High Court refers EU planning law questions to CJEU regarding strict protected species derogations.
Legislator summary
AI generatedThe High Court adjourned the proceedings to refer preliminary questions to the Court of Justice of the European Union regarding the interpretation of EU directives on habitat protection. Applicants challenged a derogation licence for residential construction at Delgany, arguing it violated strict protected species rules without sufficient justification. The court determined that the substantive legality of the licence could not be decided without clarification from the CJEU on whether development interests can override strict species protections.
Legislator headnote
AI generatedArticle 16(1) of Directive 92/43; Article 11 of Directive 2011/92: Derogations for development projects must be justified by imperative reasons of overriding public interest and cannot simply facilitate construction without considering alternatives that avoid prohibited activities affecting strictly protected species.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
[2023] IEHC 715
THE HIGH COURT
PLANNING & ENVIRONMENT
[H.JR.2021.00000251]
IN THE MATTER OF SECTIONS 50, 50A AND 50B OF THE PLANNING AND DEVELOPMENT
ACT 2000 AND
IN THE MATTER OF THE PLANNING AND DEVELOPMENT (HOUSING) AND RESIDENTIAL
TENANCIES ACT 2016
BETWEEN
ALICE O’DONNELL, COLIN ACTON, SEÁN GOFF, EVELYN CAWLEY, DECLAN MORRIS,
CIARA MAN, GARETH MADDEN, AILEEN LENNON, KEITH SCANLON AND CARINA HARTE-
HOLMES
APPLICANTS
AND
AN BORD PLEANÁLA, MINISTER FOR HOUSING, LOCAL GOVERNMENT AND HERITAGE,
IRELAND AND THE ATTORNEY GENERAL
RESPONDENT
AND
DRUMAKILLA LIMITED
NOTICE PARTY
(No. 3)
JUDGMENT of Humphreys J. delivered on Thursday the 21st day of December, 2023
1. This request for a preliminary ruling concerns the interpretation of Article 16(1) of Directive
92/43 and of Article 11 of Directive 2011/92 insofar as it relates to that provision.
2. The request is being made in proceedings concerning a challenge to the legality of a
derogation licence to facilitate the proposed construction of residential units and associated works
at the former Carmelite monastery at Delgany, County Wicklow.
Legal context
European Union law
3. Article 16(1) of Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural
habitats and of wild fauna and flora OJ L 206 22.7.1992, p. 7-50 provides:
“1. Provided that there is no satisfactory alternative and the derogation is not detrimental
to the maintenance of the populations of the species concerned at a favourable conservation
status in their natural range, Member States may derogate from the provisions of Articles
12, 13, 14 and 15 (a) and (b):
(a) in the interest of protecting wild fauna and flora and conserving natural habitats;
(b) to prevent serious damage, in particular to crops, livestock, forests, fisheries and water
and other types of property;
(c) in the interests of public health and public safety, or for other imperative reasons of
overriding public interest, including those of a social or economic nature and beneficial
consequences of primary importance for the environment;
(d) for the purpose of research and education, of repopulating and re-introducing these
species and for the breedings operations necessary for these purposes, including the artificial
propagation of plants;
(e) to allow, under strictly supervised conditions, on a selective basis and to a limited extent,
the taking or keeping of certain specimens of the species listed in Annex IV in limited
numbers specified by the competent national authorities.”
4. Article 6 of Directive 2011/92 provides:
“1. Member States shall take the measures necessary to ensure that the authorities likely
to be concerned by the project by reason of their specific environmental responsibilities or
local and regional competences are given an opportunity to express their opinion on the
information supplied by the developer and on the request for development consent, taking
into account, where appropriate, the cases referred to in Article 8a(3). To that end, Member
States shall designate the authorities to be consulted, either in general terms or on a case-
by-case basis. The information gathered pursuant to Article 5 shall be forwarded to those
authorities. Detailed arrangements for consultation shall be laid down by the Member States.
2. In order to ensure the effective participation of the public concerned in the decision-
making procedures, the public shall be informed electronically and by public notices or by
other appropriate means, of the following matters early in the environmental decision-
making procedures referred to in Article 2(2) and, at the latest, as soon as information can
reasonably be provided:
(a) the request for development consent;
(b) the fact that the project is subject to an environmental impact assessment procedure
and, where relevant, the fact that Article 7 applies;
(c) details of the competent authorities responsible for taking the decision, those from which
relevant information can be obtained, those to which comments or questions can be
submitted, and details of the time schedule for transmitting comments or questions;
(d) the nature of possible decisions or, where there is one, the draft decision;
(e) an indication of the availability of the information gathered pursuant to Article 5;
(f) an indication of the times and places at which, and the means by which, the relevant
information will be made available;
(g) details of the arrangements for public participation made pursuant to paragraph 5 of this
Article.
3. Member States shall ensure that, within reasonable time-frames, the following is made
available to the public concerned:
(a) any information gathered pursuant to Article 5;
(b) in accordance with national legislation, the main reports and advice issued to the
competent authority or authorities at the time when the public concerned is informed in
accordance with paragraph 2 of this Article;
(c) in accordance with the provisions of Directive 2003/4/EC of the European Parliament and
of the Council of 28 January 2003 on public access to environmental information ( 7 ),
information other than that referred to in paragraph 2 of this Article which is relevant for the
decision in accordance with Article 8 of this Directive and which only becomes available after
the time the public concerned was informed in accordance with paragraph 2 of this Article.
4. The public concerned shall be given early and effective opportunities to participate in
the environmental decision-making procedures referred to in Article 2(2) and shall, for that
purpose, be entitled to express comments and opinions when all options are open to the
competent authority or authorities before the decision on the request for development
consent is taken.
