High Court refers question on Article 6(3) Directive 92/43 interpretation to CJEU regarding wind farm screening.
Legislator summary
AI generatedThe High Court refused to answer the preliminary question directly, instead ordering a referral to the Court of Justice of the European Union under Article 267 TFEU. The applicant challenged a wind farm planning permission, arguing that the competent authority failed to screen the project against the conservation objectives of the relevant Special Protection Area. The court determined that the interpretation of Article 6(3) of Directive 92/43 was not yet settled by existing case law, necessitating a reference to the CJEU for a definitive ruling on the scope of the screening exercise.
Legislator headnote
AI generatedArticle 6(3) of Directive 92/43; Article 267 TFEU: The interpretation of whether a screening exercise must consider conservation objectives of a Special Protection Area is a question of EU law requiring a preliminary ruling from the Court of Justice of the European Union.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
[2025] IEHC 218
THE HIGH COURT
PLANNING & ENVIRONMENT
[H.JR.2024.0000037]
IN THE MATTER OF AN APPLICATION PURSUANT TO SECTION 50, 50A AND 50B OF THE
PLANNING AND DEVELOPMENT ACT 2000
BETWEEN
PADDY MASSEY
APPLICANT
AND
AN BORD PLEANÁLA, IRELAND AND THE ATTORNEY GENERAL, MINISTER FOR HOUSING,
LOCAL GOVERNMENT AND HERITAGE
RESPONDENTS
AND
CURNS ENERGY LIMITED
NOTICE PARTY
(No. 3)
JUDGMENT of Humphreys J. delivered on Friday the 11th day of April 2025
Subject-matter of the dispute
1. This request for a preliminary ruling concerns the interpretation of Article 6(3) of Directive
92/43.
2. The request is being made in proceedings concerning a challenge to a planning permission
to the notice party for development of a wind farm and associated infrastructure on the
Cork/Waterford border. Details are set out at https://www.lyrenacarrigawindfarm.com/. The
development is to include 17 wind turbines within two clusters, a substation and a lithium ion battery
storage facility co-located with the substation. The project relates to renewable energy
infrastructure covered by Article 16(6) of Directive 2018/2001 as amended by Directive 2023/2413.
Insofar as concerns an order quashing the permission, this is being refused by the referring court.
However a question of interpretation of EU law arises in connection with declaratory relief.
Legal context
European Union law
3. Article 3 of Directive 93/43 provides:
“1. A coherent European ecological network of special areas of conservation shall be set up
under the title Natura 2000. This network, composed of sites hosting the natural habitat
types listed in Annex I and habitats of the species listed in Annex II, shall enable the natural
habitat types and the species' habitats concerned to be maintained or, where appropriate,
restored at a favourable conservation status in their natural range.
The Natura 2000 network shall include the special protection areas classified by the Member
States pursuant to Directive 79/409/EEC.
2. Each Member State shall contribute to the creation of Natura 2000 in proportion to the
representation within its territory of the natural habitat types and the habitats of species
referred to in paragraph 1. To that effect each Member State shall designate, in accordance
with Article 4, sites as special areas of conservation taking account of the objectives set out
in paragraph 1.
3. Where they consider it necessary, Member States shall endeavour to improve the
ecological coherence of Natura 2000 by maintaining, and where appropriate developing,
features of the landscape which are of major importance for wild fauna and flora, as referred
to in Article 10.”
4. Article 6 of Directive 93/43 provides:
“1. For special areas of conservation, Member States shall establish the necessary
conservation measures involving, if need be, appropriate management plans specifically
designed for the sites or integrated into other development plans, and appropriate statutory,
administrative or contractual measures which correspond to the ecological requirements of
the natural habitat types in Annex I and the species in Annex II present on the sites.
2. Member States shall take appropriate steps to avoid, in the special areas of conservation,
the deterioration of natural habitats and the habitats of species as well as disturbance of the
species for which the areas have been designated, in so far as such disturbance could be
significant in relation to the objectives of this Directive.
