High Court grants leave to appeal on planning permission refusal but settles case by consent due to new government policy.
Legislator summary
AI generatedThe High Court granted leave to appeal the Minister's refusal of a planning permission for the Shannon LNG terminal, noting the need for correct administrative adjudication. While the applicant sought to challenge the decision, seismic political developments led to a new government approving a state-led LNG plan and terminating the previous fracking policy. Consequently, the parties agreed to a consent order narrowing the judgment's scope and striking out the appeal, rendering further judicial resolution unnecessary.
Legislator headnote
AI generatedSections 50, 50A, and 50B of the Planning and Development Act 2000; where a court grants leave to appeal but subsequent political changes render the dispute moot, the parties may settle by consent to narrow the judgment and strike out the appeal.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
[2024] IEHC 555
THE HIGH COURT
PLANNING & ENVIRONMENT
[H.JR.2023.0001269]
IN THE MATTER OF SECTION 50, 50A AND 50B OF THE PLANNING AND DEVELOPMENT
ACT, 2000 AS AMENDED
BETWEEN
SHANNON LNG LIMITED
APPLICANT
AND
AN BORD PLEANÁLA, THE GOVERNMENT OF IRELAND,
THE MINISTER FOR ENVIRONMENT, CLIMATE AND COMMUNICATIONS, IRELAND AND
THE ATTORNEY GENERAL
RESPONDENTS
JUDGMENT of Humphreys J. delivered on Monday the 30th day of September 2024
1. Administrative decision-making requires the consideration of all relevant issues in a correct
manner. That isn’t too controversial. While the facts underlying these proceedings are complex,
and the subject-matter important, that doesn’t in itself lift the legal question here out of the ordinary.
The central issue comes down to a fact-specific, case-specific application of the general requirement
of correct administrative adjudication. As it happens, we are dealing here with refusal of a
permission, but the need to apply the rules of administrative law is neutral and would apply equally
to the grant of a permission. Nor does the potentially controversial nature of the project have any
relevance to the legal analysis involved.
Judgment history
2. In Friends of the Irish Environment v. An Bord Pleanála & Anor. [2019] IEHC 80, 2 JIC 1501
(Unreported, High Court, 15th February 2019) Simons J. decided to refer questions to the CJEU
concerning whether renewal of a permission engaged the habitats directive.
3. In the judgment of 9 September 2020, Friends of the Irish Environment Ltd v An Bord
Pleanála, C-254/19, EU:C:2020:680, the CJEU in summary concluded that a renewal was potentially
capable of requiring appropriate assessment. On foot of that, the extension of the permission was
quashed by consent in the High Court.
4. In separate proceedings, Friends of the Irish Environment CLG v. Minister for
Communications, Climate Action and the Environment, Ireland and the Attorney General & Shannon
LNG Limited [2020] IEHC 383, [2020] 9 JIC 1405 (Unreported, High Court, 14th September 2020)
Simons J. refused to refer to the CJEU an issue regarding validity of the 4th Union list of Projects of
Common Interest insofar as it includes the proposed Shannon LNG terminal and connecting pipeline.
The list of projects of common interest had been adopted by the EU Commission by way of delegated
regulation: Commission Delegated Regulation (EU) 2020/389.
5. In Friends of the Irish Environment CLG v. Minister for Communications, Climate Action and
the Environment, Ireland and the Attorney General & Shannon LNG Limited [2021] IEHC 177, [2021]
3 JIC 3003 (Unreported, High Court, 30th March 2020) Simons J. dismissed the balance of the
challenge in respect of the List of Projects of Common Interest.
6. In Friends of the Irish Environment CLG v. Minister for Communications, Climate Action and
the Environment, Ireland and the Attorney General & Shannon LNG Limited [2022] IECA 298
(Unreported, Court of Appeal, Noonan J., 21st December 2022), the Court of Appeal dismissed an
appeal against Simons J.’s order declining to refer the issue of the List of Projects of Common
Interests to the CJEU.
Geographical context
7. The development is proposed in the Shannon estuary about half-way between Ballylongford
and Tarbert in Co. Kerry. A map is set out at https://www.pleanala.ie/en-ie/case/311233.
8. The development is an application for a Strategic Infrastructure Development comprising,
inter alia, a gas-powered power plant; a battery energy storage system; and a Liquefied Natural Gas
(LNG) Terminal.
Facts
9. When a consumer turns on the gas in their home, where does that come from? Mainly from
the North Sea.
10. The longer answer is approximately 80% of gas imports come through two interconnector
pipelines from Moffatt in Scotland which make landfall between Drogheda and North Co. Dublin (see
map at https://irelandenergy2050.ie/questions/where-does-irelands-gas-come-from-and-what-
determines-its-
price/#:~:text=Once%20the%20gas%20arrives%20in,40%25%20of%20the%20final%20price).
11. The balance comes from the Corrib gas field. Kinsale is now shut and non-operational.
Potentially of relevance in the event of an outage, there is also a pipeline from Scotland to Northern
Ireland.
12. Approximately 56% of UK gas is imported, and 44% is indigenous. Of the imported gas,
42% is LNG which means that 24% of UK gas is imported LNG. Approximately 50% of the gas
imported into the UK is hydraulically fractured.
13. Hydraulic fracturing (“fracking”) is the process of fracturing rock by the use of fluids. “It has
been used to specifically refer to the fracturing processes involved in the extraction of gas and oil
trapped in sedimentary rock such shale” https://www.gsi.ie/en-ie/geoscience-
topics/energy/Pages/Fracking.aspx.
14. However, the physical and geographical nature of the infrastructure means that the vast
majority of the gas that comes into Ireland is either imported from Norway or produced in the UK.
Public domain material indicates that most Scottish gas fields are in the UK continental shelf in the
North Sea: https://marine.gov.scot/sma/assessment/oil-and-gas-sector-and-
infrastructure#:~:text=Most%20oil%20and%20gas%20fields,production%20and%20hosts%20wi
nd%20turbines.
15. Very little of the imported hydraulically fractured gas that comes to the UK actually comes
to Ireland due to geographical factors.
16. Turning more specifically to the present application, we are now 17 years on from the first
proposal for an LNG facility on this site.
17. The applicant first held pre-application discussions with the board on 2nd May 2007 and
27th June 2007 under s. 37B of the 2000 Act. On 11th September 2007, the board served
notice under s. 37B(4)(a) that it was of the opinion that the proposed development would fall within
the scope of paras. 37A(2)(a) and (c) of the Act, i.e. it would be of strategic economic or social
importance to the State or the region in which it would be situate and it would have a significant
effect on the area of more than one planning authority. The formal application was made on 24th
September 2007.
18. On 31st March 2008, the board granted permission to the applicant for strategic
infrastructure comprising an LNG regasification terminal (Board ref. PL08.PA0002)
(https://archive.pleanala.ie/en-ie/case/Pa0002). The permission was twice purportedly amended
and extended (Board ref. PL08.PM0002 and PL08.PM0014) and has expired for reasons which we
will get to shortly.
19. The Strategic Integrated Framework for the Shannon Estuary is a non-statutory inter-
jurisdictional land and marine based framework plan to guide the future development and
management of the Shannon Estuary. It was commissioned by Limerick City and County Council,
Clare County Council, Kerry County Council, Shannon Development and the Shannon Foynes Port
Company. The project was overseen by a multi-agency steering group comprised of the above and
other key stakeholders with an interest in the estuary. The final Strategic Integrated Framework
Plan for the Shannon Estuary was published following a public consultation process, and launched
on 22nd November 2013.
20. On 17th February 2009, the board granted approval to the applicant for strategic gas
infrastructure comprising a 26 km pipeline between Ralappane, Co. Kerry and Leahy’s, Co. Limerick
(Board ref. PL08.GA0003). That approval has not expired.
21. On 9th July 2013, the board granted permission to the applicant for strategic infrastructure
comprising a 500 MW gas-fired power plant (Board ref. PL08.PA0028). Having regard to condition
2 of that permission, and s. 251 and 251A of the 2000 Act, the permission expired on 2nd December
2023.
22. The National Planning Framework, Project Ireland 2040 (https://cdn.npf.ie/wp-
content/uploads/Project-Ireland-2040-NPF.pdf), published in February 2018 (and currently under
challenge in other proceedings), includes National Strategic Outcome 8 which addresses the
Transition to a Low Carbon and Climate Resilient Society and includes the following policy aims:
“Deliver 40% of our electricity needs from renewable sources by 2020 with a strategic aim
to increase renewable deployment in line with EU targets and national policy objectives out
to 2030 and beyond. It is expected that this increase in renewable deployment will lead to
a greater diversity of renewable technologies in the mix.
Reinforce the distribution and transmission network to facilitate planned growth and
distribution of a more renewables focused source of energy across the major demand
centres.
Strengthen energy security and resilience to support an island population of 8 million people
through effective north-south electricity grid interconnection as well as exploring other EU
interconnection options in the longer term to 2040.
Consideration of carbon neutral electricity generation that would be facilitated through
harnessing carbon capture and storage (CCS).
National Interconnector (Sub-sea Ring around Ireland) or other solutions offer the potential
to connect Ireland to the EU electricity grid System.
Roll-out of the National Smart Grid Plan enabling new connections, grid balancing, energy
management and micro grid development.”
23. In addition, National Policy Objective 55 states that it is a policy to “promote renewable
energy use and generation at appropriate locations within the built and natural environment to meet
national objectives towards achieving a low carbon economy by 2050”.
24. On 16th August 2018, the applicant purchased the 603-acre Shannon Landbank from the
Minister for Transport, through his State agency, Shannon Commercial Enterprises DAC. The
landbank was valued, marketed, and sold to the Applicant for €31.555 million, on basis that it was
suitable for development of an LNG terminal.
25. In October 2018, the Department of Communications, Climate Action and Energy (as then
titled), with support from the Commission for Regulation of Utilities (CRU), asked Gas Networks
Ireland (GNI) and EirGrid to examine Ireland’s resilience to a prolonged gas disruption, and to make
recommendations on how Ireland might future-proof its gas supply. The resulting Long Term
Resilience Study (2018) (https://www.gasnetworks.ie/docs/corporate/gas-regulation/Long-Term-
Resilience-Study-2018.pdf) concluded inter alia:
“The most economically advantageous option to improve the resilience of Ireland’s gas
supply is a floating LNG terminal.
However, as the social benefits do not outweigh the costs. [sic] A detailed assessment of
private benefits is required to determine whether such an investment would provide a broad
societal benefit and a return for investors. Price and cost simulations and public consultation
can be used to better understand the commercial interest in such a terminal. The analysis
should include a robust Cost Benefit Analysis (CBA) including private benefits and
consideration of possible funding and ownership options.
A floating LNG terminal would provide a direct connection for Ireland to the global LNG
market and would allow Ireland to diversify its gas supply. However, greater exposure to
the LNG market comes with price risk, which could result in usage of an LNG terminal
fluctuating. This variability of utilisation needs to be considered in terms of cost recovery.
We recommend further analysis, including multi scenario modelling of future LNG and
pipeline gas prices to inform the level of utilisation and the private benefits associated with
operating an LNG terminal.”
26. Separately, in or about 2018, the CRU published the National Preventive Action Plan Gas
2018–2022 Ireland (https://energy.ec.europa.eu/system/files/2020-
04/npap_ireland_2018__0.pdf), which stated, inter alia, that Ireland failed to meet the N-1 standard
of energy security:
“In previous risk assessments, total disruption to the gas supply from the Moffat entry point
constituted the largest gas infrastructure in relation to gas supply to Ireland. Projects are
currently underway at Beattock and Brighouse Bay compressor stations to eliminate the
single point of failure which drove the existing failure mode i.e. total disruption to the gas
supply from the Moffat entry point.
These mitigation works are scheduled for completion prior to gas year 2020/21 and will allow
splitting of the entire SWSOS. This will result in a revision to the treatment of the N-1
calculation in that the loss of the largest piece of gas infrastructure will now constitute a
partial disruption to the gas supply from the Moffat entry point. It can be seen that the
result of the N-1 calculation is 85% and that Ireland fails to meet the criteria (i.e. if the
supply of gas via Moffat is partially disrupted Ireland will be unable to deliver sufficient gas
from other entry points to meet total demand on a 1 in 20 year peak-day).
