Legislator Case Law & Legislation
IEHC 431 ECLI:IE:HC:2023:431 AI generated

High Court dismisses judicial review application due to failure to meet statutory time limits for planning appeals.

Case Number IEHC 431
Court / Authority
Jurisdiction Ireland (IE)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The High Court refused an extension of time for a judicial review application challenging a planning permission refusal. The applicants had known of the council's decision and potential legal grounds for appeal months prior but delayed until after public media exposure. The court held that the statutory criteria for extending time limits were not met and that the applicants' commercial interests outweighed their procedural delays.

Legislator headnote

AI generated

Section 50(3) of the Planning and Development Act 2000; Section 50A(2) of the Planning and Development Act 2000: The court must strictly adhere to statutory time limits for planning appeals and will not extend them unless specific criteria are met, balancing structural asymmetries in planning law against the need for commercial certainty.

Keywords

AI generated
Planning and Development Act 2000 Judicial Review Time Limits Extension of Time Criteria Commercial Interests Statutory Deadlines

Cited Legislation

AI generated

Cited Case Law

AI generated
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[2023] IEHC 431

THE HIGH COURT

JUDICIAL REVIEW

IN THE MATTER OF SECTION 50, 50A AND 50B OF THE PLANNING AND DEVELOPMENT

ACT 2000

[2022 No. 1039 JR]

BETWEEN

PETER THOMSON AND DOREEN THOMSON

APPLICANTS

AND

AN BORD PLEANÁLA

RESPONDENT

AND

EIRCOM LIMITED

NOTICE PARTY

JUDGMENT of Humphreys J. delivered on the 24th day of July, 2023

Facts prior to the impugned decision

1. On 25th June, 2020, the developer applied to Kilkenny County Council for permission to

erect a telecommunications mast. The council validated the application on 1st July, 2020. The

applicants made a submission to the council objecting to the development.

2. The council’s senior executive planner prepared a report. That report concluded that due to

the location of the proposed development within the village of Kells, close to existing dwellings and

amenities, and having regard to its height and bulk, it would be visually obtrusive, and she felt that

the developer had not demonstrated that this was the most suitable site for a mast.

3. A note at the end of the planner’s report said that the council should request further

information, which it did. That was responded to, and the senior planner then prepared an updated

report in which reference was made to section 4.3 of the ministerial guidelines (Telecommunications

Antennae and Support Structures, Guidelines for Planning Authorities, July 1996) which states that

the visual impact of antennae is an important consideration, and that various areas, including

archaeological sites, architectural conservation areas and listed buildings, should be avoided. The

report emphasised that the ministerial guidelines also state that “only as a last resort should free-

standing masts be located within or in the immediate surrounds of towns or villages,” and that the

antennae support structure should be “kept to a minimum height consistent with effective

operation”. Refusal of permission was recommended.

4. In line with that, on 26th November, 2020, the council decided to refuse permission.

5. On 17th December, 2020, the developer appealed, arguing that there was a coverage

blackspot and that co-location on masts of other companies would not provide coverage. It argued

that the mast use was established at the site of the proposed development. In relation to co-

location, it said it was prepared to share its new mast with other operators.

6. The council made a submission to the board. It argued that 5 other telecommunications

operators had good to very good coverage in Kells, and that the developer should co-locate on their

masts. The applicants also made a submission.

7. The board’s inspector recommended refusal of permission on the basis of the ministerial

guidelines, in particular para 4.3 which advises that permission should only be granted as a last

resort for masts in towns and villages.

8. The board disagreed with all of the foregoing and adopted a decision on 17th June, 2021,

granting permission.

Facts after the impugned decision

9. The Applicants say in the statement of grounds (factual paras. 25 and 26) that:

“… they considered challenging the validity of the Board’s Decision. They felt that the Board

Decision did not align with the Ministerial Guidelines. The Guidelines make it clear that visual

impact is a serious issue. The Board did not address the policy of only allowing development

in towns and villages as a last resort. Kells is a village. It has architectural conservation

significance and indeed now contains an architectural conservation area under the 2021

Development Plan, adopted in November 2021. (The designation is made under Section 81

of the 2000 Act.) The Applicants considered the Board erred in law in its approach to co-

location: it accepted the irrelevant reasoning offered by the Developer that the proposed

mast would be made available to other operators, whereas the Ministerial Guidelines make

clear that it is co-location on existing masts that must be ruled out before a new mast will

be allowed. Clustering of masts must also be ruled out. Accordingly, the Proposed

Development did not even approach the threshold required for justification of a new mast in

a village. The Applicants considered that the Board had failed to offer adequate reasons,

had failed to direct itself correctly in law as to the proper interpretation of the Plan and the

Ministerial Guidelines, and had acted irrationally and unreasonably.