3. Any plan or project not directly connected with or necessary to the management of the
site but likely to have a significant effect thereon, either individually or in combination with
other plans or projects, shall be subject to appropriate assessment of its implications for the
site in view of the site's conservation objectives. In the light of the conclusions of the
assessment of the implications for the site and subject to the provisions of paragraph 4, the
competent national authorities shall agree to the plan or project only after having
ascertained that it will not adversely affect the integrity of the site concerned and, if
appropriate, after having obtained the opinion of the general public.
4. If, in spite of a negative assessment of the implications for the site and in the absence
of alternative solutions, a plan or project must nevertheless be carried out for imperative
reasons of overriding public interest, including those of a social or economic nature, the
Member State shall take all compensatory measures necessary to ensure that the overall
coherence of Natura 2000 is protected. It shall inform the Commission of the compensatory
measures adopted.
Where the site concerned hosts a priority natural habitat type and/or a priority species, the
only considerations which may be raised are those relating to human health or public safety,
to beneficial consequences of primary importance for the environment or, further to an
opinion from the Commission, to other imperative reasons of overriding public interest.”
5. Article 7 of the Directive provides:
“Obligations arising under Article 6 (2), (3) and (4) of this Directive shall replace any
obligations arising under the first sentence of Article 4 (4) of Directive 79/409/EEC in respect
of areas classified pursuant to Article 4 (1) or similarly recognized under Article 4 (2) thereof,
as from the date of implementation of this Directive or the date of classification or recognition
by a Member State under Directive 79/409/EEC, where the latter date is later.”
6. Directive 79/409 was replaced by Directive 2009/147. Articles 3 and 4 of the latter Directive
provide:
“Article 3
1. In the light of the requirements referred to in Article 2, Member States shall take the
requisite measures to preserve, maintain or re-establish a sufficient diversity and area of
habitats for all the species of birds referred to in Article 1.
2. The preservation, maintenance and re-establishment of biotopes and habitats shall
include primarily the following measures:
(a) creation of protected areas;
(b) upkeep and management in accordance with the ecological needs of habitats inside and
outside the protected zones;
(c) re-establishment of destroyed biotopes;
(d) creation of biotopes.
Article 4
1. The species mentioned in Annex I shall be the subject of special conservation measures
concerning their habitat in order to ensure their survival and reproduction in their area of
distribution.
In this connection, account shall be taken of:
(a) species in danger of extinction;
(b) species vulnerable to specific changes in their habitat;
(c) species considered rare because of small populations or restricted local distribution;
(d) other species requiring particular attention for reasons of the specific nature of their
habitat.
Trends and variations in population levels shall be taken into account as a background for
evaluations.
Member States shall classify in particular the most suitable territories in number and size as
special protection areas for the conservation of these species in the geographical sea and
land area where this Directive applies.
2. Member States shall take similar measures for regularly occurring migratory species not
listed in Annex I, bearing in mind their need for protection in the geographical sea and land
area where this Directive applies, as regards their breeding, moulting and wintering areas
and staging posts along their migration routes. To this end, Member States shall pay
particular attention to the protection of wetlands and particularly to wetlands of international
importance.
3. Member States shall send the Commission all relevant information so that it may take
appropriate initiatives with a view to the coordination necessary to ensure that the areas
provided for in paragraphs 1 and 2 form a coherent whole which meets the protection
requirements of these species in the geographical sea and land area where this Directive
applies.
4. In respect of the protection areas referred to in paragraphs 1 and 2, Member States
shall take appropriate steps to avoid pollution or deterioration of habitats or any disturbances
affecting the birds, in so far as these would be significant having regard to the objectives of
this Article. Outside these protection areas, Member States shall also strive to avoid
pollution or deterioration of habitats.”
Domestic law
7. Section 37E of the Planning and Development Act 2000 (the 2000 Act)
(https://revisedacts.lawreform.ie/eli/2000/act/30/section/37E/revised/en/html#:~:text=37E.,resp
ect%20of%20the%20proposed%20development) allows direct applications to An Bord Pleanála (the
board) for development consent for strategic infrastructure development (SID).