In the event that an EU Member State cannot fulfil the N-1 infrastructure standard on a
national basis, the Regulation permits the adoption of a regional approach in order to meet
the Standard. Following a request from the CRU, BEIS agreed to adopt a regional approach
between the UK and Ireland. The initial analysis indicates that the joint N-1 position for the
UK and Ireland is 112%. Further information on this is provided in Section 8 ‘Regional
Approach’.”
27. In Friends of the Irish Environment CLG v. An Bord Pleanála [2019] IEHC 80, [2019] 2 JIC
1501 (Unreported, High Court, 15th February 2019), Simons J. referred questions to the CJEU
regarding whether the extension of the 2008 permission engaged the habitats directive. He noted
that Barrett J. had held not in Merriman v. Fingal County Council [2017] IEHC 695, [2017] 11 JIC
2104 (Unreported, High Court, 21st November 2017) (and that leave to appeal had been refused in
respect of that conclusion). Subsequently, in the judgment of 9 September 2020, Friends of the
Irish Environment Ltd v An Bord Pleanála, C-254/19, EU:C:2020:680, the CJEU was to go on to hold
to a contrary effect in certain circumstances, stating that:
“1. A decision extending the 10-year period originally set for carrying out a project for
the construction of a liquefied natural gas regasification terminal must be regarded as an
agreement of a project under Article 6(3) of Council Directive 92/43/EEC of 21 May 1992 on
the conservation of natural habitats and of wild fauna and flora, where the original consent,
having lapsed, ceased to have legal effect on expiry of the period originally set for those
works and the latter have not been undertaken.
2. It is for the competent authority to assess whether a decision extending the period
originally set for carrying out a project for the construction of a liquefied natural gas
regasification terminal, the original consent for which has lapsed, must be preceded by the
appropriate assessment of its implications under the first sentence of Article 6(3) of Directive
92/43 and, if so, whether that assessment must relate to the entire project or part thereof,
taking into account, inter alia, previous assessments that may have been carried out and
changes in the relevant environmental and scientific data as well as changes to the project
and the existence of other plans or projects.
The assessment of a project’s implications must be carried out where it cannot be ruled out,
having regard to the best scientific knowledge in the field, that the plan or project might
affect the conservation objectives of the site. A previous assessment of that project, carried
out before the original consent for the project was granted, cannot rule out that risk unless
it contains full, precise and definitive conclusions capable of removing all reasonable
scientific doubt as to the effects of the works, and provided that there are no changes in the
relevant environmental and scientific data, no changes to the project and no other plans or
projects.”
28. On 20th March 2019, the applicant, as required by s. 37B(1) of the 2000 Act, entered into
consultations with the board in respect of the proposed application for permission for the Project
(Board ref. ABP-304007-19).
29. On 14th November 2019, the Minister for Communications, Climate Action and
Environment announced that he had received Government approval to initiate a review into the
security and sustainability of Ireland’s energy supply up to 2030.
30. On 15th June 2020, the Government published the Programme for Government “Our
Shared Future” (https://www.gov.ie/en/publication/7e05d-programme-for-government-our-
shared-future/?app=true). At p. 36, with respect to natural resources, the following commitment
was made regarding LNG:
“As Ireland moves towards carbon neutrality, we do not believe that it [makes] sense to
develop LNG gas import terminals importing fracked gas. Accordingly, we shall withdraw
the Shannon LNG terminal from the EU Projects of Common Interest list in 2021.
We do not support the importation of fracked gas and shall develop a policy statement to
establish that approach.”
31. In September 2020, the Sustainable Energy Authority of Ireland published the “Energy
Security in Ireland 2020 Report” (https://www.seai.ie/publications/Energy-Security-in-Ireland-
2020-.pdf) stating that it “provides up to date data and information which can be used as an input
to” the Security of Supply Review. This included analysis of Ireland’s dependency on import from
the United Kingdom (at pp. 28-29), analysis of the increasing amount of LNG in the gas supply of
the United Kingdom (at pp. 29-30) and analysis of gas infrastructure in the European Union showing
that LNG imports met 22% of gas demand in the European Union in 2019 (at p. 35).
32. On foot of the judgment of Simons J. in the Friends case, an order was made on 9th
November 2020 quashing the amendment bearing reference no. PL08.PM0014, so the permission
bearing reference no. PL08.PA0002 has expired.
33. On 24th February 2021, the Minister for the Environment, Climate and Communications,
in a written answer to a parliamentary question stated that the Security of Supply Review was
scheduled for completion during “Q4 2021”. I should make clear that references to parliamentary
proceedings are for background only and there is no question of holding parliamentarians to account
in that regard.
34. A broadly favourable inspector’s report on the pre-application consultation was published in
April 2021.
35. On 10th May 2021, Cambridge Economic Policy Associates (CEPA) was commissioned by
the Minister for the Environment, Climate and Communications “to undertake a technical analysis of
physical security of supply to inform the Security of Supply Review”.
36. On 18th May 2021, the Minister published a press release stating that he had received
Government approval for a “Policy Statement on the Importation of Fracked Gas”. In the press
release, the Minister stated that the policy included a “moratorium on the development of LNG import
terminals pending the completion of review of security supply”. The 2021 policy is entitled “Policy
Statement on the Importation of Fracked Gas” (https://www.gov.ie/en/publication/f3774-policy-
statement-on-the-importation-of-fracked-gas/).
37. This states, inter alia:
“Ireland imports much of its natural gas via the two interconnector pipelines from Moffat in
Scotland, which provide the majority of natural gas currently used in Ireland. Given the
level of fracked gas in the imports from Scotland is considered very low, the highest risk of
fracked gas being imported into Ireland on a large-scale would be via liquefied natural gas
(LNG) terminals, if any were to be constructed.”
38. On pp. 2-3, the policy envisaged a review of energy security:
“The Minister for the Environment, Climate and Communications is currently carrying out a
review of the security of energy supply of Ireland’s electricity and natural gas systems which
is focussing on the period to 2030 in the context of ensuring a sustainable pathway to net
zero emissions by 2050.
The Government’s 2021 Climate Action Plan will increase ambition in reducing Irelands [sic]
greenhouse gas emissions in line with the Programme for Government. This will lead to a
lower annual use of natural gas than would otherwise be the case thus reducing the potential
risks to security of supply. This will be taken into account by the review.
The review will consider if it would be appropriate, or not, to develop LNG terminals in
Ireland. It will also consider, if any such terminals were to be developed, if they should only
be in order to provide a backup to existing supply infrastructure. It is only on the completion
of this review that the Government can conclude, with certainty, the role of any future
potential LNG terminals and the type, ownership and use of such terminals.
The review will include a technical analysis and a public consultation. The outcome of the
review will be brought to Government for its approval.”
39. The policy statement concludes with the following:
“2 Policy Decision
The Government recognises that:
• fracked gas can have significantly higher greenhouse gas emissions than
conventional natural gas, both nationally and globally, and the widespread use of
fracked gas would not be consistent with Ireland’s 2030 and 2050 climate objectives
nor globally with the Paris Agreement;
• the outcome of the review of the security of energy supply of Ireland’s electricity
and natural gas systems will inform how Ireland can ensure we will have secure
energy systems focussing on the period to 2030 in the context of ensuring a
sustainable pathway to net zero emissions by 2050;
• the review will consider how the Government’s increased ambition in renewable
energy and the development of new indigenous clean energy sources, such as
hydrogen from renewable sources and biomethane, will reduce fossil fuel use and
how this can reduce the security of supply risks;
• the review will consider the risk of stranded assets, including fossil fuel
infrastructure, in the context of the Government commitment to net zero emissions
by 2050; and
• the review will inform whether it would be appropriate, or not, to develop LNG
terminals in Ireland and, if any such terminals were to be developed, whether they
should only be in order to provide a contingency supply in the event of failure of
existing natural gas supply infrastructure.
In order to implement the Programme for Government commitment that it does not support
the importation of fracked gas, the Government has approved that:
• pending the outcome of the review of the security of energy supply of Ireland’s
electricity and natural gas systems, it would not be appropriate for the development
of any LNG terminals in Ireland to be permitted or proceeded with;
• the Government will work with like-minded European States to promote and support
changes to European energy laws – in particular the upcoming revision of the
European Union’s Gas Directive and Gas Regulation – in order to allow the
importation of fracked gas to be restricted; and
• the Government will work with international partners to promote the phasing out of
fracking at an international level within the wider context of the phasing out of fossil
fuel extraction.”
40. As regards how this is to be viewed legally, the applicant is correct to submit that:
“21. In his press release to announce the Fracked Gas Policy, the Minister stated that the
policy included a ‘moratorium on the development of LNG import terminals pending the
completion of review of security of supply’.
22. As a matter of fact, and law, there is no such moratorium, or temporary prohibition,
as suggested.
...
29. The Fracked Gas Policy is a mere expression of Government policy, from which the
Board was free to depart. Although the phrase ‘it would not be appropriate for the
development of any LNG terminals in Ireland to be permitted or proceeded with’ is expressed
in blunt terms, that does not give to the Fracked Gas Policy any special priority or weight
among the listed other relevant considerations for the Board. Also, the phrase ‘would not
be appropriate’ does not comprise a prohibition, but rather an expression of desire or
preference only.”
41. It appears to be common ground between the parties that contrary to the wording used by
the Minister, the Government policy does not constitute a moratorium. It follows that the document
constituted a policy preference only, which the board is in law free to depart from because
Government policy has only a have-regard-to status and not a comply-with status.
42. On 26th May 2021, the Minister for the Environment, Climate and Communications, in a
written answer to two parliamentary questions stated that the Security of Supply Review
“includes a technical analysis which will help inform a public consultation. The technical
analysis includes identification and examination of the key risks to the security of supply
in the electricity and natural gas systems; identification of options that could address or
mitigate these risks in the period to 2030; and appraisal of these options in the context
of ensuring a sustainable pathway to 2050. It is planned that the technical analysis will
be published and the public consultation undertaken in the second half of this year. It
is planned the review will be completed by the end of 2021, following which it will be
submitted to Government.”
43. On 2nd June 2021, the board concluded that the project comprised development specified
within the Seventh Schedule of the 2000 Act and fell within the scope of sub-paras. (a), (b) and (c)
of s. 37A(2) of the 2000 Act. Accordingly, the project would be strategic infrastructure, so that an
application for permission should be made to the board under s. 37E of the 2000 Act.
44. The National Marine Planning Framework (NMPF)
(https://www.gov.ie/en/publication/60e57-national-marine-planning-framework/) was published on
30th June 2021. The NMPF addresses Natural Gas Storage in Chapter 12. It is an objective of the
NMPF to:
“Support the development of natural gas storage where appropriate in the context of the
outcome of the review of the security of energy supply of Ireland’s electricity and natural
gas systems. This review is being carried out by Department of the Environment, Climate
and Communications and is focusing on the period to 2030 in the context of ensuring a
sustainable pathway to 2050.”
45. Natural Gas Storage Policy 1 in the NMPF states:
“Subject to assessments required for the protection of the environment, and only where in
keeping with the outcome of the review of the security of energy supply of Ireland’s
electricity and natural gas systems (which is being carried out by Department of the
Environment, Climate and Communications), natural gas storage proposals should be
supported.”
46. The Energy Security of Supply Review is referenced at p. 119 of the NMPF as follows:
“Key issues for Marine Planning
The Department of the Environment, Climate and Communications is carrying out a review
of the security of energy supply of Ireland’s electricity and natural gas systems, which is
focusing on the period to 2030 in the context of ensuring a sustainable pathway to 2050.
The outcome of this review will determine the need for natural gas storage and the policy
context within which it could be developed in Ireland. It will also inform the need to update
or develop the necessary regulatory frameworks.
Any such frameworks would need to take account of the Marine Planning Policy Statement
in relation to, for example, the need for a robust, stable and effective regulatory regime to
attract investment, demonstrate stability and ensure protection of the marine environment.”