They considered challenging the validity of the Board Decision, but ultimately decided not

to, predominantly in light of the costs risk which could materialise. The First Named

Applicant also had a concern at the time given his position as a private planning consultant

with many dealings with An Bord Pleanála and his concern that his challenge of the Board

could lead to repercussions for his clients and his business.”

10. On 11th August, 2021, the 8-week period to challenge the decision under s.50(6) of the

Planning and Development Act 2000 expired.

11. The developer began construction of the development, but the applicants complained that it

had failed to build the project in accordance with the permission. On 15th November, 2021, the

applicants complained to the council about alleged non-compliance with the permission. They

alleged a series of breaches, including that the foundation was in the wrong location. They sent

copies of the complaint to Eircom and its contractor, Delmec.

12. On 17th November 2021, the applicants submitted an application for a declaration under s.

5 of the 2000 Act questioning the works by reference to the permission.

13. On 1st December, 2021, the council issued a warning letter to the developer regarding the

alleged unauthorised location of the foundation.

14. On 17th December, 2021, the developer made a submission to the council replying to the

warning letter in which it referred to condition 1 of the permission. It stated that works had halted,

and proposed to relocate the mast to the correct location and make good the ground.

15. The applicants plead that following the decision and a similar case in Kilmoganny, where

clients of the first named applicant were seeking to challenge a similar Eircom mast within a village,

and where the outcome was similar (permission having been granted in September 2021), the

Applicants began to look at other similar Eircom mast decisions and to monitor new decisions.

16. By early February 2022 they had compiled a list of Eircom mast appeal cases across Ireland

made between September 2020 and February 2022 which showed 28 cases determined – all grants

of permission overturning council refusals - and 9 cases pending.

17. The applicants go on to say that on 12th February, 2022, Mr Thomson and a neighbour met

with John McGuiness T.D. and presented these findings. They say they asked for assistance and

advice in how best to bring this to the attention of the relevant government Department with the

possibility of the matter being investigated. At this time the applicants say that they had not been

examining cases in detail to identify Paul Hyde as the Board member dealing with a high number of

cases. They were not aware of the file allocation policy of random allocation and were not aware of

the existence of board minutes. It is the minutes which identify the names of the other Members

who consider files. Mr Thomson had previously examined the case file with which we are concerned

here at the offices of the board, and there were no minutes on that file.

18. The practice of the board seems to be not to keep minutes of the relevant meeting approving

a development on the case file – but that policy isn’t challenged here. The applicants later became

aware of that practice.

19. The applicants wrote to the council on 3rd March, 2022 advising that the original foundation

had not been removed as agreed. The applicants say that this now redundant unauthorised

foundation still remains on the site.

20. On or about 7th March, 2022, the developer’s contractor, Delmec, wrote to the applicants

stating that works would be carried out in accordance with the permission, and would take place

between 7th and 16th March, 2022.

21. The second foundation was installed in the general location permitted under the permission,

but, according to the applicants, at the wrong height. This was brought to the attention of the

developer by the applicants on 11th April, 2022. The developer replied the same day advising that

it was satisfied with the height of the foundation and that the mast would be erected on 12th April,

2022, which it was.

22. The applicants lodged a second application on 25th April, 2022 for a declaration under s. 5

of the 2000 Act concerning the height of the foundation and mast.

23. The applicants plead that they received an email from John McGuiness T.D. on 27th April,

2022, advising he had sent their information to Minister Darragh O’Brien, to highlight the issue with

the board decisions.

24. They say that in April 2022, , newspaper reports were appearing that suggested that

questions of lack of impartiality arose in relation to the deputy chairperson of the Board, Paul Hyde,

who was the Board member who signed each of the impugned decisions; the other participating

member being Michelle Fagan.