5. The detailed arrangements for informing the public, for example by bill posting within a
certain radius or publication in local newspapers, and for consulting the public concerned,
for example by written submissions or by way of a public inquiry, shall be determined by the
Member States. Member States shall take the necessary measures to ensure that the
relevant information is electronically accessible to the public, through at least a central portal
or easily accessible points of access, at the appropriate administrative level.
6. Reasonable time-frames for the different phases shall be provided for, allowing sufficient
time for:
(a) informing the authorities referred to in paragraph 1 and the public; and
(b)
the authorities referred to in paragraph 1 and the public concerned to prepare and participate
effectively in the environmental decision-making, subject to the provisions of this Article.
7. The time-frames for consulting the public concerned on the environmental impact
assessment report referred to in Article 5(1) shall not be shorter than 30 days.”
5. Article 11 of Directive 2011/92 provides:
“1. Member States shall ensure that, in accordance with the relevant national legal system,
members of the public concerned:
(a) having a sufficient interest, or alternatively;
(b) maintaining the impairment of a right, where administrative procedural law of a Member
State requires this as a precondition;
have access to a review procedure before a court of law or another independent and impartial
body established by law to challenge the substantive or procedural legality of decisions, acts
or omissions subject to the public participation provisions of this Directive.
2. Member States shall determine at what stage the decisions, acts or omissions may be
challenged.
3. What constitutes a sufficient interest and impairment of a right shall be determined by
the Member States, consistently with the objective of giving the public concerned wide
access to justice. To that end, the interest of any non-governmental organisation meeting
the requirements referred to in Article 1(2) shall be deemed sufficient for the purpose of
point (a) of paragraph 1 of this Article. Such organisations shall also be deemed to have
rights capable of being impaired for the purpose of point (b) of paragraph 1 of this Article.
4. The provisions of this Article shall not exclude the possibility of a preliminary review
procedure before an administrative authority and shall not affect the requirement of
exhaustion of administrative review procedures prior to recourse to judicial review
procedures, where such a requirement exists under national law.
Any such procedure shall be fair, equitable, timely and not prohibitively expensive.
5. In order to further the effectiveness of the provisions of this Article, Member States
shall ensure that practical information is made available to the public on access to
administrative and judicial review procedures.”
6. It was common ground between the parties that Article 11 of Directive 2011/92 applies to a
challenge to a screening decision, not just to a decision following environmental assessment: the
judgment of 15 October 2015, Commission v Germany, C-137/14, ECLI:EU:C:2015:683 at §48 and
49, the judgment of 16 April 2015, Gruber, C-570/13, ECLI:EU:C:2015:231; the judgment of 7
November 2018, Flausch and Others, C-280/18, ECLI:EU:C:2019:928, paras. 46 and 47.
Additionally, the applicant’s submission was that the “Aarhus Convention Compliance Committee in
case ACCC/C/2010/50 concerning compliance by the Czech Republic held that an EIA screening
decision is a determination under Article 6(1)(b) of the Convention and therefore the provisions of
Article 9(2) apply which require that the public concerned have access to a review procedure to
challenge the legality of the outcome of the EIA screening process”.
7. Other relevant EU law includes:
(i) Judgment of 16 June 2005, Pupino, C-105/03, ECLI:EU:C:2005:386,
(https://curia.europa.eu/juris/document/document.jsf?text=&docid=59363&pageIn
dex=0&doclang=en&mode=lst&dir=&occ=first&part=1&cid=3072819);
(ii) Judgment of 19 September 2006, Germany GmbH and Arcor AG & Co. KG, C-39/04
and C-422/04, ECLI:EU:C:2006:586,
(https://curia.europa.eu/juris/showPdf.jsf?text=&docid=64424&pageIndex=0&docl
ang=en&mode=lst&dir=&occ=first&part=1&cid=3068255), para. 57;
(iii) Judgment of 15 April 2008, Impact v Minister for Agriculture and Food and others,
C-268/06, ECLI:EU:C:2008:223,
(https://curia.europa.eu/juris/document/document.jsf?text=&docid=71395&pageInd
ex=0&doclang=en&mode=lst&dir=&occ=first&part=1&cid=3070637) ;
(iv) Judgment of 28 January 2010, Commission v Ireland, C-456/08, ECLI:EU:C:2010:46,
https://curia.europa.eu/juris/document/document.jsf?text=&docid=84093&pageInd
ex=0&doclang=en&mode=lst&dir=&occ=first&part=1&cid=3071121);
(v) Judgment of 30 June 2011, Meilicke and Others, C-262/09, ECLI:EU:C:2011:438,
(https://curia.europa.eu/juris/document/document.jsf?text=&docid=106024&pageI
ndex=0&doclang=en&mode=lst&dir=&occ=first&part=1&cid=3066169) para 55;
(vi) Judgment of 18 October 2012, Pelati v Republika Slovenija, C-603/10,
ECLI:EU:C:2012:639, (https://eur-lex.europa.eu/legal-
content/EN/TXT/HTML/?uri=CELEX:62010CJ0603 ), para 36;
(vii) Judgment of 20 December 2017, Caterpillar Financial Services, C-500/16,
EU:C:2017:996, (https://eur-lex.europa.eu/legal-
content/EN/TXT/HTML/?uri=CELEX:62010CJ0603),paragraph 42;
(viii) Judgment of 15 March 2018, North East Pylon Pressure Campaign and Sheehy, C-
470/16, ECLI:EU:C:2018:185
(https://curia.europa.eu/juris/document/document.jsf?text=&docid=200265&pageI
ndex=0&doclang=en&mode=lst&dir=&occ=first&part=1&cid=3073072);
(ix) Judgment of 10 October 2019, Luonnonsuojeluyhdistys Tapiola, C-
947/17,ECLI:EU:C:2-19:851, (https://eur-lex.europa.eu/legal-
content/EN/TXT/?uri=CELEX:62017CJ0674);
(x) Opinion of the Advocate General of 21 October 2021, C-463/20, Namur-Est
Environnement, EU:C:2021:868 (https://eur-lex.europa.eu/legal-
content/EN/TXT/?uri=CELEX:62020CC0463);
(xi) Judgment of 24 February 2022, C-463/20, Namur-Est Environnement,
ECLI:EU:C:2022:121 (https://eur-lex.europa.eu/legal-content/EN/TXT);
(xii) Judgment of 6 July 2023, Hellfire Massy Residents Association, C-166/22,
ECLI:EU:C:2023:545,
(https://curia.europa.eu/juris/document/document.jsf?text=&docid=243867&pageI
ndex=0&doclang=en&mode=lst&dir=&occ=first&part=1&cid=2801329) ; and
(xiii) Judgement of 15 June 2023, Eco Advocacy, C-721/21, ECLI:EU:C:2023:477,
(https://curia.europa.eu/juris/document/document.jsf?text=&docid=274644&pageI
ndex=0&doclang=en&mode=lst&dir=&occ=first&part=1&cid=2805135).
