs aside, in the absence of the time
objection being pursued in the circumstances set out, I am satisfied that time should be extended
on the facts here.
Order
108. For the foregoing reasons, it is ordered, by consent of the respondent and without the notice
party pursuing an objection, that:
(i) time be extended for the bringing of the proceedings up to the date of the initiation
of the proceedings pursuant to s. 50(8) of the 2000 Act;
(ii) there be an order of certiorari quashing the decision of the respondent, dated 30
September 2024 (reg. ref. LRD6053/24-S3A), to grant planning permission subject
to 26 conditions to the notice party for a proposed development comprising a LRD
(consisting, inter alia, of the demolition of existing buildings and structures on site
and the construction of a mixed-use development comprising a single block including
221 purpose-built student accommodation bedspaces and café) at a c. 0.24 ha site
on lands at Church Lane and Swords Road, Santry, Dublin 9;
(iii) the applicant be entitled to recover, as against the respondent, such outlay and other
out-of-pocket expenses as are properly allowable in relation to these proceedings,
in accordance with the general principles governing legal costs, with such outlay and
other out-of-pocket expenses to be adjudicated in default of agreement (together
with the costs of legal costs adjudication if it arises); and
(iv) there be otherwise no order as to costs.