47. In addition, Chapter 15 of the NMPF is addressed to “Energy – Transmission”. It is an
objective of Chapter 15 to:
“Support the development of additional natural gas transmission/import infrastructure
where it is in keeping with the outcome of the review of security of energy supply of Ireland’s
electricity and natural gas systems, and does not involve the importation of fracked gas.
This review is being carried out by the Department of Environment, Climate and
Communications (DECC) and is focussing on the period to 2030 in the context of ensuring a
sustainable pathway to 2050.”
48. Chapter 15 of the NMPF identifies Key Issues for Marine Planning in the context of energy
transmission and states as follows in respect of natural gas:
“Natural Gas
Security of energy supply is a key imperative energy policy objective for Ireland and the
European Union. However, security of supply cannot be examined in isolation from
sustainability. That is why the review of the security of energy supply of Ireland’s electricity
and natural gas systems, which is being carried out by Department of the Environment,
Climate and Communications, is focusing on the period to 2030 in the context of ensuring a
sustainable pathway to 2050. It is also critical that any new natural gas transmission
infrastructure does not involve the importation of fracked gas.”
49. Transmission Policy 6 of the NMPF states:
“Subject to required assessments for the protection of the environment, and only where in
keeping with the outcome of the review of the security of energy supply of Ireland’s
electricity and natural gas systems (which is being carried out by Department of the
Environment, Climate and Communications), and not involving the importation of fracked
gas, additional proposals for natural gas transmission/import infrastructure should be
supported.”
50. On 6th July 2021, the CRU Commissioner testified to the Oireachtas Joint Committee on
Environment and Climate Action that:
“When we talk about this diversity of supply we are being quite open. We have obligations
around security of supply and we must consider all options. A relationship has been drawn
between LNG and certain types of gas and I am not sure that this helps the overall
discussion. LNG can be and could be natural gas. Another point on diversity of supply is
the type of gas that is entering the system. We should also be considering what role
indigenous biogas will have and what role blue hydrogen might have as we transition through
a blended natural gas system to a system that might ultimately be decarbonised.
There are many aspects to diversity of supply. I would neither rule in nor rule out that we
might be discussing the role of LNG, but I emphasise that we should take the idea of fracked
gas and separate it completely from the idea of LNG, to just consider LNG, if we are looking
at that as a route for natural gas to ensure diversity and therefore security of supply.”
51. Notice of the present application was published in the Irish Examiner and the Kerryman
newspapers on 25th August 2021, and in the Kerry’s Eye newspaper on 26th August 2021.
Notice of the application at the site was erected on 25th August 2021. The application was
available for inspection at the offices of the board and Kerry County Council. The entire of the
application was hosted by the applicant on a website at https://stepplanning.com/. A copy was also
hosted by the board on its website at https://www.pleanala.ie/en-ie/case/311233.
52. On 27th August 2021, the applicant formally made the application the subject of the
proceedings. This was an application for permission for strategic infrastructure under s. 37E of the
2000 Act (Board ref. ABP 311233-21). The application was accompanied by an Environmental
Impact Assessment Report (in four volumes: Volume 1 – Non Technical Summary, Volume 2 – Main
Report, Volume 3 – Figures, Volume 4 – Appendices) and a Natura Impact Statement.
53. As far as concerns the articulated Government policy against hydraulic fracturing, the EIAR
stated:
“In relation to the Policy Statement on the Importation of Fracked Gas, it is noted that most
of the LNG in the world is not sourced from fracked gas. For context, all of the LNG required
for the Proposed Development represents only 1% of the globally traded non fracked LNG.
LNG is a globally traded commodity and there are 37 operational LNG terminals in Europe
at present. Accordingly, the Proposed Development does not depend on fracked gas and
the Applicant is confident that it can source gas from non-fracked sources to meet energy
demand and ensure security of supply in Ireland.”
54. The application was open to observations from the public for a seven-week period from 3rd
September 2021 to 22nd October 2021.
55. In his submission to the board on the application for permission for the project, dated 19th
October 2021, the Minister stated inter alia:
“I wish to make it very clear that I believe the permitting of this project would be in direct
contravention to [sic] Government policy and therefore it should not, under any
circumstances, be permitted.”
56. The applicant submits that the letter’s “tone” is “remarkable” and reflects “strong antipathy”
towards a commercial LNG facility.
57. On 11th February 2022, the board invited the applicant to confirm whether any rights or
obligations arising from Regulation (EU) No. 347/2013 on guidelines for trans-European energy
infrastructure (TEN-E Regulation or PCI Regulation) have a bearing on the consideration by the
board of the project. On 23rd February 2022, the applicant confirmed to the board that the TEN-E
Regulation did not apply, as the project was not contained on the “fourth list” of projects of common
interest, within Commission Delegated Regulation (EU) 2020/389 of 31st October 2019 amending
the TEN-E Regulation and that no application had been made to include the project on the “fifth list”,
at the time described within proposed Commission Delegated Regulation (Commission ref. C(2021)
8409 final).
58. The Russian Federation’s full-scale war of aggression against Ukraine commenced on 24th
February 2022.
59. On 8th March 2022, the Commission communicated a proposed new policy named REPower
EU (https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=COM:2022:108:FIN).
60. This included the following:
“II. REPower EU: eliminating our dependence on Russian Fossil FUELS
Phasing out our dependence on fossil fuels from Russia can be done well before 2030. To
do so, the Commission proposes a REPowerEU plan that will increase the resilience of the
EU-wide energy system based on two pillars:
• Diversifying gas supplies, via higher LNG imports and pipeline imports from non-
Russian suppliers, and higher levels of biomethane and hydrogen.
• Reducing faster our dependence on fossil fuels at the level of homes, buildings and
the industry, and at the level of the power system by boosting energy efficiency
gains, increasing the share of renewable and addressing infrastructure bottlenecks.
...
REPOWER EU FOCUS FF55 REPOWEREU REPLACED ADDITIONAL
TRACK AMBITION MEASURE BY THE TO FF55 BY
BY 2030 END OF 2030 (BCM
2022 equivalent)
(BCM estimate
equivalent)
estimate
GAS NON-RU - LNG 50* 50
DIVERSIFICATION NATURAL GAS diversification
”.
61. The section on diversifying gas supplies begins as follows:
“2.1. Diversify gas supplies
2.1.1. LNG and pipe imports
An unprecedented LNG supply to the EU in January 2022 has ensured security of gas supply
for this winter. The EU could import 50 bcm more of LNG (e.g. from Qatar, USA, Egypt,
West Africa) on a yearly basis. Diversification of pipe sources (e.g. Azerbaijan, Algeria,
Norway) could deliver another 10 bcm of yearly savings on Russian gas imports.
The Commission will assess as a matter of priority whether measures and investments are
needed in hydrogen-ready gas infrastructure and interconnections to overcome bottlenecks
to the full use of the EU’s LNG capacity.
While diversifying supply, the EU fosters its international partnerships. The Commission will
continue discussing within G7 and with major global purchasers of gas (Japan, South Korea,
China, India) medium-term market developments.”
62. The thrust of the Commission’s approach is not something one would immediately reconcile
with the Irish Government’s anti-LNG policy of 2021.
63. The Versailles declaration of 10-11th March 2022
(https://www.consilium.europa.eu/media/54773/20220311-versailles-declaration-en.pdf) was a
unanimous declaration of heads of State and Government of EU countries in which the Taoiseach
participated. It noted that:
“Russia’s unprovoked and unjustified military aggression against Ukraine grossly violates
international law and the principles of the UN Charter and undermines European and global
security and stability. It is inflicting unspeakable suffering on the Ukrainian population.
Russia, and its accomplice Belarus, bear full responsibility for this war of aggression and
those responsible will be held to account for their crimes.”
64. On energy security, the declaration went on:
“14. Over the past few years, the European Union has set ambitious targets to reach the
objective of climate neutrality by 2050.
15. As the EU works towards achieving that goal, the current situation calls for a thorough
reassessment of how we ensure the security of our energy supplies.
16. In this respect, we agreed to phase out our dependency on Russian gas, oil and coal
imports as soon as possible, in particular by:
a) accelerating the reduction of our overall reliance on fossil fuels, taking into
account national circumstances and Member States’ choices of their energy mix;
b) diversifying our supplies and routes including through the use of LNG and the
development of biogas;
c) further developing a hydrogen market for Europe;
d) speeding up the development of renewables and the production of their key
components, as well as streamlining authorisation procedures to accelerate energy
projects;
e) completing and improving the interconnection of European gas and electricity
networks and fully synchronising our power grids throughout the EU;
f) reinforcing EU contingency planning for security of supply;
g) improving energy efficiency and the management of energy consumption, and
promoting a more circular approach to manufacturing and consumption patterns.
We invite the Commission to propose a RePowerEU plan to this effect by the end of May.
17. In addition, we will continue working on the following strands:
a) ensuring sufficient levels of gas storage and putting in place coordinated refilling
operations;
b) monitoring and optimising the functioning of the electricity market;
c) channelling coordinated investment in energy systems, including providing LNG
infrastructure;
d) enhancing connectivity with our immediate neighbourhood.
18. We invite the Commission to put forward a plan to ensure security of supply and
affordable energy prices during the next winter season by the end of March.
19. In parallel we will urgently address and consider concrete options, building on the
Commission Communication of 8 March 2022, for dealing with the impact of increased
energy prices on our citizens and businesses, especially our vulnerable citizens and SMEs,
including at the next meeting of the European Council on 24-25 March 2022.”
65. Heads of State and Government met again at the European Council later in March. The
conclusions of the European Council of 24-25th March 2022
(https://www.consilium.europa.eu/media/55082/2022-03-2425-euco-conclusions-en.pdf)
(referenced in the National Energy Security Framework) include the commitment that:
“Refilling of gas storage across the Union should start as soon as possible, taking fully into
account national preparedness measures. With a view to next winter, Member States and
the Commission will urgently:
a) establish the necessary solidarity and compensation mechanisms;
b) work together on voluntary common purchase of gas, LNG and hydrogen, making optimal
use of the collective political and market weight of the European Union and its Member States
to dampen prices in negotiations. The common purchases platform will also be open for
Western Balkan countries and the three associated Eastern Partners”
66. Again, let’s not overlook the obvious point that Ireland had a seat at the table in the
unanimous conclusions of the European Council.
67. In April 2022, the “Electricity Crises: A Risk Preparedness Plan for Ireland”
(https://energy.ec.europa.eu/document/download/f42c4e4e-12f9-4f0a-aecf-
88de0eaba892_en?filename=IE_%20RPP%20electricity.pdf&prefLang=bg) was published by the
CRU under Regulation (EU) 2019/941 on risk preparedness in the electricity sector. This identifies
(at p. 26) fossil fuel (including natural gas) shortage to have a “disastrous” impact, rated as “major”.
68. On 13th April 2022, the National Energy Security Framework (NESF) was published
(https://www.gov.ie/pdf/?file=https://assets.gov.ie/221399/86cb99f5-58e3-4821-bc4c-
e1bb1fa706fb.pdf#page=null).
69. The NESF summarises the European Council conclusions as follows:
“• set out that the European Union will phase out its dependency on Russian gas, oil, and
coal imports as soon as possible (as set out in the Versailles Declaration) and that the
European Commission will develop a comprehensive and ambitious plan, on a phased basis,
by end of May;
• issued an invitation to Member States and the European Commission to continue to make
best use of the Toolbox (see below) including the new State Aid temporary crisis framework;
• tasked the Council and the European Commission to consider the short-term options in the
European Commission’s REPowerEU communication (see below) and how they would
contribute to reducing gas prices and addressing contagion effect on electricity markets;
• called on the European Commission to submit proposals that effectively address the
problem of excessive electricity prices while preserving the integrity of the Single Market,
maintaining incentives for the green transition, preserving the security of supply, and
avoiding disproportionate budgetary costs;
• tasked the Council to examine the proposals by the European Commission on EU gas
storage policy duly taking into account and addressing the interests of the Member States
with significant storage capacity in order to ensure a fair balance and in relation to next
winter Member States and the Commission will urgently:
▪ establish the necessary solidarity and compensation mechanisms;
▪ work together on voluntary common purchase of gas, liquified natural gas and
hydrogen;
▪ complete and improve our gas and electricity interconnections throughout the
European Union; and
▪ work on ensuring the security of supplies for all Member States.