8. Blackwater Callows SPA is a site designated for the purposes of Directive 2009/147. It was
provided for by the European Communities (Conservation of Wild Birds (Blackwater Callows Special
Protection Area 004094)) Regulations 2012 (S.I. No. 191 of 2012)
(https://www.irishstatutebook.ie/eli/2012/si/191/made/en/print), which includes the Whooper
Swan (Cygnus cygnus) as a qualifying interest.
9. The European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477 of
2011) (https://www.irishstatutebook.ie/eli/2011/si/477/made/en/print) transposes the Directives
referred to above. Article 26 provides:
“Conservation objectives and measures to be undertaken by the Minister
26. (1) The Minister shall exercise his or her functions relating to nature conservation so as
to secure compliance with the requirements of the Habitats Directive and the Birds Directive.
(2) The Minister shall establish such particular conservation objectives as he or she, from
time to time, considers necessary to achieve the maintenance of the habitat types or species
in respect of which a site has been identified as a European Site at favourable conservation
status or their restoration to such favourable status.
(3) The Minister may, where he or she considers it would contribute to the achievement of
the objective of Article 3(1) of the Habitats Directive, namely to enable the natural habitat
types listed in Annex I to that Directive and the habitats of the species listed in Annex II to
that Directive to be maintained at or, where appropriate, restored to a favourable
conservation status in their natural range, establish the conservation or restoration of such
a habitat type or the habitat of such a species as a conservation objective of a site.
(4) The Minister shall, having established conservation objectives under paragraph (2) or
(3) or identified under subparagraph (7)(b) one or more additional bird species for inclusion
in the conservation objectives of the site, notify the bodies and persons referred to in
Regulations 16(6) and 16(7) providing those bodies and persons, within a reasonable period,
with a statement of the updated conservation objectives of the site concerned, and shall
publish them on the Department’s website.
(5) The Minister shall establish the conservation measures which he or she considers
necessary, in respect of special areas of conservation designated under Regulation 14
including, if need be, management plans either specifically designed for the sites or
integrated into appropriate plans.
(6) The Minister shall establish the administrative or contractual measures which correspond
to the ecological requirements of the natural habitat types in Annex I to the Habitats
Directive and the species in Annex II to that Directive present on the sites including, but not
limited to, management agreements under Regulation 24, threat response plans under
Regulation 39 and administrative agreements under Regulation 40.
(7) The Minister may, for the purposes of the Birds Directive—
(a) establish conservation measures which he or she from time to time considers necessary,
in respect of special protection areas designated under Regulation 18 including, if need be,
management plans either specifically designed for the sites or integrated into appropriate
plans,
(b) identify additional species referred to in Article 4(1) and 4(2) of the Birds Directive for
inclusion in the conservation objectives of the site, and
(c) establish in relation to special protection areas the administrative or contractual
measures which he or she considers correspond to the ecological requirements of the species
in Annex I to the Birds Directive and of the regularly occurring migratory species not in
Annex I to the Birds Directive present on the sites.
(8) In relation to the exercise of his or her functions under this Regulation, the Minister may
consult with such persons as he or she considers appropriate.”
Facts
10. A SID determination letter issued to Innogy Renewables Ireland Limited on 28 May 2020
enabling it to apply directly to the board for permission for a SID development.
11. Relying on that, on 8 January 2021, the notice party, Curns Energy Limited, made an
application for development consent under section 37E of the 2000 Act for the wind farm
development. The application documentation contained a suite of documents, including, inter alia,
an environmental impact assessment report (EIAR), an appropriate assessment (AA) screening
report and a Natura impact statement (NIS).
12. The nearest European Site to the development site is the Blackwater River (Cork/Waterford)
SAC [002170] located adjacent to the north-eastern boundary of the site. The development is 9.9
km from the Blackwater Callows SPA.
13. In March 2021, the Chief Executive of Waterford City and County Council made a report on
the wind farm development under section 37E(4) of the 2000 Act. Similarly, in March 2021, the
Chief Executive of Cork Council also made a report on the wind farm development.
