Judicial review dismissed for being out of time; applicants failed to challenge planning decision promptly despite later discovering new information.
Legislator summary
AI generatedThe High Court refused leave to seek judicial review against An Bord Pleanála, granting permission for a telecommunications mast. Applicants argued they should have challenged the decision sooner but delayed until discovering a licence agreement, claiming uncertainty about the law at the time. The court held that the 8-week limitation period had expired and no good reason existed to extend it, as the applicants' delay was not justified by the uncertainty they cited.
Legislator headnote
AI generatedSections 50, 50A and 50B of the Planning and Development Act 2000; Judicial review proceedings must be commenced within 8 weeks of the applicant's knowledge of the grounds for review, and extensions are only granted where good and sufficient reasons exist, which were absent here due to the applicants' own delay in pursuing their concerns.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
[2023] IEHC 432
THE HIGH COURT
JUDICIAL REVIEW
[2023 No. 212 JR]
IN THE MATTER OF SECTION 50, 50A AND 50B OF THE PLANNING AND DEVELOPMENT
ACT 2000
BETWEEN
TIMOTHY FRAWLEY AND ANNABEL MEEHAN FRAWLEY
APPLICANTS
AND
AN BORD PLEANÁLA
RESPONDENT
AND
EIRCOM LIMITED AND TOWERCOM LIMITED
NOTICE PARTIES
JUDGMENT of Humphreys J. delivered on the 24th day of July, 2023
1. This matter raises similar issues to those in Thomson & Thomson v. An Bord Pleanála [2023]
IEHC 431 and much of the legal discussion there should be read as being also relevant here.
Facts
2. On 25th May, 2021, the developer applied to Wicklow County Council for permission to erect
a telecommunications mast and associated works at Eir Exchange, Ballymanus Lower, Glenealy,
County Wicklow. The applicants made a submission objecting to that. The council’s assistant
planner reported on 13th July, 2021, noting various negative impacts including a profound negative
visual impact on the residential area and on St Joseph’s Church, Glenealy, and recommended refusal
on visual amenity grounds. The council refused permission on 14th July, 2021.
3. The developer appealed on 10th August, 2021. The applicants made a submission on 1st
September, 2021 objecting to the development. The board’s inspector recommended refusal of
permission. The board disagreed and granted permission on 8th February, 2022.
4. The applicants say that they “considered challenging the validity of the board decision, but
ultimately decided not to, predominantly in light of the costs risk which could materialise”. They say
they:
“... decided not to bring judicial review proceedings when the Decision was adopted, because
they were concerned about the risk of an adverse costs order in circumstances where the
law was, at that time, uncertain. However, they began to track other mast decisions made
by the Board. They looked back at mast decisions it had made in the recent past. They
noted that the Board was overturning its inspectors’ recommendations in what seemed to
them to be a disproportionate number of cases. They made a spreadsheet recording the
decisions taken.”
5. Ms Frawley avers at para. 28 of her affidavit:
“We saw the reports in the Examiner newspaper on 18 May 2022 by Mick Clifford, ‘Do ABP
revelations mean Government must plan for wider inquiry?’. We contacted the Examiner on
20 May 2022 stating that we wished to raise concerns regarding the then Deputy Chairperson
Mr Hyde in relation to Mast decisions. Cianan Brennan, a journalist with the Examiner
responded to us. Further to this we sent the aforementioned spreadsheet to Cianan
Brennan, on 24 May 2022.”
6. The applicants plead as follows:
“36. On 25 May 2022 the Applicants asked the Board to investigate telecommunications
appeal decisions, and sent a dossier of information. They got no substantive reply until 4
July 2022, when the Board stated it would investigate the Applicants’ case but could not
reopen it. However, the Applicants considered that the response indicated that the role of
the Planning Regulator and the Minister would not be so restricted ...
37. The Applicants gave certain information to national newspapers, and liaised with the
Minister, Mr Darragh O’Brien, whose office advised the applicants that [Remy] Farrell SC
would look at all matters. They believed the Government would ensure reopening of any
cases where any adverse findings were made.”
7. Ms Frawley avers:
“32. Because of the difficulties we had had getting a substantive reply from Ms Hill [of
the board], we had by this time taken our concerns to RTE who were preparing a Prime Time
Investigates programme on the emerging issues in An Bord Pleanála. We remained in
further contact with the Examiner newspaper, who were continuing to show an interest in
the issue of telecommunication mast decision making. They shared our research with Peter
Thomson, a planning consultant who was also in contact with the newspaper. This would
have been after the initial reports of concerns about Mr Hyde’s involvement in decisions
relating to matters where his business associates or extended family had an interest.
33. We liaised with the Minister, Mr Darragh O’Brien. The Minister’s office told us that
Remy Farrell SC would look at all matters. We continued to have confidence that once Mr
Farrell had reported, that the Government would address issues such as the grant of
permission by Paul Hyde and Michelle Fagan for the mast in Glenealy.