• the European Commission to take any necessary initiatives by May 2022, also taking into
account the final ACER and ESMA reports to ensure a robust and fully interconnected internal
electricity market and a well-functioning carbon market.”
70. The NESF states at p. 9:
“Ireland’s imports of natural gas come from the UK and therefore not directly from Russia.
However, the European gas market is an interconnected market from both a physical and
wholesale price perspective. The physical supplies to, and the wholesale market price of
natural gas in Ireland are therefore influenced by the supply of natural gas from Russia into
the European market.
The flow of physical gas throughout Europe is closely inter-related with disruptions in one
part of the network having the ability to spread elsewhere. However, this
interconnectedness is also a strength as countries are able to avail themselves of multiple
ways of obtaining gas.
There are four sources of gas supply potentially available to countries: indigenous
production, imports via liquified natural gas terminals, imports via pipeline and prior gas
production/imports held in storage facilities. Ireland has two of these: indigenous production
and imports via pipeline. The UK by comparison has all four.”
71. The NESF quotes the REPower EU policy on pp. 32-33:
“In March 2022, the European Commission published REPowerEU – a Joint European Action
for more affordable, secure and sustainable energy. The plan outlined a series of measures
including:
• Mitigating the impact of high retail prices and supporting heavily exposed companies
• Preparing for next winter by ensuring sufficient gas storage is available
The plan also aimed to phase out dependence on Russian fossil fuels within the EU through
two pillars:
• Diversifying gas supplies, via higher liquified natural gas and pipeline imports from
non-Russian suppliers, and larger volumes of biomethane and renewable hydrogen
production and imports;
• Accelerating the reduction of the use of fossil fuels in our homes, buildings, industry,
and power system, by boosting energy efficiency, increasing renewables and
electrification, and addressing infrastructure bottlenecks”
72. On diversifying gas supplies, the NESF conclusions are open-ended and certainly not anti-
LNG:
“7.3 Diversifying Fossil Fuel Supplies
While the supply of natural gas required to meet Ireland’s energy needs has not, to date,
been impacted by the war in Ukraine, there are security of supply risks. Ireland’s high
dependence on imports from a single source in the UK, along with the high and growing
reliance of the electricity system on natural gas supplies, has necessitated a review of
security of supply, which is being carried out by the Department of the Environment, Climate
and Communications.
The review is considering the risks to both natural gas and electricity supplies, and a range
of measures, including the need for additional capacity to import energy (such as liquified
natural gas), energy storage, fuel diversification and renewable gases (such as hydrogen).
The completion of the review is a key priority.
Response 31: Prioritise the review of security of supply of Ireland’s electricity and natural
gas systems
• Led by the Department of the Environment, Climate and Communications
• Due for implementation: Q3 2022”
73. It can be noted that notwithstanding the urgency of Versailles, and the statement that the
Government would “prioritise” the review which was “due” in Q3 2022 (i.e., by 30th September
2022), we are still waiting for the completion of the review two years later.
74. On 28th April 2022, the applicant wrote to the Minister seeking a meeting to discuss
relevant issues in the wake of the Russian Federation’s full-scale invasion of Ukraine.
75. On 16th June 2022, the Minister’s office wrote to the applicant refusing the request to
meet, without reasons:
"On behalf of [the] Minister ... I would like to thank you once more for your correspondence
and acknowledge your meeting request. Please forgive the extensive delay in reverting to
you. Unfortunately, the Minister is unable to facilitate a meeting and sends his regrets. Kind
regards."
76. On 4th July 2022, the elected members of Kerry County Council adopted the Kerry County
Development Plan 2022 to 2028 (https://cdp.kerrycoco.ie/), which includes an express objective
(KCDP 12-3, at p. 255) that supports the proposed development at this specific location as follows,
“facilitates the sustainable expansion of the gas network, including the facilitation of a gas
importation facility in the Tarbert/Ballylongford Landbank”.
77. On 5th July 2022, the board requested further information from the applicant, addressing
the principal issues arising from the observations received by the board.
78. On 18th August 2022, the applicant responded to the request. That response was open
to observations from the public for a one-month period from 9th September 2022 to 10th October
2022.
79. During the public consultation periods in 2021 and 2022, a total of 76 observations were
made.
80. On 19th September 2022, the Minister for the Environment, Climate and Communications
published the CEPA “Technical Analysis of the Security of Energy Supply of Ireland’s Electricity and
Natural Gas Systems”, dated 16th September 2022, together with a non-technical summary for
public consultation. A consultation then commenced on 28th October 2022. The accompanying
consultation document, inviting submissions from the public, described the CEPA report (at p. 4) as
follows:
“Supporting technical analysis has been conducted by Cambridge Economic Policy Associates
Ltd (CEPA). The technical analysis consisted of three different stages of work, (i) the
identification and examination of risks, (ii) the identification of options to address these risks,
and (iii) the appraisal of these options. There are two reports of the technical analysis which
are available to be reviewed in conjunction with this consultation document. This
consultation will help inform the Department’s review of the security of energy supply of
Ireland’s electricity and natural gas systems and the outcome of the review will be brought
to Government for its consideration.”
81. With reference to the 2021 policy, the consultation document states (at p. 26) that:
“It is foreseen that the outcome of the review of the security of energy supply of Ireland’s
electricity and natural gas systems would supersede the policy statement on the importation
of fracked gas.”
82. With reference to mitigation options for the security of gas supply, the consultation
document states (at pp. 42-43) the following regarding LNG and a potential floating LNG storage
and regassification unit (FSRU):
“Liquid natural gas (LNG) is natural gas which has been cooled down to a temperature that
converts it from a gas to a liquid that is 1/600th of its original volume. LNG enables large
volumes of natural gas to be stored and transported on specially designed vessels and
therefore provides an alternative to transporting natural gas via pipeline. LNG provides
access to alternative sources of natural gas. There is currently no import capability for LNG
in Ireland. This mitigation option is based on a floating LNG storage and regassification unit
(FSRU) which could be used on a non-commercial strategic basis. A FSRU is a non-fixed
LNG storage facility with an onboard regassification plant that is capable of returning
imported LNG to its original gaseous state and then supplying it directly into the onshore
gas network. FSRUs are usually moored at a jetty and can be refilled by other LNG vessels
that dock alongside it. When the FRSU [sic] is no longer required, it can be transported to
another location without leaving a large piece of stranded infrastructure behind. This
mitigation option assumes that the LNG FSRU could be leased for a limited period of time,
as a medium-term solution to mitigate more immediate security of supply concerns.
An alternative option could be to have an FSRU which is operated on a commercial basis but
with a mandated level of strategic storage held at all times so that in the event of a supply
shock a level of gas supply would be available immediately for the purpose of mitigating the
supply shock. An emerging advancement is the possibility to design hydrogen-ready LNG
facilities. For example, hydrogen can be stored as a gas using high pressure tanks or as a
liquid requiring cryogenic temperatures. A German utility is planning a ‘hydrogen-ready’
terminal for LNG in Germany which may incorporate a green ammonia terminal.”
83. Appendix B sets out a long-list of mitigation options and indication of whether they would
be shortlisted. A fixed LNG terminal (commercially operated) was not short-listed, for the following
reasons:
• “The introduction of commercial LNG would likely result in the importation of fracked
gas to Ireland.168 This would be in direct contradiction to the Government’s
opposition to the use of natural gas produced from fracking.169
• The additional energy requirements associated with LNG relative to natural gas
supplies (including liquefication, transport, and regasification) mean that the use of
LNG in Ireland may have an adverse impact on the Government’s decarbonisation
targets170 – e.g., the Programme for Government’s commitment to delivering a 7%
reduction in emissions each year to 2030).
• As storage stocks would be driven by market fundamentals, there would be no
guarantee that stored gas volumes would be sufficient to cover a security of supply
shock. This risk could be partially mitigated by requiring the LNG facility to hold a
minimum volume of LNG in reserve to meet any emergent security of supply
shocks.”
84. The footnotes are:
“168 We note that the Office of the Attorney General concluded in 2021 that it is not
possible for Ireland under the European Treaties or EU Directive to ban the import into
Ireland of fracked gas (available on gov.ie). Even if legally viable, it may be extremely
difficult in practice to isolate fracked gas within global LNG supply chains. For example, the
majority of US gas production is from fracking with injection into transportation
infrastructure before being exported. Restricting fracked gas would effectively mean
banning US LNG imports, which would restrict imports from one of the largest and most
reliable sources of LNG.
169 DECC (2021) ‘Policy Statement on the Importation of Fracked Gas’, available on
gov.ie
170 For example, the UK North Sea Transition Authority has estimated that LNG imports
into GB are on average over double the emission intensity of UK gas production and pipeline
gas imports from Norway. Available on nsauthority.co.uk.”
85. A floating LNG FSRU was also rejected for similar reasons (p. 140).
86. In passing, the logic of footnote 168 isn’t totally clear. Does it make sense to say that we
shouldn’t import LNG from the US so therefore we shouldn’t import LNG at all? The word “may” in
the phrase “may be extremely difficult” seems to be doing a lot of work.
87. More immediately, the logic for distinguishing quite so markedly between a commercial
facility (bad) and a state facility (good) is not overwhelmingly clear. Assuming that private sector
recourse to hydraulically-fractured gas or more general stimulation of demand for gas would be a
problem, it isn’t immediately obvious why that couldn’t be mitigated by planning conditions or some
other form of contractual or legal regulation, or if not, perhaps it could be explained why not.
88. On 26th September 2022, the two Nord Stream gas pipelines linking Germany to the
Russian Federation were sabotaged.
89. On 25th October 2022, the Irish Academy of Engineering made a submission. They
criticised the failure to examine the technical or financial feasibility of the supply mitigation options,
stating that “[h]olding a consultation on options which have not been technically or financially
examined is totally inappropriate in a context where the likely cost will be measured in billions and
the consequences of doing nothing are likely to result in major load shedding across the country”.
On the possible gas supply mitigation option of strategic LNG storage, they stated:
“FSRU’s are not designed for long term storage as such units, of necessity, lose up to 0.2%
of their gas per day, due to the fact that LNG is stored at minus 162 oC. This is described as
‘Boil Off Gas’ (BOG). This gas is normally injected into the gas grid. An FSRU with a typical
capacity of 160,000 m3 could lose 20% of its cargo (32,000m 3) over a 4 month period. If
long term storage is envisaged, BOG would need to be captured and injected into the gas
grid to avoid venting to the atmosphere. In this case the FSRU becomes an import facility
with an artificially constrained delivery.”
90. They stated that the assessment was “very much informed (or misinformed) by supposed
Government policy” and continuing:
“In short, the LNG option was eliminated due to Government policy. But this is not what
Government policy states. The Policy Statement on the Importation of Fracked Gas (May
2021) references the ongoing review of the security of Ireland’s energy supply and stated
that:
‘The review will inform whether it would be appropriate, or not, to develop LNG terminals in
Ireland and, if any such terminals were to be developed, whether they should only be in
order to provide a contingency supply in the event of failure of existing natural gas supply
infrastructure’.
CEPA should have examined the LNG option in an objective manner.
It makes absolutely no sense to rule out an Irish land-based LNG terminal on the basis of
reduced imports of fracked gas. Precisely the same quantity of fracked gas will be delivered
to the EU gas grid one way or another and we in Ireland will soon be 100% dependent on
that gas.”
91. The applicant made a submission on the technical analysis on 28th October 2022.
92. The submission points out the following:
“The impact of an outage affecting the gas interconnectors is, and always has been, the key
risk to Ireland's energy systems. While there are 2 separate pipelines, they join or pass
near each other at numerous points both onshore and subsea.”