Domestic law
8. Section 4 of the Planning and Development (Housing) and Residential Tenancies Act 2016
(as enacted - https://www.irishstatutebook.ie/eli/2016/act/17/enacted/en/html) allowed (prior to
its repeal) for strategic housing development applications.
9. Order 84 r. 21(1) to (5) of the Rules of the Superior Courts (RSC)
(https://www.courts.ie/rules/judicial-review-and-orders-affecting-personal-liberty) states:
“21. (1) An application for leave to apply for judicial review shall be made within three
months from the date when grounds for the application first arose.
(2) Where the relief sought is an order of certiorari in respect of any judgement, order,
conviction or other proceeding, the date when grounds for the application first arose shall
be taken to be the date of that judgement, order, conviction or proceeding.
(3) Notwithstanding sub-rule (1), the Court may, on an application for that purpose, extend
the period within which an application for leave to apply for judicial review may be made,
but the Court shall only extend such period if it is satisfied that:
(a) there is good and sufficient reason for doing so, and
(b) the circumstances that resulted in the failure to make the application for leave within
the period mentioned in sub-rule (1) either:
(i) were outside the control of, or
(ii) could not reasonably have been anticipated by
the applicant for such extension.
(4) In considering whether good and sufficient reason exists for the purposes of sub-rule
(3), the court may have regard to the effect which an extension of the period referred to in
that sub-rule might have on a respondent or third party.
(5) An application for an extension referred to in sub-rule (3) shall be grounded upon an
affidavit sworn by or on behalf of the applicant which shall set out the reasons for the
applicant’s failure to make the application for leave within the period prescribed by sub-rule
(1) and shall verify any facts relied on in support of those reasons.”
10. In accordance with established European and domestic caselaw, and in particular with the
principle of effectiveness, the domestic law power to extend time under O. 84 r. 21(3) RSC is
susceptible to a conforming interpretation such that it can and must be exercised in such a way as
to provide for the full period (in this case, 3 months) to run from the date on which an applicant is
or ought to be aware of the impugned decision. However the applicants made no application here
for an extension of time.
11. There is no specific statutory or regulatory provision in Irish law specifying how Article 11(2)
of Directive 2011/92 applies to derogation decisions under Article 16(1) of Directive 92/43.
12. Therefore general principles of statutory interpretation apply. The general national law
principle is that interim decisions should be challenged following the final decision in a procedure,
but while this is the predominant approach, this principle has not been applied consistently. However
as a matter of domestic law the derogation licence is not an interim decision. The referring court
concludes that in domestic law, and subject to any requirements of conforming interpretation, where
a project requires multiple consents, each consent is a separate substantive decision which are to
be individually challenged within the statutory period running individually from the date of each
decision. Such a situation is not a series of interim decisions leading to a final definitive consent.
13. Thus a derogation decision is a separate decision in law so that the time for judicial review
commences when that decision is made, not when the related development consent is granted.
14. The referring court concludes that the time limits for challenge to the derogation licence are
reasonably foreseeable by reference to the general law on judicial review.
15. Other relevant domestic law includes:
(i) Sections 50 and 50A of the Planning and Development Act 2000 (as amended):
https://revisedacts.lawreform.ie/eli/2000/act/30/revised/en/html#SEC50 ;
(ii) Planning and Development Regulations 2001 to 2023 (SI 600 of 2001), as amended
(unofficial consolidation):
https://assets.gov.ie/135619/1ef55833-465c-48da-afc0-592a164fdd1d.pdf;
(iii) Regulations 51, 54 and 54A of the European Communities (Birds and Natural
Habitats) Regulations 2011 to 2021 (unofficial consolidation):
https://www.npws.ie/sites/default/files/files/European%20Communities%20(Birds
%20and%20Natural%20Habitats)%20Regulations%202011%20to%202021%20-
%20Unofficial%20Consolidation%20(Updated%20to%2028%20July%202022)(1).
pdf; and
(iv) Quinn and anor. v. An Bord Pleanála [2022] IEHC 699, [2022] 12 JIC 1608 (and the
case law cited):
https://courts.ie/view/judgments/9778a840-567e-4b45-a9dd-
fb409957df81/415dff81-b1e2-4dc6-a80a-75cc04f15e04/2022_IEHC_699.pdf/pdf.