34. On 7 June 2022 my husband Timothy spoke to the chair of the Oireachtas Housing
Committee, Mr Steven Matthews, who is also a local TD in Wicklow. He said the Committee
would look at the issue; but we do not believe it ever did.”
8. The applicants plead:
“38. The Applicants spoke to the chair of the Oireachtas Housing Committee, Mr Steven
Matthews who said the Committee would look at the issue; but they do not believe it ever
did. They made contact with the Office of the Planning Regulator, which emailed them the
terms of reference of the inquiry the Regulator had begun. They understood from it that all
avenues would be looked at and that it would investigate the allegations made. ... They
also contacted the Office of the Ombudsman. They were assigned a reference number for
their complaint, but the Office of the Ombudsman never reverted to them in relation to that
complaint.”
9. Importantly, the applicants also plead:
“40. In an interview on 16 August 2022 with the broadcaster, Pat Kenny, the Minister for
Housing, Local Government and Heritage, Darragh O’Brien, discussed the allegations of
impropriety in the handling of the Board’s files, and, when asked to clarify the position
relating to the position of people such as the Applicants for whom time to challenge decisions
had expired, Minister O’Brien would not be drawn as to what specifically the Government
would do but did state ‘I think in relation to decisions that have been made, that would be
a matter for people to assess when the report has been published itself. But we have a bit
more work to do on this.’ The Applicants understood from that interview, that the question
of reopening existing decisions was not closed as far as the government was concerned.”
10. Ms Frawley’s affidavit states:
“37. On 16 August 2022, I … recall listening [sic] the Pat Kenny show where he
interviewed the Minister for Housing, Local Government and Heritage, Darragh O’Brien in
relation to the government response to the An Bord Pleanala Report (full interview available
on https://link.goloudplayer.com/s/pGMzGmnnCygX). During this interview Pat Kenny
asked ‘those permissions that have been given against the run of play if you like by the
Board and then if they are found to be tainted in the Remy Farrell investigation or in any
criminal prosecution that might follow, what of those permissions that have damaged
communities, damaged local amenities are they to stay standing?’, Minister O’Brien replied
initially in relation to Strategic Housing Developments and then added ‘I think in relation to
decisions that have been made, that would be a matter for people to assess when the report
has been published itself. But we have a bit more work to do on this’.
38. Mr Kenny followed up seeking further clarity on the legal position where developers
are ‘about to start a development that is tainted, if that is to happen, what then?’
39. Minister O’Brien responded ‘I am not saying at this stage, obviously I am somewhat
restricted in what I can say in regard to the report at this time but that is why I want to
ensure as best as possible that we can publish the report. I have written to the joint
Oireachtas committee the chairperson Steven Matthews and all the opposition spokes people
on housing as well to inform them of the process and what we have done so far. I think
that is another step forward Pat, it is something that I can’t comment on right now to be
fair, I would say to the OPR review assisted by Conleth Bradley senior counsel as well would
[be] a very important one too. The structure within the Board and how the Board operates
and the decision making is something that is being looked at and I will be bringing measures
to government in September. The other thing that I did discuss with you before is the full
review of planning itself which is work that is underway between myself and the Attorney
General which we expect to consolidate a planning bill later this year in the autumn which
will be the most significant updating of our planning legislation. So, there is a lot of moving
parts in this.’.
40. The Minister’s public statements as outlined above informed our thinking. We
understood that the question of reopening existing decisions was not closed. Timothy was
interviewed by a radio station, East Coast FM during the summer of 2022, and he confirmed
to them, our understanding that the question of past decisions was not closed.”
11. The applicants outline the various major pieces of fall-out from the turmoil in the board, as
largely set out in Thomson & Thomson v. An Bord Pleanála, and go on to plead:
“43. The Applicants awaited the results of the Board’s internal investigation and report,
but then they learned that the Board had decided not to publish it. They did not know what
it contained. Even though they had made the allegations, or some of the allegations, that
caused the report to be prepared, they were not notified of its outcome.
44. In January 2023 the Applicants learned of another set of proceedings relating to
Board approval of telecommunications masts, Peter Thomson and Doreen Thomson v Bord
Pleanala, 2022 No. 1039 JR, and learned for the first time that an extension of time to seek
relief might be possible. On 2 February 2023, the news website ‘ontheditch.com’ published
a copy of the Board’s internal investigation report. The Board’s report revealed, in somewhat
oblique language, that the Board agreed that the former deputy chairperson and Ms Fagan
had decided cases in a manner that was not in accordance with Board procedures, in
particular in relation to allocation of files, and that there was no record of any decision to
depart from those procedures.”
12. The applicants instructed their solicitors to draft the present proceedings on 17th January,
2023.