93. The applicant made the case for a FSRU in its submission, and concluded inter alia that:
“Ireland must take the lead from other EU countries and bring all stakeholders together to
implement the most beneficial and viable projects without any ideological thinking getting
in the way of rational decision making.”
94. On 28th October 2022, Engineers Ireland, formerly the Institute of Engineers in Ireland,
made a submission that is published on their website. The first “key recommendation” (at p. 2) is
“[t]o balance the risks of natural gas supply to Ireland, it is prudent in the near term to deploy one
or more LNG floating storage and regasification units (FSRU) to achieve diversification of natural gas
supply routes”. With respect to any concern about LNG sourced from hydraulic fracturing, they state
(at p. 10) that “this specific risk can be largely avoided by direct national and/or EU oversight and
regulation”.
95. On 8th November 2022, the Minister for the Environment, Climate and Communications,
in a written answer to a parliamentary question, stated that over 400 responses had been received.
He stated that “[t]he completion of the review is a key priority. I will bring my security of energy
supply recommendations to Government once the review process has been completed”. On 21st
February 2023, in a written answer to a parliamentary question, the Minister stated that there had
been “over 450 responses”.
96. On 28th March 2023, the Minister for the Environment, Climate and Communications, in a
written answer to a parliamentary question, stated: “[t]he consultation responses have been
reviewed and analysed and have provided important insights with regard to energy security risks,
mitigation options and policy measures. I will bring my recommendations on energy security to the
Government shortly”.
97. On 5th April 2023, EirGrid plc and SONI Limited, in their capacity as system operators of
the Single Electricity Market on the island of Ireland, published the results of the 2026/2027 T-4
Capacity Auction (EirGrid ref. PCAR2627T-4) to ensure power generation capacity to meet security
of supply for the period 1st October 2026 to 30th September 2027
(https://www.eirgrid.ie/news/eirgrid-group-publishes-t-4-capacity-auction-results). Of the
7,204 MW cleared for award in the auction, 5,496 MW (76%) was from gas-fired power generation
units. The results include an award of capacity to the applicant for 353.2 MW (EirGrid ref.
GU_404590 and GU_404860).
98. On 9th April 2023, when asked if commercial LNG infrastructure would have to be built in
Ireland in the years ahead, the Minister for the Environment, Climate and Communications was
quoted as follows (Sunday Business Post, 9th April 2023, https://www.businesspost.ie/news/ryan-
mulls-green-policy-u-turn-on-commercial-lng-terminal/):
“The world changed a year ago when those Nord Stream gas pipelines were blown up in the
Baltic [Sea]. The concern about energy security and particularly gas pipelines was
heightened. So we do need a form of storage and an alternative gas supply route and gas
supply source so that, should anything happen, we have some protection. We can’t protect
against everything, but we do have a security issue there we have to address … The metrics
we will look at are: how much security can you get? Are you certain you can get an
alternative source of supply? How low-carbon is it? Because you can’t do something if it is
in breach of your climate limits. And what is the price? Those are the three things to
consider in any energy trilemma. We will look at it on that basis.”
99. On 27th April 2023, the Minister, in a written answer to a parliamentary question, stated:
“I will bring recommendations arising from the review to Government in Q2 for their consideration”.
100. On 16th May 2023, the “Long-term Strategy on Greenhouse Gas Emissions Reduction” was
published. This was prepared by the Department of Environment, Climate and Communications
under Regulation (EU) 2018/1999 on the governance of the energy union and climate action. This
acknowledges the importance of “security of gas supply infrastructure, particularly in the context of
electricity generation”, and “gas importation infrastructure (LNG)” among the mitigation solutions.
101. On 24th May 2023, in a written answer to a parliamentary question, the Minister stated
that would happen “in the near future”. On 15th June 2023, he stated that the Department was
“finalising the completion of the review, as a matter of priority”.
102. On 31st May 2023, the board invited the applicant to make a submission on the
observations received.
103. On 12th June 2023, the applicant responded to this request, including by pointing out that
the technical analysis was not itself Government policy.
104. The inspector’s report on the present application is dated 14th June 2023, and
recommended that the board refuse permission for part of the project, comprising the proposed
floating storage and regasification unit, jetty and onshore receiving facilities. The report
recommended that the board grant permission for the balance of the project, comprising the 600 MW
power plant, 120 MW battery energy storage system, above ground installation and all ancillary
structures/works.
105. The decision recites “policy documents” which it considered:
“5.0 Policy and Context
Regard is had to the following national, regional and local policy documents:
National
• National Planning Framework 2018
• National Development Plan 2021-2030
• National Marine Planning Framework 2020
• The Climate Action and Low Carbon Development (Amendment) Act 2021
• Climate Action Plan 2023
• National Adaptation Framework (NAF) (January 2018)
• Sectoral Emission Ceiling Limits (Sept 2022)
• The National Energy and Climate Plan (NECP) 2021-2030
• Government Policy Statement on the Importation of Fracked Gas (May 2021)
• Policy Statement on Security of Electricity Supply (November 2021)
• National Energy Security Framework (April 2022)
• Review of the security of energy supply of Ireland's electricity – Consultation Papers
(2022)
• National Ports Policy (2013)
Other Energy Sector Reports
• All-Island Generation Capacity Statement 2022-2031
• CRU Information Paper Security of Electricity Supply – Programme of Actions
• SEAI Energy Security in Ireland (2020)
• Long Term Resilience Study 2018
Regional and Local Policy
• Regional Spatial Economic Strategy for the Southern Region
• Strategic Integrated Framework Plan for the Shannon Estuary (SIFP)
• Kerry County Development Plan 2022-2028
• Listowel Municipal District Local Area Plan 2020 – 2026”
106. On pp. 81-82, the inspector reinforces this by saying that:
“It is therefore useful to identify some of the current policy provisions most relevant to this
case:
• The National Planning Framework 2018 promotes renewable energy use and
generation and identifies the single point of connection to the UK gas network in
Scotland and our limited gas storage capacity, as a risk to security of supply.
• The National Development Plan identifies the delivery of c.2GW of new conventional
generation capacity to support a predominantly wind/solar electricity system, as a
strategic investment priority. The review of the security of energy supply of
electricity and natural gas systems will inform Government policy in relation to
security of supply and the need for further investment.
• The Programme for Government (2020) states that as Ireland moves towards carbon
neutrality, it does not make sense to develop LNG gas import terminals importing
fracked gas.
• Targets and actions set out in the Climate Action Plan 2023 include the delivery of
c.2 GW of new flexible gas-fired power stations by 2030 and supports the phasing
out of hydraulic fracking at an international level.
• The Government Policy Statement on the Importation of Fracked Gas states that it
would not be appropriate for LNG terminals to be permitted or proceeded with
pending the outcome of the review of the security of energy supply of Ireland’s
electricity and natural gas systems. The National Energy & Climate Action Plan
2021-2030 notes that increased penetration of wind energy will increase reliance on
the gas network.
• The National Energy Security Framework 2022 notes that completion of the review
of security of energy supply, which will consider LNG import capacity, is a priority.
• The National Marine Planning Framework supports additional natural gas
transmission / import infrastructure where it is in keeping with the outcome of the
review of the security of energy supply and not involving the importation of fracked
gas.
• The Policy Statement on Security of Electricity Supply (November 2021) identifies
the development of new conventional as a national priority and should be permitted
and supported to ensure security of supply and support the growth of renewable
electricity generation.
• The Review of the Security of Energy Supply of Ireland’s Electricity And Natural Gas
Systems identifies options to mitigate risk of disruption to gas supply and electricity
generation, including strategic FSRU and Strategic gas storage capacity. (A public
consultation phase has closed and the review is currently being considered by the
Dept.)”
107. The applicant particularly complains about the last of these which it says is not a statement
of national policy. The board in submissions accepted that the consultation paper is not national
policy, but said that reference to it was not material to the decision and merely a statement of fact.
108. The applicant also complains that a critical policy statement to which the Government was
a party, the Versailles Declaration, is not mentioned.
109. The inspector’s analysis on the key issue is:
“10.3.1. General Policy Context
Policy in relation to energy security and supply, and climate change is a complex and
evolving area, subject to environmental, economic and geopolitical influences. It is not the
role of the Board to set policy and, in this regard I note that under s.143(1) of the 2000 Act,
as amended, the Board is required to have regard to:
(a) the policies and objectives of the Government, State authority, Minister,
planning authorities and any other body which is a public authority whose functions
have, or may have, a bearing on the proper planning and sustainable development
of cities, towns or other areas, whether urban or rural,
(b) the national interest and any effect the performance of the Board’s functions
may have on issues of strategic economic or social importance to the State, and
(c) the National Planning Framework and any regional spatial and economic strategy
for the time being in force.
Furthermore, the Climate Action and Low Carbon Development (Amendment) Act 2021
requires that public bodies perform their functions in a manner consistent with, inter alia,
the most recent approved climate action plan, national long term climate action strategy and
the furtherance of the national climate objective. These matters are considered in further
detail below. It is therefore useful to identify some of the current policy provisions most
relevant to this case:
• The National Planning Framework 2018 promotes renewable energy use and
generation and identifies the single point of connection to the UK gas network in
Scotland and our limited gas storage capacity, as a risk to security of supply.
• The National Development Plan identifies the delivery of c.2GW of new conventional
generation capacity to support a predominantly wind/solar electricity system, as a
strategic investment priority. The review of the security of energy supply of
electricity and natural gas systems will inform Government policy in relation to
security of supply and the need for further investment.
• The Programme for Government (2020) states that as Ireland moves towards carbon
neutrality, it does not make sense to develop LNG gas import terminals importing
fracked gas.
• Targets and actions set out in the Climate Action Plan 2023 include the delivery of
c.2 GW of new flexible gas-fired power stations by 2030 and supports the phasing
out of hydraulic fracking at an international level.
• The Government Policy Statement on the Importation of Fracked Gas states that it
would not be appropriate for LNG terminals to be permitted or proceeded with
pending the outcome of the review of the security of energy supply of Ireland’s
electricity and natural gas systems.
• The National Energy & Climate Action Plan 2021-2030 notes that increased
penetration of wind energy will increase reliance on the gas network.
• The National Energy Security Framework 2022 notes that completion of the review
of security of energy supply, which will consider LNG import capacity, is a priority.
• The National Marine Planning Framework supports additional natural gas
transmission / import infrastructure where it is in keeping with the outcome of the
review of the security of energy supply and not involving the importation of fracked
gas.
• The Policy Statement on Security of Electricity Supply (November 2021) identifies
the development of new conventional as a national priority and should be permitted
and supported to ensure security of supply and support the growth of renewable
electricity generation.
• The Review of the Security of Energy Supply of Ireland’s Electricity And Natural Gas
Systems identifies options to mitigate risk of disruption to gas supply and electricity
generation, including strategic FSRU and Strategic gas storage capacity. (A public
consultation phase has closed and the review is currently being considered by the
Dept.)
Energy security is described by the International Energy Agency (IEA) as ‘the uninterrupted
availability of energy sources at an affordable price’. Security is subject to variation and risk
in terms of demand for energy and supply thereof. Key variables on the supply side include
physical infrastructure (e.g. terminals, distribution networks) and international supply
chains. In considering the proposed development, it is useful to note the distinction between
security of gas supplies and security of electricity supply / generation. While there are
dependencies between these areas, recent concerns in relation to the capacity of the national
grid to meet demand for electricity relate primarily to electricity generation capacity rather
than supply of fuel.
At EU level, policy measures aim to provide for integration in the energy market, security of
energy supply and a sustainable energy sector. Regulations were introduced in 2010 and
2017 requiring Member States to undertake security of gas supply risk assessments and
ensure that adequate preventive action plans and emergency plans are developed to
mitigate identified risks. I note that such risks have intensified in the past year. RePower
(2022) aims to end reliance of the European market on Russian fossil fuels, including
increased deployment of renewables and diversification of gas supplies via pipelines and LNG
imports.
The technical report informing the Review of the Security of Energy Supply of Ireland’s
Electricity and Natural Gas Systems Consultation Paper (September 2022) notes the
interconnected nature of the European gas network and of supplies within the European
market. Notwithstanding the EU N1 standard, it would appear that the key gas supply risk
for Ireland relates to the risk of disruption to the single point of connection to the UK and
wider European gas market.”