Facts
16. In anticipation of the development consent application, an application for a bat derogation
licence was made to the National Parks and Wildlife Service (NPWS) on 17th January, 2020. The
licence was issued on 4th March, 2020.
17. On 16th July, 2020, a request was made to amend the licence to include the brown long-
eared bat. That was granted and an amended licence issued on 21st July, 2020.
18. The licence states:
“This licence is granted solely to allow the activities specified in connection with the proposed
strategic housing development located at Delgany, Co. Wicklow, for Drumkilla Ltd.”
19. Condition 4 states:
“The mitigation measures outlined in the application report (Environmental Impact
Assessment for a proposed strategic housing development on lands, Delgany, Co. Wicklow,
7. remedial or reductive measures, 7.11 Protection Measures for Bat Roosts -- Buildings,
7.12 Protective Measures for Bat Roosts -- Trees, 7.13 Protective Measures for Bat Foraging
and Commuting, pp 30-37), together with any changes or clarification agreed in
correspondence between NPWS and the agent or applicant, are to be carried out. Strict
adherence must be paid to all the proposed measures in the application.”
20. Two factual conclusions can be drawn by the referring court in relation to the derogation
licence:
(i) while the licence denies the existence of satisfactory alternatives to the grant of the
derogation, the materials disclose no consideration of alternatives with less impact
on strictly protected species, or of the alternative option of not granting the licence,
which gives rise to the inference that it is likely that there was no such consideration;
and
(ii) the licence states that it is issued in the interests of protection of the species
concerned. If and insofar as that requirement means that the derogation itself, as
opposed to mitigating conditions, is in the interests of such species, then that
conclusion is manifestly unreasonable and indeed absurd.
21. The critical dates are as follows:
(i) date of derogation licence – 4th March, 2020, amended on 21st July, 2020;
(ii) date applicants knew or could reasonably have been aware of the derogation licence
– 21st October, 2020 on the making of the application for permission;
(iii) date of permission – 15th February, 2021; and
(iv) date on which the proceedings challenging the derogation licence were brought –
25th March, 2021.
22. Pre-application consultation took place on 23rd July, 2020, which resulted in a board order
identifying issues to be addressed dated 12th August, 2020.
23. The application for planning permission under section 4 of the Planning and Development
(Housing) and Residential Tenancies Act 2016 was submitted on 21st October, 2020. The application
was accompanied by an EIA screening report. The revised derogation licence was appended to the
application documentation, so the application date was the first date on which the applicants could
have known about it.
24. The applicants made submissions on the application. The board’s inspector then prepared
a report recommending grant of permission with conditions dated 3rd February, 2021. The board
broadly accepted this recommendation.
25. The board completed a screening for environmental impact assessment and considered that
the Environmental Impact Screening Report submitted by the developer identified and described
adequately the direct, indirect, secondary and cumulative effects of the Proposed Development on
the environment. The board concluded that having regard to the matters listed in the board’s
decision that the proposed development, by reason of the nature, and location of the site the
proposed development would not be likely to have significant effects on the environment. The board
therefore decided that an environmental impact assessment report for the proposed development
was not necessary.
26. The board granted permission on 15th February, 2021.
27. Insofar as the applicant made an issue under Article 11(2) and (5) of Directive 2011/92 it
was common ground that:
(i) there is no specific statute specifying the time limit for a challenge to a derogation
decision specifically, above and beyond the rules on judicial review generally; and
(ii) likewise the State has not specifically publicised any particular procedure for the
information of the public as to how to challenge a derogation decision as opposed to
giving public information on judicial review generally.
Procedural history
28. Proceedings challenging the board’s decision and the derogation licence were issued on 25th
March, 2021. The applicants did not seek to extend time for the challenge.
29. The applicants did not challenge the derogation licence within 3 months of when they became
or ought to have become aware of it (and hence within a period that the court would have permitted
by way of a conforming interpretation of the power to extend time, had such an application been
made).
30. On 19th April, 2021, the referring court granted leave to seek judicial review and a stay on
the works. The referring court gave case management directions on 14th May, 2021. The matter
was heard on 9th to 11th May, 2023.
31. Following the CJEU judgment of 15 June 2023, Eco Advocacy, C-721/21,
ECLI:EU:C:2023:477, the matter was listed for any further submissions arising from that case.
32. On 5th July, 2023, the referring court dismissed the application to quash the planning
permission and adjourned for further submissions the challenge to the derogation licence. The stay
was continued for the time being.
33. An important point in this regard is that the applicants failed to mount a derogation-based
challenge to the planning permission. On the pleaded case, the challenge to the derogation licence
was not a ground to challenge the permission. Hence the challenge to the planning permission was
dismissed even though the derogation licence challenge remains outstanding.
34. On 1st November, 2023, the referring court identified relevant questions of EU law and
invited further submissions.
35. A hearing was then held on 24th October, 2023 which was followed by written submissions
by the parties.
36. A further hearing was held on 11th December, 2023 at which time judgment was reserved.
37. The referring court’s conclusion is that the application is out of time and should be dismissed,
subject to any rule of EU law that required a contrary result. The referring court was inclined to the
view that there was no such rule, but that the position was not completely beyond doubt and
therefore that it was appropriate to refer the issue to the CJEU.
38. In the circumstances the referring court has decided to stay the proceedings and to refer
the following questions to the Court of Justice for a preliminary ruling.
39. The board (the first named respondent) did not get involved in the issues regarding the
reference.