Procedural history
13. Proceedings were filed on 7th March, 2023. The matter was first mentioned to the court on
8th March, 2023, and on 27th March, 2023 I admitted the case to the List. On 24th April, 2023, I
directed that leave be sought on notice and joined Towercom Ltd as a notice party. In addition to
seeking leave on notice, the applicants also sought to amend their pleadings by motion dated 20th
June, 2023. Those applications were heard on 5th July, 2023, when judgment was reserved.
Relief sought
14. The relief for which leave is sought, as that relief is proposed to be amended, is:
“1. An Order of Certiorari pursuant to Order 84 of the Rules of the Superior Courts 1986
as amended and Section 50 of the Planning and Development Act 2000 as amended quashing
the decision of the Respondent, An Bord Pleanála (the Board), dated 8 February 2022, file
reference ABP-311081-21, to grant permission for erection of a 18m high mobile phone mast
at Glenealy, County Wicklow, therein described as:
Proposed Development: The construction of an 18 metre monopole support structure
(overall height of 19.5 metres) carrying telecommunications antennas, dishes and
associated equipment, together with new ground level equipment cabinets,
landscaping and all associated site works at Eir Exchange, Ballymanus Lower,
Glenealy, County Wicklow.
2. Such declaration(s) of the legal rights and/or legal position of the applicants and (if
and insofar as legally permissible and appropriate) persons similarly situated and/or of the
legal duties and/or legal position of the Respondent as the court considers appropriate.
3. Directions of the type outlined at paragraph 81 of the decision in Reid v Bord
Pleanala, [2021] IEHC 362 requiring the Board to investigate and determine, and file one or
more affidavits giving a detailed account of:
3.1. How it managed the allocation of the file relating to its decision dated 8
February 2022, on file reference ABP-311081-21.
3.2. How it managed the allocation of files relating to telecommunications masts
and antennae generally between 1 January 2021 and 8 July 2022, and in particular
how it came about that two Board members, Paul Hyde and Michelle Fagan, were
allocated to such a large proportion of such files between those dates.
3.3. The circumstances leading to the resignation of Paul Hyde.
4. Such further declarations, injunctions and directions as may be appropriate for the
purposes of giving full effect to the above relief, or of any finding relating to any matter
emerging in the course of such investigation, determination and filing.
5. An extension of time to apply for leave to seek judicial review of the decision of the
Board, pursuant to Section 50(8) of the Planning and Development Act 2000 as amended.
6. A Declaratory Order confirming that Section 50B of the Planning and Development
Act 2000 as amended and / or Sections 3 and 4 of the Environment (Miscellaneous
Provisions) Act 2011 as amended apply to the Applicants herein in respect of the Grounds
set out at Part E hereof.
7. A stay pending determination of the present proceedings on the erection by the
Respondent of the mobile phone mast and / or telecommunications antennae purportedly
authorised by the Decision dated 8 February 2022, file reference ABP-311081-21, to grant
permission for erection of a 18m high mobile phone mast at Ballymanus Lower, Glenealy,
County Wicklow.
8. Further or other relief.
9. Costs.
10. Discovery for the purposes of grounding the reliefs set out above, including third
party discovery against:
1) Paul Hyde, c/o An Bord Pleanala, 64 Marlborough Street, Dublin 1
2) Sharon Hickey and Sean Hickey
3) Promontoria Ltd, c/o Mason Hayes and Curran, Solicitors, South Bank House,
Barrow Street, Dublin 4
Additional Reliefs
13, An extension of time, pursuant to S50(8) of the 2000 Act, to allow the Applicant to bring
the additional claim at Core Ground 8.
14, An Order pursuant to Order 31 Rule 12 of the Rules of the Superior Courts for discovery
of the commercial agreement or agreements between Eircom Ltd, trading as Eir, and
Towercom Ltd, pursuant to which Towercom Ltd became entitled to apply for permission to
carry out the Proposed Development and / or entitled to carry out the Proposed
Development.”
Grounds of challenge
15. The core grounds as proposed to be amended are as follows:
“1, The Board Decision is invalid because the Board was affected by bias.
2, The Board Decision is invalid because the Board members involved in taking the decision
failed to comply with the provisions of the Board’s Code of Conduct, contrary to S150(1) of
the 2000 Act.
3, The Board Decision is invalid because Paul Hyde entered into a composition or
arrangement with creditors as a result of which he was deemed pursuant to S106(13)(d) to
have ceased to be a member.
4, The Board Decision is invalid because the Board erred in law in its interpretation of
paragraph 9.4.2 of the 2016 Development Plan, and / or failed to have any or any adequate
regard to the Ministerial Guidelines in breach of Section 28 of the 2000 Act, and / or failed
to give any or any adequate reasons for its departure from Ministerial Guidelines and the
requirements of the 2014 Development Plan in breach of Section 34(10) of the 2000 Act.