110. At p. 239 onwards the inspector concludes:
“That permission be refused for the following elements of the development:
• A proposed Floating Storage and Regasification Unit (FSRU), with a Liquified Natural
Gas (LNG) storage capacity of 170,000 m3 (up to 180,000m3), 292.6m long and
43.4m wide, with a scantling draft water line of 12.9m.
• A proposed jetty, the deck of which will be set at +9 m OD (Malin Head), and ancillary
structures.
• Proposed onshore receiving facilities.
for the reasons and considerations set out below.
It is Government policy, as set out in the Policy Statement on the Importation of Fracked
Gas (May 2021), that it would not be appropriate to permit or proceed with the development
of any LNG terminals in Ireland pending completion of the review of the security of energy
supply of Ireland’s electricity and natural gas systems. Other policy statements, including
the National Marine Planning Framework 2020, National Energy Security Framework (2022)
and the National Energy & Climate Action Plan 2021-2030 confirm that completion of the
review is a key priority in considering risks to energy supply, and the need for energy
storage, fuel diversification and additional capacity to import energy.”
111. On 3rd August 2023, the “National Risk Assessment 2023: Overview of Strategic Risks”
was published by the Government. This recognises (at p. 16), with respect to sources for the supply
of energy, the “lack of diversity of supply sources and storage is a risk for security of supply”.
112. A board direction (Board ref. BD-013610-23) was made on 7th September 2023, which
stated that the submissions on file and the inspector’s report had been considered at board meetings
held on 29th May 2023, 31st August 2023, and 7th September 2023. It is recorded that the board
decided, by a majority of 8:2, to refuse permission for the project.
113. By order of the board (Board ref. ABP-311233-21), dated 13th September 2023, the board
refused permission for the project.
114. Departing from the inspector’s recommendation, the board refused permission outright
rather than in part only. Critically, the decision states:
“Reasons and Considerations
It is Government policy, as set out in the Policy Statement on the Importation of Fracked
Gas (May 2021), that it would not be appropriate to permit or proceed with the development
of any Liquified Natural Gas terminals in Ireland pending completion of the review of the
security of energy supply of Ireland’s electricity and natural gas systems. Other policy
statements, including Project Ireland 2040 National Marine Planning Framework, National
Energy Security Framework (2022) and the National Energy and Climate Action Plan 2021-
2023 confirm that completion of the review is a key priority in considering risks to energy
supply, and the need for energy storage, fuel diversification and additional capacity to import
energy.
The Review of the Security of Energy Supply of Ireland’s Electricity and Natural Gas Systems
(Department of the Environment, Climate and Communications Sept 2022) has been subject
to public consultation and the initial technical analysis does not support the development of
a commercially operated Liquified Natural Gas Floating Storage and Regasification Unit. The
review has not yet been completed.
Having regard to the above and to the nature and form of the proposed development which
constitutes an overall integrated facility incorporating an Liquified Natural Gas terminal and
with a clear focus on the use of Liquified Natural Gas as the primary fuel source for related
elements such as the proposed power station, it is considered that the development at this
time would be contrary to current government policy, and in the absence of such policy
support, such development would be contrary to the proper planning and sustainable
development of the area.”
115. On 14th November 2023, the Minister finally published the results of the Security of Supply
Review (https://www.gov.ie/en/consultation/dbe14-review-of-the-security-of-energy-supply-of-
irelands-electricity-and-natural-gas-systems/) comprising a report entitled “Energy Security in
Ireland to 2030, Energy Security Package” (Energy Security Report) and annexes, including (as
Annex 2) a report entitled “Securing Ireland’s Gas Supplies” (Gas Supply Report).
116. The applicant effectively stated that it was suspicious that the publication of the review was
held up until after the board decision.
117. The Energy Security Report identifies, as Action 17, the need to create a “Strategic Gas
Emergency Reserve to protect Ireland in the event of a gas supply disruption”. It is noted that by
2030, Ireland’s natural gas supplies are expected to be almost entirely from UK imports and that
should there be an interruption in supply on a day of peak gas demand due to low availability of
renewable sources, there is potential for up to 35% of gas demand being unmet, which would result
in “severe economic and social impacts”. It is stated that, based on the Department’s preliminary
analysis, it is anticipated that an FSRU will best meet the criteria set out. It is noted that this solution
is preferred by many EU Member States. However, the report also indicates that this is to be “State-
led”, meaning “commissioned by the State via GNI within a regulatory framework overseen by the
CRU”. The 2021 policy is listed in Appendix 2 as one of the “Major Policy Statements 2015-2023”.
118. The 2023 review oddly enough has minimal express reference to LNG apart from mentioning
the 2021 policy, but it includes the following:
“Based on preliminary analysis of the Department, it is anticipated that a floating reserve
(FSRU) will best meet these criteria, a solution preferred by a range of EU Member States.
However, this will be examined in detail by GNI with a substantive proposal by Q2 2024.
The optimum solution to deliver this strategic reserve project will be subject to final approval
by Government.”
119. The Gas Supply Report refers in §5 to the Technical Analysis. It refers at §§5.4-7 to the
choice of short-listed mitigation options from the long list, noting at §5.6 that only an FSRU could
fully mitigate unserved demand in the various shock scenarios considered, and at §5.7 that although
commercial LNG was long-listed, it was rejected for reasons including: “a) They would likely result
in the importation of fracked gas”. No further consideration is given to a commercial FSRU in the
Gas Supply Report; only a State-led FSRU is addressed. Mitigation Option E is “Offshore Gas
Emergency Reserve”, in the form of a FSRU. The Gas Supply Report notes, at §7.52:
“Introduction of this policy measure would require a change in policy which presently does
not allow for the development of LNG facilities.”
120. The applicant complains that since the 2021 document was only meant to be an interim
statement pending a review, its content should not have been relied on decisively to limit the options
to be considered in the review.
121. Despite publication of the Energy Security Report and its annexes, the 2021 policy has not
been formally terminated. The State’s submissions say this is because the Government has yet to
make a final decision.
122. The applicant has made two further applications to the board that are currently pending.
Application dates, ABP reference numbers and the links to those applications are as follows:
(i) 19th April 2024 – ABP-319566 - a 600 MW Powerplant, 120 MW Battery Energy
Storage System, Above Ground Installation and associated ancillary works
https://www.pleanala.ie/en-ie/case/319566; and
(ii) 29th July 2024 – ABP-320300 - a Gas Insulated Switchgear (GIS) substation
compound https://www.pleanala.ie/en-ie/case/320300.
123. Both files are currently with an inspector for completion of a report.
Procedural history
124. The proceedings were filed on 6th November 2023. On 7th November 2023, I allowed a
pre-leave amendment of the statement of grounds.
125. The matter was listed again on 13th November 2023, when leave was granted on standard
terms with the motion returnable for two weeks’ time.
126. The originating notice of motion was filed on 16th November 2023.
127. On 27th November 2023, the matter was adjourned for discussion regarding directions,
costs and whether Friends of the Irish Environment (who were, as noted above, litigants in previous
cases involving permissions in favour of the applicant) would get involved.
128. On 4th December 2023, the parties confirmed that costs protection applied, and Friends of
the Irish Environment expressly indicated that they were not getting involved. The matter was
adjourned to 18th December 2023.
129. On 18th December 2023, a timetable for directions was agreed between parties. The matter
was adjourned to March 2024.
130. At the list to fix dates on 11th March 2024, the court allocated a hearing date of 16th
September 2024. The matter was adjourned to 8th April 2024 for mention.
131. The first named respondent filed its opposition papers on 12th March 2024.
132. The second, third, fourth and fifth named respondents filed their opposition papers on 12th
April 2024.
133. On 15th April 2024, further directions were agreed, with the matter for mention on 29th July
2024 to confirm papers were in order.
134. The applicant filed its replying affidavit on 16th May 2024.
135. The applicant filed its written submissions on 3rd July 2024.
136. The first named respondent filed its written submissions on 18th July 2024.
137. The second, third, fourth and fifth named respondents filed their written submissions on 31st
July 2024.
138. In the light of the general reduction in hearing times set out in PD HC126, the time allocation
was reduced to two days. On foot of that, the matter was listed for mention on 9th September 2024
to attempt to focus the issues. Following that, the applicant sought liberty to put in a further affidavit
exhibiting relevant material.
139. The matter was then heard on 16th and 17th September 2024. The applicant’s solicitor’s
late affidavit was formally admitted on 17th September 2024 on the basis that the State would have
an opportunity to reply in the event of a further module, and judgment was reserved on that date.
Subsequent to the delivery of the original version of this judgment, there were then some procedural
and policy happenings which are summarised in the postscript and which resulted in an amended
judgment being issued, by consent of the parties, which re-opened the issue of core ground 3(vi),
which it was then not necessary to decide.
Relief sought
140. The reliefs sought in the amended statement of grounds are as follows:
“1. An Order of certiorari quashing the decision of the First Respondent, An Bord
Pleanála (the ‘Board’), made on 13 September 2023 (ref. ABP-311233-21) refusing
permission for strategic infrastructure development, comprising the Shannon Technology
and Energy Park consisting of 600 MW power plant, 120 MW battery energy storage system,
floating storage and regasification unit, jetty, onshore receiving facilities, above ground
installation and all ancillary structures/works, at Kilcolgan Lower and Ralappane,
Ballylongford, Co. Kerry (the ‘Project’).
2. A declaration that the decision of the Second Respondent, the Government of Ireland
(the ‘Government’), at the request of the Third Respondent, the Minister for Environment,
Climate and Communications, made on 18 May 2021 to adopt within the ‘Policy Statement
on the Importation of Fracked Gas’ a policy statement that ‘pending the outcome of the
review of the security of energy supply of Ireland’s electricity and natural gas systems, it
would not be appropriate for the development of any LNG terminals in Ireland to be
permitted or proceeded with’ is invalid. Strictly in the alternative, an Order of certiorari
quashing the said decision.
3. In the alternative, a declaration that the Project is not contrary to the said policy
statement of 18 May 2021.
3. If necessary, an Order, pursuant to Order 84, rule 21(3) of the Rules of the Superior
Courts, extending the time to seek the relief at paragraph 2 above.
4. Such declaration(s) as to the legal rights and/or legal position of the Applicant and
(if and insofar as legally permissible and appropriate) persons similarly situated and/or of
the legal duties and/or legal position of the Respondent as the court considers appropriate.
5. A declaration that protective cost provisions of section 50B of the Planning and
Development Act 2000 (as amended) (the ‘2000 Act’) and/or sections 3 and 4 of the
Environment (Miscellaneous Provisions) Act 2011, and/or Order 99 and/or section 169 of
Legal Services Regulation Act 2015, as interpreted in light of Article 9 of the Aarhus
Convention, apply to these proceedings.
6. Further or other order.
7. Liberty to Apply.
8. An Order in respect of the costs of these proceedings.”
Grounds of challenge
141. The core grounds of challenge are as follows:
“(1) Domestic Law Grounds
Grounds with respect to the relief sought at (d)(1), (3) to (8)
1. The decision of the Board made on 13 September 2023 (ref. ABP-311233-21)
refusing permission for the Project (the ‘Board Decision’) is invalid as the Board slavishly
adhered to a single policy statement of the Government, the ‘Policy Statement on the
Importation of Fracked Gas’ made on 18 May 2021 (the ‘Fracked Gas Policy’), to which the
Board was, in accordance with section 37G(2)(g) and 143 of the 2000 Act, obliged to ‘have
regard’ and/or ‘consider’ only. The Board applied the Fracked Gas Policy as if it were an
over-riding consideration and/or prohibition, and thereby abdicated its decision-making
function. Further particulars of which are set out in Part 2 below.