The first question – Scope of Namur-Est
40. The first question is:
Does Article 11 of Directive 2011/92 read in the light of the principle of wide access
to justice under Article 9(2) of the Aarhus Convention have the effect that, in a
case where a project within the meaning of Article 1(2)(a) of Directive 2011/92
the subject of an application for development consent (the “primary consent”)
cannot be carried out without the developer having first obtained another
permission (the “secondary consent”), and where the authority competent for
granting the primary consent for such a project retains the ability to assess the
project’s environmental impact more strictly than was done in the secondary
consent, such a secondary consent (if granted prior to the primary consent) is to
be treated as forming part of the development consent procedure for purposes
other than in relation to the scope of matters to be considered or assessed under
Directive 2011/92, either generally or where the secondary consent is a decision
adopted under Article 16(1) of Directive 92/43 and which authorises a developer
to derogate from the applicable species protection measures in order to carry out
the project?
41. The applicant’s proposed answer is that the Namur-Est judgment is not limited to the scope
of consideration and therefore is relevant for procedural matters such as limitation periods. It is
clear from the Namur-Est judgment, that in the particular circumstances which arose in Belgium and
which also apply in Ireland, the derogation decision must be considered as forming part of the
development consent procedure with the grant of development consent being the end point of the
decision making process. In particular the authority competent for granting development consent,
i.e. the board, retains the ability to assess the project’s environmental impact assessment more
strictly than was done in the derogation decision. The Court also ruled that it was not necessary to
provide public participation in respect of the derogation decision provided that such participation is
effectively ensured before the adoption of the decision on possible development consent. This is also
the case in Ireland. As already submitted by the applicants, the EIA screening decision is effectively
a threshold determination as to whether EIA is required for the project and therefore also as to
whether the findings of the Namur-Est case apply at all to the project. This supports the applicants’
view that under EU law the time limit to challenge the derogation licence must run from the date of
the EIA screening decision which screened the project out, since it is only at that point is it
determined whether the derogation decision must be considered as part of the development consent
procedure per Namur-Est or whether it comes within another regime. It would also be contrary to
Namur-Est for it to be interpreted as applying only to the scope of consideration and irrelevant to
other issues such as limitation periods. It would be perverse for Directive 2011/92 to be interpreted
in such a way that a member of the public concerned would have to challenge a derogation licence
before the public participation phase of the procedure had concluded, which would be the case if
national limitation periods were not affected by the Namur-Est ruling.
42. The State’s proposed answer is that in Namur-Est, the CJEU held (at §66) that the Directive
2011/92 must be interpreted as meaning that a decision adopted under Article 16(1) of Directive
92/43/EEC, which authorises a developer to derogate from the applicable species protection
measures in order to carry out a project within the meaning of Article 1(2)(a) of Directive 2011/92,
forms part of the development consent procedure within the meaning of Article 1(2)(c) of Directive
2011/92, where, first, the project cannot be carried out without the developer having first obtained
that derogation decision and, secondly, the authority competent for granting development consent
for such a project retains the ability to assess the project’s environmental impact more strictly than
was done in that derogation decision. Thus, a decision to grant a Derogation Licence under Article
16 of Directive 92/43 forms part of the development consent procedure within the meaning of Article
1(2)(c) of Directive 2011/92. In that context, the Derogation Licence is a discrete decision taken in
a development consent process and is “challengeable” as a discrete decision taken in that process.
However, the Derogation Licence is not to be treated as forming part of the development consent
procedure for purposes other than in relation to the scope of matters to be considered or assessed
under Directive 2011/92. It is further submitted that the decision in Namur-Est is limited to the
scope of consideration and is irrelevant to the issue of the applicable limitation period.
43. The notice party’s proposed answer is to agree with the State’s proposed answer.
44. The referring court’s proposed answer is No. While the referring court appreciates that in
both the opinion of Advocate General Kokott in Namur-Est at para. 37, and the judgment of the
CJEU, para. 66, the derogation licence was to be treated as part of the development consent, this
was only in the context of the scope of matters to be considered or assessed as part of environment
impact assessment. Namur-Est does not establish that a derogation licence or other multi-consent
decision must be treated as a single decision for any other purpose, such as time limits for example.
To treat such secondary consents as part of the primary consent for such other purpose would create
procedural chaos and would be contrary to the principle of legal certainty. There is nothing perverse
about requiring an applicant to challenge a derogation licence while public participation may be
ongoing in the related development consent. Nor does this undermine public participation or access
to justice in any other way. It simply requires members of the public concerned to bring any
challenge to the derogation decision separately by way of an action within the time fixed by domestic
law. Otherwise, challenges to a multi-stage consent process would become unmanageable and
chaotic if all were to be potentially postponable until the final consent.
45. The relevance of the question is that if an earlier derogation decision is treated as part of
the development consent only for the purposes of matters to be considered, and not for the purposes
of any extension of limitation periods for challenge, then the present action is out of time under
domestic law, and a conclusion to that effect does not contravene EU law, subject to the next
question.
The second question – limitation periods generally
46. The second question is:
If the answer to the first question is Yes, does Article 11 of Directive 2011/92 read
in the light of the principle of wide access to justice under Article 9(2) of the Aarhus
Convention have the effect that national domestic rules as to the date on which
time commences to run to challenge the validity of a decision adopted under Article
16(1) of Directive 92/43 (the “secondary consent”) must be interpreted so as to
preclude that time from commencing to run prior to the date of adoption of the
development consent concerned (the “primary consent”), either generally or in a
case where: (i) the project was subject to the case-by-case examination envisaged
by Article 4(2)(a) of Directive 2011/92, and/or (ii) the determination under Article
4(5) for the purposes of the primary consent was made after the secondary
consent had been granted and simultaneously with the decision on the primary
consent, and/or (iii) the proceedings challenging the validity of the secondary
consent do not contain any ground challenging the relevant primary consent by
reference to the asserted invalidity of the secondary consent, and/or (iv) the
applicant fails to apply for an extension of time to bring the challenge to the
secondary consent, which application is required by domestic law for a late
challenge in the absence of any EU law rule to the contrary?