25. Initially, the Reports suggested that the concerns related to Mr Hyde’s involvement with a

property company, H2O Property Holdings Ltd. On foot of these concerns the Minister had appointed

Mr Remy Farrell S.C., to investigate the issues raised regarding Mr Hyde and to report.

26. The applicants say that they decided to engage with media organisations in relation to the

issue, and forwarded their findings to The Ditch on 11th May, 2022. By that time, they had realised

that Mr Hyde was linked to most of the cases they had found. The journalist they were speaking to,

Mr Roman Shortall, expressed an interest in the information and agreed to review it and speak to

them thereafter. They spoke to him the following day and he advised them of the existence of

processes within An Bord Pleanála of which they were not previously aware, such as random file

allocation and how to source board minutes.

27. On 12th May, 2022, the terms of reference of a report to be conducted in relation to issues

concerning the board by Mr Farrell S.C. were published.

28. There was a further warning letter dated 12th May, 2022 to the developer in respect of non-

compliance with condition 1 of the permission.

29. The applicants say that on 19th May, 2022, Mr Shortall forwarded copies of some of the

board minutes he had obtained from the board relating to some of the Eircom cases. On or just

before 26th May, 2022, Mr Shortall advised the applicants that the Irish Examiner was also looking

into Eircom decisions and passed the applicants’ information to that newspaper. From that emerged

the first newspaper article on the telecommunication mast issue and the involvement of Mr Hyde in

most mast cases: “An Bord Pleanála deputy chair overruled inspectors in vast majority of mast

applications” (Irish Examiner, 28th May, 2022) by Mr Cianan Brennan.

30. On 3rd June, 2022, the council followed up with an enforcement notice.

31. The applicants plead that on 4th June, 2022 the applicants emailed the Irish Examiner on

foot of its article and outlined their desire to have the telecommunication mast decisions included in

the Farrell investigation into certain board decisions. However, shortly afterwards they were advised

by their solicitors that the scope of the Farrell investigation was not going to be extended beyond 3

particular cases.

32. They made a submission to the Office of the Planning Regulator (OPR) on 6th June, 2022.

33. On 8th July, 2022, the former deputy chairperson, Mr Hyde, resigned.

34. The applicants plead that on 15th July, 2022, they sent their material to the board and

requested it be included in the internal review which the board was in the process of carrying out in

light of the revelations concerning some cases handled by Mr Hyde.

35. On 18th July, 2022, they were advised by email from the OPR that it was not investigating

the behaviour or performance of any individual but was looking into systems and procedures. This

email followed a call the applicants had made to the OPR earlier, having not received a response to

their email.

36. In response to the enforcement notice, the developer submitted a construction management

plan on 29th July, 2022.

37. The applicants plead that there were numerous emails between the applicants and the board

concerning their submission. On 7th September, 2022, it was confirmed for the first time that the

Eircom files on their list were being included in the internal investigation. The same email advised

that, subject to legal advice, the chairperson intended to publish the findings of the report.

38. By 22nd September, 2022, the applicants were aware that there was no formal record of

allocation of telecommunications files from board email correspondence.

39. On 26th September, 2022, the applicants’ solicitors made an AIE request to the board

pursuant to the European Communities (Access to Information on the Environment) Regulations

2007, enquiring about the manner in which the file relating to the Kells board decision was allocated.

40. On 10th October, 2022, media reports indicated that Mr Hyde was being prosecuted. This

seems to have been an important event in the applicants’ change of mind about not challenging the

permission. Mr Thomson advised his solicitors verbally on 10th October, 2022 to draft proceedings

and on or after that date counsel advised that the proceedings could be taken.

41. The developer removed the mast on 13th October, 2022. Since that, the mast has not yet

been re-erected.

42. The applicants plead that on 21st October, 2022 they received an email from the board

advising the report had been discharged to the Chairperson following legal analysis and it was for

him to decide what he would do with the report. They say that:

“Throughout this time, the Applicants had felt they should not take any premature action,

and that they should await the publication of the Board’s report in order to see if there was

any substance to the circulating allegations, and what impropriety, if any, might come to

light. However, the non-publication of the report, along with the news that Mr Hyde was

being prosecuted, has destroyed, in the Applicants’ minds, the last vestiges of credibility in

the impartiality of the decision making process”.