2. The Board Decision is invalid as the Board misinterpreted and misapplied the Fracked
Gas Policy, in particular by determining that the proposed development would be contrary
to the policy of discouraging the import of fracked gas and/or ensuring the State does
nothing to encourage or facilitate fracking elsewhere. The Board failed to properly interpret
the Fracked Gas Policy, which, in express terms, records that, on advice provided by the
Attorney General, ‘a legal ban on the importation of fracked gas could not be put in place at
this time’. The Fracked Gas Policy, and the commitment in the Programme for Government
to which it purports to give effect, are concerned only with the import of natural gas
extracted by ‘fracking’. The policy objective is to prevent import of fracked gas and/or to
ensure the State does nothing to encourage or facilitate fracking elsewhere. In the
alternative, the Board failed to consider whether that policy objective can be achieved by
other means, including by way of condition. Further particulars of which are set out in Part
2 below.
3. The Board Decision is invalid as the Board failed to consider and/or have regard,
properly or at all, to, and/or failed to give reasons that address, relevant considerations that
support the proposed development and/or contradict the Fracked Gas Policy, including:
(i) Kerry County Development Plan 2022 to 2028, which includes an express
objective (KCDP 12-3, at page 255) that supports the proposed development at this
specific location as follows, ‘facilitates the sustainable expansion of the gas network,
including the facilitation of a gas importation facility in the Tarbert/Ballylongford
Landbank’;
(ii) The ‘Electricity Crises: A Risk Preparedness Plan for Ireland’ prepared by the
Commission for Regulation of Utilities (‘CRU’) under Regulation (EU) 2019/941 on
risk preparedness in the electricity sector and published in April 2022, which
identifies (at page 26) fossil fuel (including natural gas) shortage to have a
disastrous’ impact, rated as major’;
(iii) The most recent ‘National Preventive Action Plan for Gas’ prepared by the
CRU under Regulation (EU) 2017/1938 concerning measures to safeguard the
security of gas supply (the ‘N 1 Regulation’), which identifies measures to safeguard
security of gas supply, and acknowledges (at pages 37-38) that the State does not
satisfy the N-1 requirement for security of gas supply;
(iv) The Versailles Declaration made by European Union leaders on 10 and 11
March 2022, on the Russian aggression against Ukraine, as well as reducing energy
dependencies, which expressly requires ‘diversifying our supplies and routes
including through the use of LNG and the development of biogas’ and ‘providing LNG
infrastructure’;
(v) The ‘Long-term Strategy on Greenhouse Gas Emissions Reduction’ prepared
by the Department of Environment, Climate and Communications under Regulation
(EU) 2018/1999 on the governance of the energy union and climate action, and
published by the United Nations (‘UN‘) on 16 May 2023, which acknowledges the
importance of ‘security of gas supply infrastructure, particularly in the context of
electricity generation’, and ‘gas importation infrastructure (LNG)’ among the
mitigation solutions; and/or,
(vi) The National Risk Assessment 2023: Overview of Strategic Risks’ published
by the Government on 3 August 2023, which recognises (at page 16), with respect
to sources for the supply of energy, the ‘lack of diversity of supply sources and
storage is a risk for security of supply’.
Further particulars of which are set out in Part 2 below.
4. The Board Decision is invalid as the Board had regard to an irrelevant consideration,
namely, the initial technical analysis prepared for the Minister for Environment, Climate and
Communications as part of the ongoing ‘Review of the Security of Ireland’s Electricity and
Gas System’ published for public consultation on 19 September 2022 (the ‘Security of Supply
Review’). Pending completion of the review, including the submissions received in response
to the publication consultation, these technical materials should be considered drafts that
are not relevant to the decision-making function of the Board. Further particulars of which
are set out in Part 2 below.
5. Without prejudice to core ground 4 above and in the alternative, the Board Decision
is invalid as the Board failed to properly interpret the initial technical analysis prepared as
part of the ongoing Security of Supply Review. The technical analysis does, in fact, consider
a gas supply mitigation option, including by reference to floating LNG terminal (commonly
called a Floating Storage and Regasification Unit (‘FSRU’)), as proposed within the Project.
In particular, it contemplated expressly ‘[a]n alternative option could be to have an FSRU
which is operated on a commercial basis but with a mandated level of strategic storage held
at all times so that in the event of a supply shock a level of gas supply would be available
immediately for the purpose of mitigating the supply shock.’ Further particulars of which
are set out in Part 2 below.
6. The Board Decision is invalid as the Board failed to properly consider the
recommendation made by its inspector to grant permission for part of the proposed
development, comprising the proposed power plant. The reasons given by the Board for
departure from the recommendation of its inspector do not justify, properly or at all, the
decision to refuse permission for the power plant. In particular, the Board’s reference to the
Strategic Integrated Framework for the Shannon Estuary is misplaced, in circumstances
where that was considered by Kerry County Council when making the Kerry County
Development Plan 2022 to 2028, which includes an express objective (KCDP 12-3) that
supports the proposed development at this specific location as follows, ‘facilitates the
sustainable expansion of the gas network, including the facilitation of a gas importation
facility in the Tarbert/Ballylongford Landbank’. Further particulars of which are set out in
Part 2 below.
(2) EU Law Grounds
7. The Board Decision is invalid as, notwithstanding that the Fracked Gas Policy was
adopted by the Government without complying with the European Communities
(Environmental Assessment of Certain Plans and Programmes) Regulations 2004 (SI No.
435 of 2004) (as amended) and/or Directive 2001/42/EC on strategic environmental
assessment, and notwithstanding that the environmental effects of the policy were not
considered before the policy was adopted, or applied by the Board, the Board has applied
the Fracked Gas Policy as if it were a plan or programme that sets the framework for
consents that require environmental impact assessment and further as if it were a plan or
programme that amends plans or programmes that were subject to environmental
assessment under the aforesaid Regulations and Directive. Further particulars of which are
set out in Part 2 below.
(3) Validity Grounds
Grounds with respect to the relief sought at (d)(2) to (8)
Without prejudice to core ground 2 above, and in the alternative:
8. The Fracked Gas Policy is invalid as the policy is a plan or programme that sets the
framework for consents that require environmental impact assessment, as it has exerted
decisive influence over the planning process for the proposed development, a project that
requires environmental impact assessment. The policy has been adopted in breach of the
European Communities (Environmental Assessment of Certain Plans and Programmes)
Regulations 2004 (SI No. 435 of 2004) (as amended) and/or Directive 2001/42/EC on
strategic environmental assessment. Further particulars of which are set out in Part 2 below.
9. The Fracked Gas Policy is invalid as, although the policy is expressed to apply to all
LNG terminals, there is only one such terminal proposed, the proposed development.
Section 30(1) of the 2000 Act provides that ‘the Minister [for Housing, Local Government
and Heritage] shall not exercise any power or control in relation to any particular case with
which a planning authority or the Board is or may be concerned’. The policy is a decision of
Government, a cabinet of Ministers that includes the Minister for Housing, Local Government
and Heritage. The policy is therefore in breach of section 30. Further, the policy is akin to
a Bill of Attainder that singles out an individual person, Shannon LNG Limited, for
burdensome treatment in breach of its rights to natural justice and/or to property under
Article 40.3 and 43 of the Constitution. Further particulars of which are set out in Part 2
below.
10. The Fracked Gas Policy is invalid as the policy that ‘it would not be appropriate for
the development of any LNG terminals in Ireland to be permitted or proceeded with’ is not
rationally connected to, and extends beyond, the recited evidential basis for the policy. It
is not necessary to prohibit a terminal of the kind proposed, where the objective is to ban
the import of fracked gas. Further particulars of which are set out in Part 2 below.
11. The Fracked Gas Policy is invalid as the policy acknowledges that it would not be
lawful to impose a ban on the import of fracked gas, simpliciter. The policy that ‘it would
not be appropriate for the development of any LNG terminals in Ireland to be permitted or
proceeded with’ is designed as a measure having equivalent effect, targeting only import of
LNG at a terminal, not import by interconnector pipeline or by ferry. Further particulars of
which are set out in Part 2 below.”
Core ground 4
142. Core ground 4 is:
“4. The Board Decision is invalid as the Board had regard to an irrelevant consideration,
namely, the initial technical analysis prepared for the Minister for Environment, Climate and
Communications as part of the ongoing ‘Review of the Security of Ireland’s Electricity and
Gas System’ published for public consultation on 19 September 2022 (the ‘Security of Supply
Review’). Pending completion of the review, including the submissions received in response
to the publication consultation, these technical materials should be considered drafts that
are not relevant to the decision-making function of the Board. Further particulars of which
are set out in Part 2 below.”
143. The parties’ positions as recorded in the statement of case are summarised as follows:
“Core Ground 4 - Technical analysis as irrelevant consideration
Applicant
The Applicant alleges that the Board was not entitled to have regard to the Technical
Analysis. The Technical Analysis was prepared as part of an ongoing review that was pending
when the Board considered the application. The Technical Analysis was akin to work in
progress or draft materials, to which no regard should have been had by the Board.
It is submitted that the Technical Analysis falls within the category of preliminary, scoping,
proposed, or consultative documents, which must be excluded from consideration. It is not
an expression of Government policy or a guideline to be followed. Rather, it was explicitly
recognised as an input to an ongoing review, which was not then complete.
The Board expressly relied on the Technical Analysis. On this basis also, the Board Decision
is invalid.
First Respondents
The Applicant claims the Board had regard to an irrelevant consideration – the initial
technical analysis prepared for the Minister as part of the ongoing Review (‘the Technical
Analysis’). The Applicant asserts that ‘the Board expressly relied on the Technical Analysis’
in its decision, thus falling into error. With respect, this complaint is subtended on a
misinterpretation and mischaracterisation of the Board’s Decision. The comments of the
Court in O’Donnell v An Bord Pleanála [2023] IEHC 381 are particularly apt – one must read
the decision ‘not solely from an applicant’s point of view (an impossible standard), but from
the starting point of it being valid rather than invalid where possible. One has to stand back
and ask what the decision is fundamentally saying’. When this is done, it is clear this ground
is without substance.
The Applicant’s assertion that the Inspector and Board relied’ on the Technical Analysis in
determining the application is not correct. Same misunderstands the Inspector’s Report and
Board’s Decision which only referred to the Technical Analysis for the purposes of outlining
that the Review was not yet complete and that the Fracked Gas Policy remained the relevant
policy in such circumstances. This comprises nothing more than a correct statement as to
the status of the Review –there was no legal error in the Board’s approach.
Second, Third, Fourth and Fifth Respondents
Core Ground No. 4 is directed at the Board and is not addressed by the State Respondents.”
144. While there is an analogy with Element Power Ireland Ltd v. An Bord Pleanála [2017] IEHC
550, [2017] 9 JIC 2802 (Unreported, High Court, Haughton J., 28th September 2017) in terms of
the issue of reliance on draft documents, there is an underlying dimension to that complaint which
is in effect error in the record by the classification of the consultation document as an instrument of
“national policy”.
145. The basic problem with the inspector’s report is that it lists a mere departmental
consultation document under the heading of “national … policy”. That is the inspector’s term, not
mine, and the lack of an alternative analysis in the board decision implies reliance on the inspector’s
report.
146. The board didn’t seek to defend the concept that the consultation document was national
policy. Rather it pleaded that it was contextual or something of that nature. But the indiscriminate
listing of the document as an instrument of national policy is clearly an error on the face of the
record. If the board is determined to base its decisions on policy, it needs to be able to clearly,
lawfully and accurately relate any given instrument to the appropriate category of document to which
it is directed to have regard under the 2000 Act. That was not done here because of the mis-
classification of this document as one of national policy.
147. Compounding this, it is clear that the technical analysis is in part relied on in coming to the
inspector’s conclusions:
“The Review of The Security of Energy Supply of Ireland’s Electricity and Natural Gas
Systems (Department of the Environment, Climate and Communications Sept 2022) has
been subject to public consultation and the initial technical analysis does not support the
development of a commercially operated Floating LNG FSRU. The review has not yet been
completed.”
148. The context of this statement is as part of the reasoning, and not a mere background detail.
So this can’t be dismissed as a mere immaterial side-note. Both the misclassification in itself, and
the regard in the operative reasoning to a draft document (returning to Haughton J. in Element
Power Ireland Ltd v. An Bord Pleanála), constitute reviewable legal error.