14. Submissions were received from six prescribed bodies including Inland Fisheries Ireland, the
Development Applications Unit (formerly NPWS) and Irish Water.
15. A total of 679 observations were submitted by members of the public, including the
applicant.
16. On 26 January 2022, generic conservation objectives were adopted for Blackwater Callows
SPA and other sites.
17. On or about 8 April 2022, the board sought further information from Curns. A response was
provided by Curns on 11 October 2022, which included a series of appendices comprising expert
reports.
18. Following correspondence from the board, Curns published notices advising of the
submission of the further information and the date by which submissions were to be made to the
board. Submissions were received from three prescribed bodies and 196 observations were received
from members of the public. No further submissions from the planning authorities were received.
19. On 8 May 2023, the board decided that no oral hearing was to be held.
20. Curns was invited to make a submission in response to the observations made by the public
in response to the developer’s further information. This response was received by the board on 23
June 2023.
21. In August 2023, the board’s inspector made her report recommending that planning
permission be granted for the wind farm development, subject to conditions.
22. The board met to consider the file on 19 October 2023, and prepared a direction
recommending that planning permission be granted.
23. By order dated 8 November 2023, the board granted planning permission for the impugned
development.
24. On 24 March 2024, site-specific objectives and conservation measures were put in place for
Blackwater Callows SPA.
Procedural history
25. The proceedings were issued on 11 January 2024.
26. In correspondence dated 7 February 2025, it was confirmed that the Minister will consent to
a declaration that the Second and or Third and Fourth Respondents failed to fulfil their obligations
under Articles 3, 4(1) and 4(2) of Directive 2009/147 and Article 6 of Directive 92/43 and transposing
legislation by failing to have in place the necessary site specific conservation objectives and
conservation measures in the Blackwater Callows Special Protection Area.
27. The matter was heard on 4 and 5 March 2025 and then listed for further mention on 25 and
31 March 2025 and 7 April 2025.
28. On 11 April 2025 the referring court found that it can exclude any reasonable possibility that
any failure to consider conservation objectives and/or measures in this case would give rise to effects
on any European site. Hence the referring court has refused an order quashing the development
consent, irrespective of the outcome of the present preliminary reference. However, the referring
court requests the CJEU to address the question set out below for the purpose of deciding whether
or not to grant declaratory relief to the applicant. On 19 May 2025 the present judgment was revised
to incorporate further submissions from the parties.
29. In those circumstances the referring court is staying the balance of the proceedings and
referring the questions below to the Court of Justice for a preliminary ruling.
The referred question
30. The referred question is:
“Does Article 6(3) of Directive 92/43 as applied to Directive 2009/147 by Article
7 of the former Directive have the effect that a determination by a competent
authority of a Member State as to whether or not a plan or project not directly
connected with or necessary to the management of any site for the purposes of
Directive 2009/147 is likely to have a significant effect on any such site, either
individually or in combination with other plans or projects, must be carried out by
reference to conservation objectives and/or measures established for any site
concerned and/or in particular for any site which is proposed to be screened out
of consideration as one unlikely to be significantly so affected?”
31. The applicant’s proposed answer is Yes. Regarding conservation objectives - the risk of a
significant effect “is deemed to be present where it cannot be ruled out, having regard to the best
scientific knowledge in the field, that the plan or project might affect the conservation objectives of
the site” – Case C-254/19 FIE at 50-51 and case law cited. The relevant assessment cannot be
carried out in the absence of conservation objectives. This is reflected in S.I. No. 477 of 2011 Article
42. The Board suggests the court is asking, in essence, whether it is possible for a competent
authority to conduct screening for AA screening at all in the absence of valid conservation objectives
and/or measures. The applicant’s answer to that question, as regards conservation objectives, is
“No” – AA screening should be carried out in the way the Directive, as interpreted by the CJEU,
requires - rather than in some other way, as was done here. COs should precede the conservation
measures – Case C-116/22 Commission v Germany. Insofar as COs are essential to AA screening,
the absence of CMs compounds rather than creates the problem. However, insofar as it is contended
that AA screening can in principle be performed without COs, the CMs have the potential to inform
the interpretation and application of the COs, and thus should be considered essential to jurisdiction.