47. The applicant’s proposed answer is that insofar as relates to a derogation licence, this does
not arise in light of the Namur-Est judgment and the national law principle that interim decisions
should be challenged following the final decision in a procedure. The applicants argue, by analogy,
that the derogation licence decision is a preliminary decision for the purpose of the EIA screening
determination in the same way as it was held to be a preliminary decision within the EIA procedure,
and therefore only becomes final once the procedures under Directive 2011/92 come to an end,
either with a negative EIA screening determination or the EIA determination if the project is screened
in by the competent authority. In addition, since the rationale of Namur-Est is derived from the
procedural rights given to the public concerned under Directive 2011/92 for projects requiring EIA,
it would be contrary to that directive for national law to require the applicants to challenge the
derogation licence even before those rights were established which only occurs with the EIA
screening determination under Article 4(5) of Directive 2011/92. The EIA screening determination
essentially determines whether the procedural rules under EU law apply, as set out in Namur-Est,
or whether national procedural rules apply, which would be case if a negative screening
determination was made under Article 4(5)(b) of Directive 2011/92. If the project is screened in
then Namur-Est applies which means that the applicants are entitled to wait at least until the
screening determination is made before their rights in relation to the derogation licence crystalise.
If the project were to be screened in they would then be entitled to wait until the conclusion of the
environmental assessment by the competent authority and to consider a possible challenge in light
of that assessment as explained by the AG in Namur-Est . It would therefore be contrary to Directive
2011/92 for the time limit to challenge the Derogation Licence to start to run before the EIA
screening determination was published.
48. The State’s proposed answer is that, in the light of the judgment of 6 July 2023, Hellfire
Massy Residents Association, C-166/22, ECLI:EU:C:2023:545, the question of when time runs where
a point of EU law is at issue is acte clair or acte éclairé against the applicants. First, the time period
within which to challenge the derogation licence was three months from the grant of the derogation
licence or, alternatively, applying a conforming interpretation, from the date when the applicants
actually, or should have, found out about the derogation licence. Secondly, Directive 2011/92,
when read in light of the access to justice principles in Articles 9(2) of the Aarhus Convention, does
not require that domestic time limits should be construed differently in this case. Third, the CJEU
very recently concluded in Hellfire Massy Residents Association, C-166/22 that Directive 2011/92
did not lay down any obligation for the derogation procedure under Article 16 to be integrated into
the procedures for granting development consent to projects. Fourth, in the particular circumstances
of this case, where the Court has already held that the applicants did not contend on the pleadings
that the permission was invalid because the derogation licence was invalid, there is no basis for an
interpretation of sub-rules 21(1) and/or (2) that a challenge to the derogation licence may be
brought at the end of the development consent/planning application procedure. Fifth, the applicants
could have challenged the decision of the relevant competent authority – An Bord Pleanála – to grant
development consent, on the basis that it did not assess the project’s impact on protected species
more strictly than was done at the derogation licence stage. However, the applicants simply did not
advance that proposition. It is a matter of the utmost significance that, in considering the inter-
relationship between a derogation licence and a grant of planning permission, the CJEU has very
recently held that neither Directive 92/43 nor Directive 2011/92 lay down any obligation for the
derogation procedure under Article 16 to be integrated into the procedures for granting development
consent to projects. The State Respondents submit that if there is no obligation for the derogation
licence procedure to be integrated into the procedures for granting planning permission, there can
be no concomitant obligation for a conforming interpretation to be applied to sub-rule 21(2) insofar
as it applies to administrative proceedings, so as to conclude that the date of the proceedings would
have to be interpreted as the date of the final decision under the planning code. It would be entirely
contrary to the principle of legal certainty if the time limit that applies to the grant of the derogation
licence was, somehow, to be “suspended” until the grant of the development consent. If the court
was to hold with this principle, it would potentially also apply to other statutory consents such as
foreshore licences granted under the Foreshore Act 1933 (which is domestic law) or industrial
emission licences (granted under Regulations and the Environmental Protection Agency Act 1992
giving effect to the Industrial Emissions Directive).
49. The notice party’s proposed answer is No.
50. The referring court’s proposed answer is that this does not arise because the answer to the
first question is No, but if it does arise the answer is No. The Namur-Est decision should not be
extended to have the effect of cutting across domestic limitation periods which are a matter within
the scope of national procedural autonomy, subject to the principles of equivalence and
effectiveness: Judgment of 17 November 2016, Stadt Wiener Neustadt v Niederösterreichische
Landesregierung, C-348/15, ECLI:EU:C:2016:882 at paras. 40 and 41, judgment of 20 December
2017, Caterpillar Financial Services, C-500/16, EU:C:2017:996, paragraph 42) (Flausch and Others,
C-280/18, EU:C:2019:928, paragraphs 46-49, 51, and 54-60. To so extend Namur-Est would be
contrary to the principle of legal certainty. No such extension is necessary because where a project
requires multiple consents, each consent can be challenged as it is made, within the relevant
limitation period in domestic law which may vary from decision to decision subject to the principles
of equivalence and effectiveness. As regards the specific sub-elements referred to in the question:
(i) the fact that the project was subject to the case-by-case examination envisaged by
Article 4(2)(a) of Directive 2011/92 is immaterial;
(ii) the fact that the determination under Article 4(5) for the purposes of the primary
consent was made after the secondary consent had been granted and simultaneously
with the decision on the primary consent is also immaterial;
(iii) if EU law does not generally require the postponement of a time limit to challenge a
secondary consent until the primary consent is given, this must apply a fortiori if the
proceedings challenging the validity of the secondary consent do not contain any
ground challenging the relevant primary consent by reference to the asserted
invalidity of the secondary consent; thus while the answer should be No in any event,
this is doubly so where the challenge brought to an earlier consent in a multi-stage
consent process is not linked in the pleadings to the validity of any consent issued at
a later stage; and
(iv) where the applicant fails to apply for an extension of time to bring the challenge to
the secondary consent, which application is required by domestic law for a late
challenge, this has the effect that a necessary precondition for a conforming
interpretation does not apply on the facts. An applicant’s failure to even apply for an
extension of time as mandated by national rules is a disregard of domestic law which
goes beyond any EU law entitlement. If an extension of time that is necessitated by
domestic law is actually applied for, any EU law entitlements can be read in by way
of a conforming interpretation. But if an applicant fails to even seek the necessary
extension of time, contrary to domestic law, the need for a conforming interpretation
does not arise.