149. The board’s argument in reliance on Hogan J. in Killegland Estates Ltd v. Meath County
Council [2023] IESC 39, [2023] 12 JIC 2109 (Unreported, Supreme Court, 21st December 2023)
doesn’t apply here, particularly because the review is wired in to the critical section of the inspector’s
reasoning. This isn’t immaterial. And even counterfactually if it could be viewed as such, the board
didn’t plead in their statement of opposition that any error should be disregarded as immaterial.
150. Consequently I would uphold core ground 4 on this basis.
Conclusion on the decision
151. Having regard to the specific ground being upheld as above, it is not necessary in the
particular circumstances to address the remaining grounds of challenge (see also Practice Direction
HC126 para. 123). I can note for completeness that core ground 6 was withdrawn.
Challenge to the Policy
Whether the challenge to the policy arises having regard to the foregoing
152. The threshold issue under this heading is, given that the board’s decision is being quashed,
whether the court should proceed to entertain a challenge to the policy. The State submits:
“3. As already noted, the proceedings primarily relate to the validity of the decision of
the Board to refuse planning permission and the challenge to the Policy Statement is brought
in the alternative. Consequently, pursuant to the principle of judicial restraint, the challenge
to the Policy Statement will only be required to be addressed where the Applicant does not
obtain relief against the Board.”
153. What was agreed by the parties was that if the applicant was unsuccessful against the board,
there would be a second module against the State, but if the applicant was successful the court
could indicate a provisional view as to the necessity for a second module and the parties could have
liberty to apply.
154. In that regard, the State’s position, logically, was that the challenge to the policy could be
postponed so that it would only arise in the event that the applicant didn’t succeed against the board.
The applicant and the board seemed to think that the policy should be assessed either way.
155. My provisional view subject to contrary argument is as follows.
156. The normal rule is that when a decision is quashed, it is not necessary or prudent to go on
to examine the validity of a measure of general application which fed into the decision. If a fresh
decision is made on remittal, and is then challenged and found to be intra vires, the challenge to
any measures of general application could more properly be considered at that hypothetical future
point. That process ensures that the court does not rush into assessing the validity of legislation or
other measures of general application unless it is actually necessary to do so. That is for a number
of reasons – separation of powers more generally, plus the lack of any power vested in the court to
fill any vacuum that it might create by invalidating a general measure. So that’s the conclusion
promoted by the principle of judicial restraint.
157. That conclusion is reinforced here by a couple of context-specific factors.
158. Firstly, the number of moving parts and the fact that matters have somewhat evolved since
the bare 2021 policy, which has the effect that any reconsidered application would be dealt with in
a different policy context whatever happens. At a minimum, one can see the argument that the
2021 document in isolation ceased to represent the totality of government policy in this area no
later than March 2022. And policy continues to evolve.
159. It seems unfortunate that the 2023 review was not available when the board made its
decision. On the face of things, the application is basically consistent with the outcome of the 2023
review, particularly if the identity of the owner of any particular facility is taken not to be a proper
planning consideration. The State on one view impliedly accepted this by saying that “The ownership
of the facility isn’t the issue it’s the function of the facility”. The State’s concern essentially is that
a commercial facility would import and store more LNG than strategically necessary whereas a State-
led facility would be confined to what was necessary for energy security as opposed to anything that
would increase demand for fossil fuels. But again it is not obvious that constraints on the use of the
facility could not be put in place in some way such as by condition.
160. Relatedly, the applicant alleges that the board didn’t adequately consider whether the
application could have been allowed notwithstanding the language of the 2021 document (essentially
a Yoon-type issue). Whether that’s correct or not, something I don’t need to decide, the legal
proposition certainly is correct that the board isn’t bound by Government policy, which means that
remitted application is not necessarily doomed to the same fate, even if the 2021 policy is allowed
stand for the time being.
161. In addition, the fact that two further applications have been made to the board by the
applicant may dilute the case to review the 2021 policy at this stage.
162. A final factor is the somewhat exiguous nature of the pleaded challenge, which the applicant
has sought to expand in the written submissions and then to contract somewhat in the oral
submission, in that it didn’t seem to be pressing ground 11 as currently drafted. That ground sought
to assert, rather than establish (by reference to specific legislation), that prohibition of LNG facilities
would be contrary to EU law. This is not as obvious a proposition as the applicant seems to have
thought, and isn’t established merely because the Government thought that too. Post-2021 policy
developments are not challenged in the present proceedings. Indeed, many of the applicant’s
complaints about the Government policy and actions aren’t embodied in pleaded grounds in the
present case. For instance, it isn’t suggested that the policy is factually unreasonable, or that the
Government delay in finalising the review is unreasonable and contradictory of its acceptance at
European level that changes to energy policy are urgent, or that there was a suspicious delay in
advancing the review so that the application would be refused. Insofar as there are dimensions to
the 2021 policy and subsequent statements that are puzzling and unexplained, it would be up to an
applicant to evidentially develop that. To the extent that the applicant has made various criticisms
of the Government which don’t correspond to specific legal pleas, there wouldn’t be a whole lot that
a court could do about that in any event. In such circumstances an examination of the validity of
the 2021 policy on foot of the present challenge might be unsatisfactory at best. But that is without
prejudice to the applicant’s right to complain about the 2021 policy or any subsequent policy
instrument in any hypothetical future proceedings should that become necessary.
Conclusion and summary
163. In concluding, I emphasise that I wouldn’t wish to be taken as commenting for or against
the merits of the project for which permission was sought. With that overarching point firmly in
mind, and with all due respect to all interested parties whether before the court or not, if comment
of any sort can be forgiven I would confine it to emphasising the potential advantages of some fairly
neutral values (which we do make some efforts to embody at the judicial end of things), specifically
the benefits of a hearing, of dialogue, and of efficiency in decision-making.
164. As regards the need for giving interested parties a hearing, I don’t want to either endorse
or criticise the review process, about which people will have to make their own minds up for now.
The applicant complains effectively that the review was rigged by a kind of Balz-type a priori
exclusion of a commercial LNG terminal, not on the basis that it doesn’t make sense economically,
environmentally or in terms of energy security, but because it was contrary to the interim
Government policy. Since the policy was meant to be interim pending the review, the applicant
effectively characterises that as circular reasoning and “Kafkaesque”. Defenders of the process
might say that there is no point in this context or any context on wasting time examining options
that have been ruled out politically. Whatever one’s point of view, and one could argue the
desirability of such ruling-out either way, on the documents before the court and the express
conclusions in the review material, it’s obvious that whatever it was, the review clearly wasn’t an
entirely open-minded and thorough consideration of all economic and environmental pros and cons
of all potential options. The applicant’s preference was effectively ruled out (if not quite in limine)
on Government policy (i.e., political) grounds. That’s just a fact as it appears from the material
before the court. That isn’t criticism of the consultants. It’s up to the Government in the first
instance to make its own decision as to whether that is the appropriate basis for any final policy
stance. Again, to repeat, I’m not criticising the Government’s policy positions, which are a matter
for them; merely being clear factually that insofar as concerns ruling out a commercial LNG terminal,
the review doesn’t rationally provide an independent foundation for that conclusion because the
interim policy has significantly influenced the outcome of the review, which is therefore a
consequence of rather than a support for the a priori policy stance.
165. As far as dialogue is concerned, it’s true that the Minister wasn’t in a position to meet the
applicant at a particular point in time. But a lot has happened since then, and if and insofar as there
might be any prospect of dialogue in the reasonable medium term between the applicant and the
Government at whatever level and perhaps other institutional stakeholders as to the options for the
future of this site, whatever they might be, and whether or not in the Government’s view those
options include the precise project for which consent was sought, can I be forgiven for encouraging
that – in the interests of reducing the amount of future litigation on these issues if nothing else.
166. Finally, as regards efficiency in decision-making, it would appear on the face of things
desirable for there to be an actual conclusion to the review of energy security and gas supply policy
that has been ongoing for the best part of two and a half years. The State in submissions effectively
sought to attribute the delay to the Russian Federation’s full-scale invasion of Ukraine, but that
should be a reason to speed matters up, not to slow them down. If a decision isn’t made, the board
on remittal of the application would be left, yet again, without a final policy position to assist it to
the extent that assistance is legally relevant. But, even acknowledging that there may well be a
case for some further thought and analysis, if nonetheless the proceedings result in encouragement
to the executive to take the plunge in the relatively near future into final decisions and actions, they
will perhaps have been worthwhile beyond the legally conventional and relatively unremarkable
issues formally being addressed.
167. On those fairly unremarkable issues, in outline summary, and without taking from the more
specific terms of this judgment:
(i) the board misclassified a consultation document by listing it under the heading of
national policy and relatedly incorrectly considered such draft consultation material
as part of the substantive decision, which is an error in lawful consideration;
(ii) accordingly, core ground 4 is being upheld to the extent outlined in the judgment;
and
(iii) in the light of the foregoing, it is not necessary to decide the remaining grounds of
challenge or, subject to any further argument to the contrary, to address the
challenge to the 2021 policy document, to which the principle of judicial restraint
applies.
Order of 30th September 2024
168. For the foregoing reasons, it is ordered that:
(i) there be an order of certiorari in terms of relief 1;
(ii) unless any party applies otherwise by written legal submission within 14 days from
the date of this judgment:
(a) the matter be remitted to the first named respondent for reconsideration
and decision in accordance with law;
(b) there be no order on the other reliefs claimed save as otherwise provided,
without prejudice to the applicant’s right to seek such reliefs in future
hypothetical proceedings;
(c) the foregoing order be perfected forthwith thereafter on the basis of an order
for costs (including the costs of written submissions and certifying for two
counsel in respect of any applications) being awarded to the applicant
against the first named respondent, and no order as to costs in favour of or
against any other party; and
(iii) the matter be listed at 09:30 on Monday 14th October 2024 to confirm the foregoing.
Postscript – order of 24th March 2025
169. The original version of the foregoing judgment was delivered on 30th September 2024. The
board then indicated an intention to seek leave to appeal. But before that came on for hearing,
there were a number of seismic developments regarding the underlying policy situation. On 8th
November 2024, the Dáil was dissolved. On 23rd January 2025, a new Government took office. On
4th March 2025, the new Government approved a plan to develop a State-led LNG terminal and
terminated the former fracking policy in doing so. The net effect of those developments was that it
was no longer necessary for the current issues between the parties to be resolved by further judicial
decision. My willingness to agree to the board’s suggestion to facilitate the conclusion of the litigation
by narrowing the scope of the judgment on consent derives from the basic point that “Litigation is
not in itself an intrinsically desirable activity” (O’Donnell J. in Rooney v. Minister for Agriculture and
Food [2016] IESC 1 (Unreported, Supreme Court, 28th January 2016) at para. 2). Judgments aren’t
an end in themselves – they are there to resolve differences that would not be resolved otherwise,
not to prevent resolution of a matter which could be resolved but for a judgment. If a consent
amendment of a judgment, especially a purely negative refinement to narrow the issues needing to
be addressed, would serve the purpose of achieving consensual resolution then I think a court should
be willing to put its shoulder to the wheel. In this case, in the light of the above-mentioned
developments, the parties agreed to an order as follows, which was made on 24th March 2025:
(i) by consent, the original judgment be amended by the re-opening of issues related
to core ground 3(vi) with the effect that in the light of the terms of the consent order
it would no longer be necessary to address that ground;
(ii) by consent, it be noted that the court re-affirms the very specific factual nature of
the finding on core ground 4 and accordingly notes that the finding does not have
more general precedential value;
(iii) by consent, the order set out (in part provisionally) at para. 168(i) and (ii) in the
original judgment be perfected forthwith along with the following orders;
(iv) by consent, there be an order striking out the leave to appeal application with no
order as to costs; and
(v) by consent, in addition to the costs in favour of the applicant at para. 168(ii)(c)
above up to 30th September 2024, there be an order for the applicant’s costs
(certifying for two counsel) of the mention date on 14th October 2024, and no order
as to the costs of the proceedings after that date.