32. In replying to this question the applicant also sought to argue that the conservation
objectives ultimately adopted were not consistent with the AA set out in the inspector’s report. This
is an issue that was never pleaded or argued at the substantive hearing and hence is wholly
impermissible at this stage and in any event is irrelevant to the specific relief which is the subject of
the reference.
33. The respondent’s proposed answer is No. It submits that the absence of conservation
objectives and/or measures having been established for a site concerned does not mean or have the
effect that the competent authority cannot carry out an AA screening at all and is not a jurisdictional
bar to the carrying out by a competent authority of an AA screening. There is no textual basis in
Article 6(3) itself or elsewhere in Directive 92/43 for such a jurisdictional bar, nor is there any
contextual basis for inferring the existence of such a jurisdictional bar, nor is there is any purpose
served by reading in the existence of same. Article 6(3) does not contain any reference at all to
conservation measures. As regards conservation objectives, reference to objectives is not made in
the first part of Article 6(3) dealing with the threshold for an appropriate assessment, namely
whether a plan or project would be likely to have a significant effect on any European site. Insofar
as AA screening comprises four steps (per Section 3.1 of Commission Notice (2021/C437/01), such
a jurisdictional bar would needlessly preclude the carrying out of the first three of those steps,
pursuant to which it may be possible to screen the requirement for an AA in or out in a given case
without reference to the conservation objectives for the site concerned. Such a jurisdictional bar
would, for example, unnecessarily deprive the competent authority of competence to exclude at the
screening stage plans or projects that would have no appreciable effect at all on any site concerned,
where any such unaffected site did not have valid conservation objectives. Whether an absence of
conservation objectives affects a competent authority’s ability to carry out screening necessarily falls
to be assessed on a case by case basis. Any conclusion that the competent authority’s ability to
carry out AA screening is affected would have to have an evidential basis. To require a blanket
jurisdictional bar goes far beyond, and is not justified by, the text and purpose of Directive 92/43.
34. The notice party’s proposed answer is No, the absence of conservation objectives does not
deprive the competent authority of jurisdiction to assess whether a project is likely to have a
significant effect on the qualifying interests of the SPA. The taking into account of conservation
objectives would, if anything, narrow the scope of any screening for AA – by shifting focus from
effects per se to effects by reference to the conservation objectives. Recital 7 of Directive 2009/147
states that “conservation is aimed at the long-term protection and management of natural resources
as an integral part of the heritage of the peoples of Europe”. Article 1(i) of Directive 92/43 defines
“conservation status of a species” as meaning:
“the sum of the influences acting on the species concerned that may affect the long-term
distribution and abundance of its populations within the territory referred to in Article 2.
The conservation status will be taken as ‘favourable’ when:
- population dynamics data on the species concerned indicate that it is maintaining
itself on a long-term basis as a viable component of its natural habitats, and
- the natural range of the species is neither being reduced nor is likely to be reduced
for the foreseeable future, and
- there is, and will probably continue to be, a sufficiently large habitat to maintain
its populations on a long-term basis;”
Conservation objectives aim to define favourable conservation status for the purposes of the
Directive 92/43. In theory, a plan or project may be considered as likely to have significant effects
on an SPA but escape such conclusions when viewed in light of conservation objectives – which take
into account matters such as population dynamics, range of species and having a sufficiently large
habitat. Screening for AA, which does not take into account conservation objectives, would, if
anything, involve a more enhanced/expansive scope for screening, which is consistent with the fact
that screening involves a low threshold. This is further fortified by the fact that a competent
authority is mandated to adopt a precautionary approach to screening for AA. On the facts of this
case, the competent authority found there were no effects and so it logically follows that there is no
possibility/likelihood of significant effects to the qualifying interests, regardless of the conservation
objectives. Where, as here, the finding (made on the basis of the evidence adduced) of the
Competent Authority is that there are no significant effects on any European Sites arising from the
project, the absence of site specific conservation objectives does not and could not alter or affect
this outcome – in such circumstances, noting the purpose of the Directive (which is in no way
undermined) the absence of site specific conservation objectives does not have the consequence of
depriving the Competent Authority of jurisdiction from carrying out such an assessment. As regards
conservation measures, the absence of site specific special conservation measures does not preclude
the Competent Authority of jurisdiction to assess whether a project is likely to have a significant
effect on a European Site. An assessment under Article 6(3) of Directive 92/43, as per the text of
same, does not concern conservation measures. Under Article 4(1) of Directive 2009/147, the
designation of SPAs is itself a conservation measure. Therefore, under both Article 4(1) of the Birds
Directive and Article 6(1) of Directive 92/43, conservation measures have no link to the assessment
under Article 6(3) of Directive 92/43.