51. The relevance of the question is that if the answer to either the first question or this question
is No then the action must be dismissed as out of time.
The third question – limitation periods in the absence of express provision
52. The third question is:
If the answer to the first question is Yes and if the answer to the second question
in general is No, does Directive 2011/92 read in the light of article 47 of the Charter
of Fundamental Rights and/or the principle of wide access to justice under Article
9(2) of the Aarhus Convention have the effect that a time limit provided by the
domestic law of a member state for the bringing of proceedings to assert a right
under that Directive, must be reasonably foreseeable, but does not have to be
expressly specified in legislation in accordance with Article 11(2) of Directive
2011/92 and/or in practical information made available to the public on access to
administrative and judicial review procedures pursuant to Article 11(5) of
Directive 2011/92 and/or definitively determined with certainty by domestic
caselaw, so that the answer to the second question is unaffected by provision being
made in the domestic law of a member state for a foreseeable time limit of a
general nature which applies to public law actions generally including for the
bringing of proceedings challenging a decision adopted under Article 16(1) of
Directive 92/43 and which authorises a developer to derogate from the applicable
species protection measures in order to carry out the project, albeit that this is
implicit rather than explicit in the domestic law concerned?
53. The applicant’s proposed answer is as per the second question. In the judgment of 28
January 2010, Commission v Ireland, C-456/08, ECLI:EU:C:2010:46, the Court of Justice held that
the sixth subparagraph of Article 10a of the previous Directive 85/337 (which is identical to Article
11(5) of the current directive) is an obligation to obtain a precise result which the Member State
must ensure is achieved. The Court of Justice held that: “In the absence of any specific statutory or
regulatory provision concerning information on the rights thus offered to the public, the mere
availability, through publications or on the internet, of rules concerning access to administrative and
judicial review procedures and the possibility of access to court decisions cannot be regarded as
ensuring, in a sufficiently clear and precise manner, that the public concerned is in a position to be
aware of its rights on access to justice in environmental matters.” Thus, it is not sufficient for the
State to state baldly that the general rules, including common law rules, provide that time runs from
the date when the public becomes aware of a preliminary decision. The State is required to determine
specifically at what stage a challenge may be brought and to provide practical information on access
to procedures to bring those challenges, including precisely specifying when the time period within
which a challenge must be brought.
54. The State’s proposed answer is that Directive 2011/92 read in the light of the principle of
wide access to justice under Article 9(2) of the Aarhus Convention does not have the effect specified
in the second question where the law of the member state concerned has not definitively determined,
in accordance with Article 11(2) of Directive 2011/92, at what stage the decisions, acts or omissions
may be challenged, and where the position is not determined with certainty by domestic caselaw.
55. The notice party’s proposed answer is that this does not arise on the facts of this case. Order
84 RSC provides for when time begins to run in respect of a challenge by way of judicial review. The
three-month time limit runs from the date of the decision as set out above.
56. The referring court’s proposed answer is that this does not arise because the answer to the
first question is No. But if it does arise, the answer is Yes. The objectives of access to justice are
met by the existence of a foreseeable time limit. There is no basis to go beyond that and to require
that the time limit for any particular type of proceedings should be determined beyond doubt by
express provision in legislation or express findings in definitive caselaw. Such an obligation would
be impracticable given the vast number of possible legal actions that could be brought across the
field of EU law, each of which would in principle be subject to the requirement for the existence of
an effective remedy. Creating an express list of such actions and keeping it up to date would be
impracticable and indeed virtually impossible. Hence a general, foreseeable, time limit must suffice.
Here, the general time limit in O. 84 RSC applies and that creates sufficient foreseeability for
applicants generally.
57. The relevance of the question is that if the answer to the first question is yes but the answer
to the second question remains negative despite the existence of a general time limit then the action
must be dismissed as out of time.
The fourth question – merits – alternatives to derogation
58. The fourth question is:
If the answer to the first question is Yes and either the answer to the second
question is Yes or the answer to the third question is No, does Article 16(1) of
Directive 92/43 have the effect that a competent authority cannot conclude that
there is “no satisfactory alternative” to a decision which authorises a developer to
derogate from the applicable species protection measures in order to carry out a
project within the meaning of Article 1(2)(a) of Directive 2011/92 unless the
competent authority actually considers alternatives such as alternative location or
design, or refusal of the derogation?