5, There is good and sufficient reason to extend time for bringing of the application for leave
to apply for judicial review, and the circumstances of same were outside the control of the
Applicants, in accordance with Section 50(8) of the 2000 Act.
6, The Applicants are entitled to the protection against adverse costs conferred by Section
50B of the 2000 Act and / or Sections 3 and 4 of the Environment (Miscellaneous Provisions)
Act 2011.
7, The Court should stay the erection of the Development pending the determination of the
within proceedings.
8, The Board Decision is invalid because the Application for Permission is invalid because it
failed to state the name of the applicant for permission, contrary to R18(1)(a) and / or
R19(1) of the 2001 Regulations.”
16. In the course of the hearing, in response to the replying submissions of the board and after
the conclusion of those submissions, the applicant sought to re-word the additional core ground 8
as follows:
“8, The Board lacked jurisdiction to grant permission because the application form,
newspaper notice and site notice were invalid as they failed to correctly state the identity of
the applicant for permission and accordingly the application was invalid.”
The law in relation to grant of leave and extension of time
17. The requirements regarding extension of time are broadly as set out in Thomson & Thomson
v. An Bord Pleanála.
18. The law in relation to amendment only arises if we get over the hurdle of extension of time.
19. The requirements for grant of leave in planning cases are set out in Duffy v. Clare County
Council [2023] IEHC 430.
Should leave and an amendment be granted here?
20. Apart from the ministerial comments which the applicants relied on, the applicants here have
the same difficulties as those in Thomson & Thomson v. An Bord Pleanála and are not otherwise
entitled to an extension of time. In essence the reliance interests enjoyed by the developer in a
commercial context outweigh such features of the application as might favour the applicants.
21. As regards the ministerial comments, those might indeed have been a legitimate basis for
an extension of time if time was still running on the date of the interview but a potential applicant
was induced or misdirected into holding off on proceedings on the basis of those statements. But
the problem for the applicants is that they seemingly knew of Mr Hyde’s alleged financial troubles,
and hence of the alleged vacation of his office, from a piece in The Ditch in April, 2022. They also
knew, to at least some extent, of the anomalies in mast decision-making around that date. So the
8-week period to bring proceedings had already expired as of the date of the ministerial comments.
Those comments don’t therefore save the applicants here, even on a holistic overview of all
circumstances (Heaney v. An Bord Pleanála [2022] IECA 123, [2022] 5 JIC 3123 (Unreported, Court
of Appeal, Donnelly J., 31st May, 2022)). Third party rights, specifically the commercial interests of
Towercom, are critical here.
22. Considering the grounds in the light of the above, the situation is as follows:
(i) An extension of time to pursue core grounds 1 to 3 will be refused and thus leave is
refused;
(ii) Core ground 4 is a piggy-back ground that was there all along so an extension of
time and leave for that should be refused, at least if there are no other grounds
where an extension of time is warranted;
(iii) Core ground 5 (extension of time) is being disposed of by order now so there is no
basis for leave because the extension is being refused;
(iv) Core grounds 6 and 7 are procedural so will follow the other grounds by being
refused; and
(v) As regards core ground 8 (as sought to be added by amendment), while I appreciate
that the applicants didn’t know there was a licence agreement, that is basically an
indoor management point that doesn’t impact on them. The claim that the identity
of the applicant for permission could have made a difference because of possible
past breaches of planning law is totally hypothetical and speculative and there is no
evidence making that even a potential issue here. The Planning and Development
Regulations 2001 art. 18(1)(a) and corresponding requirements provide that the
applicant’s name should be stated. The judicial review applicants here complains
that the “applicant” for permission is not the “developer” – but so what. The
permission enures for the benefit of the land. The fact that the capacity of the
developer was somewhat ambiguous or even shifting (i.e., whether Towercom were
acting merely as an agent or in some way as a principal developer) doesn’t make
the application invalid without something more substantive that would mean that
that has some real legal relevance. There are no substantial grounds for the point
being made in the amendment, so it is refused on that basis.
23. Like the applicants in Thomson & Thomson v. An Bord Pleanála, one can reasonably say that
the applicants here have contributed to public debate by bringing their concerns and findings to
public attention via the media. But not having brought those complaints to the court at the
appropriate time, namely within 8 weeks from their coming into possession of the relevant
information in or around April, 2022, they are out of time to do so now. There is not good and
sufficient reason to extent that time.
Order
24. For the foregoing reasons, it is ordered that:
(i) the amendment sought be refused;
(ii) the application for an extension of time be refused;
(iii) leave to seek judicial review be refused; and
(iv) unless the parties apply otherwise by written legal submission within 7 days, the
foregoing order be perfected forthwith thereafter on the basis of no order as to costs.