35. The State’s proposed answer is No. Conservation objectives may be relevant to appropriate
assessment screening but are not a jurisdictional requirement. There is no textual basis in Article
6(3) from which a jurisdictional bar could be inferred, and neither the context nor the purpose of
Article 6(3) requires or supports such an inference. If a jurisdictional bar existed, it would constitute
a complete prohibition on the granting of consent, if there were a single site anywhere in the country
that lacked conservation objectives. There could be no justification for implying such an extreme
obligation into Article 6(3), where it will frequently be possible to screen out a site without reference
to conservation objectives. This would be to adopt an overly formalistic position, such as AG
Sharpston warned against in Case C-258/11 Sweetman at [48]. Any circumstance in which a lack of
conservation objectives might impact on a competent authority’s ability to carry out the screening
exercise will necessarily arise only on a case-by-case assessment and does not equate to or require
a jurisdictional bar. Conservation measures have no relevance to the carrying out of an appropriate
assessment or an appropriate assessment screening. There is therefore no conceivable basis to infer
into Article 6(3) a jurisdictional bar to carrying out an appropriate assessment screening in the
absence of conservation measures.
36. The referring court’s proposed answer is No. The process of screening for appropriate
assessment would be unworkable if the competent authority was required to consider conservation
objectives and/or measures of any site being screened out. The vast majority of sites can be
screened out due to distance and the lack of a plausible pathway. There is no textual link in the
Directive between screening and objectives or measures.
37. The relevance of the question is that if the answer is Yes, the applicant will be given a
declaration that the screening exercise here ought to have been carried out by reference to the
conservation objectives and/or measures of the relevant SPA.
38. Given the significant overlap with C-27/25, Knocknamona, and the fact that similar
considerations for priority apply in the present case including the impact on the present and other
applications for renewable energy infrastructure, the referring court respectfully requests an Order
affording the present reference priority over other cases pursuant to Rule 53(3) of the Rules of
Procedure and/or an Order that this reference and Case C-27/25, Knocknamona be joined pursuant
to Rule 54(1) and (2) of the Rules of Procedure.
Order
39. For the foregoing reasons, it is ordered that:
(i) the question set out in this judgment be referred to the CJEU pursuant to Article 267
TFEU;
(ii) having regard to the Order of the President of the CJEU of 20 March 2025, C-27/25
Knocknamona, in which the application of the expedited procedure was refused but
it was stated that the CJEU will give the case priority over others, pursuant to Article
53(3) of the Rules of Procedure, the referring court respectfully requests an Order
affording the present reference priority over other cases pursuant to Rule 53(3) of
the Rules of Procedure and/or an Order that this reference and Case C-27/25,
Knocknamona be joined pursuant to Rule 54(1) and (2) of the Rules of Procedure;
(iii) the applicant has requested the referring court to inform the CJEU that he does not
wish his name to be anonymised for the purposes of the proceedings in the CJEU
and therefore that he can be named by the CJEU including by way of the publication
of materials or of the judgment of that court; and
(iv) the substantive determination of the balance of the proceedings be adjourned
pending the judgment of the CJEU, without prejudice to the determination of any
appropriate procedural or interlocutory issues in the meantime.