59. The applicant’s proposed answer is that the competent authority must (a) consider
alternatives; and (b) explain how it has considered them. This is also clear from the judgment of 10
October 2019, Luonnonsuojeluyhdistys Tapiola, C-947/17, ECLI:EU:C:2019:851, which held that the
obligation to provide a statement of reasons is not met when the derogation contains no reference
to the absence of any other satisfactory alternatives or any reference to technical, legal and scientific
reports to that effect. Thus it follows that given the requirement to state reasons in relation to
satisfactory alternatives, there must be a requirement for the competent authority to actually
consider satisfactory alternatives such as alternative location or design, or refusal of the derogation,
and to document its reasoned conclusion in its decision. As identified by Richard Moules, Significant
EU Environmental Cases: 2019, Journal of Environmental Law, Volume 32, Issue 1, March 2020,
Pages 161–172, https://doi.org/10.1093/jel/eqaa002, at page 168: “This decision illustrates that
the Court is willing to put national authorities to proof to demonstrate the strict necessity of
derogations from the Habitats Directive. The requirement for objective scientific data and clear and
precise reasons ensures that derogations are only made as a matter of last resort, thereby
strengthening the aim of the Habitats Directive of ensuring biodiversity through the conservation of
natural habitats and wild fauna and flora.” In the present case none of these concerns was present.
There was no countervailing objective of protecting other wild flora or fauna or natural habitats, and
the need for a derogation could have been avoided entirely by either not carrying out the project or
alternatively through a modified project.
60. The State’s proposed answer is that the fourth and fifth questions are moot because the
proceedings are outside time. The Court has itself identified that the issues falling for consideration
relate to the interpretation and application of Order 84, rule 21 of the Rules of the Superior Courts
1986, as amended. If contrary to this the question arises, the fourth question should be answered
in the affirmative.
61. The notice party’s proposed answer is that the fourth and fifth questions are not required as
the challenge to the Derogation Licence is time-barred and no application for an extension of time
has been made.
62. The referring court’s proposed answer is that this does not arise because the answer to the
threshold first question is No. If it does arise the answer is Yes. The requirements of Directive
92/43 would be significantly undermined and the consideration of alternatives would be artificial and
unreal unless the actual alternatives, specifically alternative locations if that is an option, alternative
designs if that is an option, or refusal of the derogation, are actually given meaningful consideration.
63. The relevance of the question is that if the application is not out of time, and the question is
answered No, the derogation licence would be held invalid.
The fifth question – merits – protection by means of derogation
64. The fifth question is:
If the answer to the first question is Yes and either the answer to the second
question is Yes or the answer to the third question is No, does Article 16(1) of
Directive 92/43 have the effect that a competent authority cannot conclude that it
is “in the interest of protecting wild fauna and flora and conserving natural
habitats” to grant a decision which authorises a developer to derogate from the
applicable species protection measures in order to carry out a project within the
meaning of Article 1(2)(a) of Directive 2011/92 unless some identified protection
is created by the derogation itself rather than by mitigation measures adopted to
reduce or compensate for the detriment created by the steps authorised by the
derogation decision?
65. The applicant’s proposed answer is that Article 16(1)(a) of Directive 92/43 does not provide
an appropriate legal basis for the grant of the Derogation Licence since the activities sought to be
authorised, i.e. the construction of a private housing development, are not aimed at the protection
of wild fauna and flora or the conservation of natural habitats. In fact, the overall net result of the
derogation would be to harm wild fauna and their habitats, since there are no identified positive
benefits from the proposed development which would otherwise give rise to the protection of wild
flora and fauna or natural habitats. In the applicants’ view, the derogation under Article 16(1)(a)
involves a proportionate trade-off between strict protection of species on the one hand and the
protection of other wild flora and fauna and the conservation of habitats on the other. In other words,
in certain circumstances a derogation may be granted if the harm caused by activities prohibited
under Article 12 is the price worth paying for the protection of other species or the conservation of
other habitats. This provision is not concerned with facilitating development, particularly where (as
here) there is no evidence that the developer considered development alternatives that would have
allowed a modified development to proceed that also avoided entirely prohibited activities affecting
strictly protected species.
66. The State’s proposed answer is that this does not arise as per the fourth question, but if it
does arise, the fifth question should be answered in the affirmative.
67. The notice party’s proposed answer is as per the fourth question.
68. The referring court’s proposed answer is that this does not arise because the answer to the
threshold first question is No. If it does arise the answer is Yes. The language and intention of
Article 16(1) of Directive 92/43 supports the intention that the reference to the interest of protecting
wild fauna and flora and conserving natural habitats must be promoted by the decision itself.
Granting the decision for other reasons and then mitigating that decision with protection measures
would not comply with that provision.
69. The relevance of the question is that if the application is not out of time, and the question is
answered No, the derogation licence would be invalid.
Order
70. For the foregoing reasons, it is ordered that:
(i) the questions set out in this judgment be referred to the CJEU pursuant to article 267
TFEU;
(ii) the substantive determination of the proceedings be adjourned pending the judgment
of the CJEU, without prejudice to the determination of any appropriate procedural or
interlocutory issues in the meantime including the stay on the primary consent, leave
to appeal in relation to the primary consent, and costs of the challenge to that
consent;
(iii) the parties be required to comply with the directions regarding preparation of papers
for transmission to the CJEU as set out in Guidance Notes attached to Practice
Direction HC124, so that all papers are received by the List Registrar in PDF format
by 13:00 on Friday 19th January, 2024;
(iv) the parties be required to comply with the directions to keep the referring court
informed of progress of the reference as set out in para. 100(vii) of Eco Advocacy
CLG v. An Bord Pleanála [2021] IEHC 265;
(v) the matter be listed for mention on Monday 22nd January, 2024 to enable directions
to be given regarding any appropriate procedural or interlocutory issues;
(vi) the costs of the proceedings related to the challenge to the derogation licence and in
connection with the reference be reserved pending the outcome of the reference; and
(vii) all other costs to date not already disposed of be adjourned to a date to be fixed
following the mention date already referred to.