43. On 24th October, 2022, there was media publication of details from the board’s unpublished

internal review report.

44. On 29th October, 2022, the board made a statement that the internal review report would

not be published following legal advice.

45. On 8th November, 2022, the board confirmed in response to the AIE request that normal

planning appeals files are randomly allocated.

Procedural history

46. The proceedings challenging the decision were issued on 28th November, 2022. On that

date they were mentioned before Holland J. and adjourned.

47. On 19th December, 2022 I admitted the case to the Commercial Planning & Environmental

List, and noted Eircom’s representation that the development hasn’t been re-erected in whole or in

part other than by way of pre-concrete-pouring groundworks. I also noted Eircom’s undertaking not

to re-erect the development in whole or in part pending final determination of the proceedings

without prejudice to their right to retrieve equipment currently on the lands in question. On that

basis I changed Eircom’s status in the proceedings from a respondent to a notice party and excused

them from further participation, with liberty to apply.

48. On 23rd December, 2022 I allowed a first amended statement of grounds.

49. On 20th February, 2023 I granted an extension of time without prejudice to any argument

the opposing parties might make, and granted leave on the basis of allowing a second amended

statement of grounds.

50. The board then brought a notice of motion filed on 14th March, 2023 seeking to set aside

leave. That motion was heard on 4th July, 2023 and listed for mention on 5th July, 2023, when

judgment was reserved.

Relief sought

51. The relief sought in the second amended statement of grounds is as follows:

“1. An Order of Certiorari pursuant to Order 84 of the Rules of the Superior Courts 1986

as amended and Section 50 of the Planning and Development Act 2000 as amended quashing

the decision of the First Respondent, An Bord Pleanála (the Board), dated 17 June 2021, file

reference ABP-308931-20, to grant permission for erection of a 15m high mobile phone mast

at Kells, County Kilkenny, therein described as:

Proposed Development: The development will consist of the replacement of an

existing 10m wooden pole for a 15 metre high free standing communications

structure with its associated antennae, communication dishes, ground equipment

and all associated site development works. The development will form part of Eircom

Limited existing telecommunications and broadband network at Kells Eircom

Exchange, Haggard Road, Kells, County Kilkenny.

2. Such declaration(s) of the legal rights and/or legal position of the applicant and (if

and insofar as legally permissible and appropriate) persons similarly situated and/or of the

legal duties and/or legal position of the Respondents and Notice Party as the court considers

appropriate.

3. Directions of the type outlined at paragraph 81 of the decision in Reid v Bord

Pleanála, [2021] IEHC 362 requiring the Board to investigate and determine, and file one or

more affidavits giving a detailed account of:

3.1. How it managed the allocation of the file relating to its decision dated 17

June 2021, on file reference ABP-308931-20.

3.2. How it managed the allocation of files relating to telecommunications masts

and antennae generally between 1 January 2021 and 8 July 2022, and in particular

how it came about that two Board members, Paul Hyde and Michelle Fagan, were

allocated to such a large proportion of such files between those dates.

3.3. The circumstances leading to the resignation of Paul Hyde.

4. Such further declarations, injunctions and directions as may be appropriate for the

purposes of giving full effect to the above relief, or of any matter emerging in the course of

such investigation, determination and filing.

5. A Declaration that Section 50(7) and / or (8) of the Planning and Development Act

2000 as amended are contrary to Article 34 of the Constitution and invalid, and / or contrary

to Article 4(3) and 19(1) of the Treaty on European Union and must be set aside.

6. A Declaratory Order confirming that Section 50B of the Planning and Development

Act 2000 as amended and / or Sections 3 and 4 of the Environment (Miscellaneous

Provisions) Act 2011 as amended apply to the Applicants herein in respect of the Grounds

set out at Part E hereof.

7. An extension of time to apply for leave to seek judicial review of the decision of the

Board, pursuant to Section 50(8) of the Planning and Development Act 2000 as amended.

8. A stay pending determination of the present proceedings on the re-erection by the

Second Respondent Notice Party of, the mobile phone mast and / or telecommunications

antennae purportedly authorised by the Decision dated 17 June 2021, file reference ABP-

308931-20, to grant permission for erection of a 15m high mobile phone mast at Kells,

County Kilkenny, same having been removed along with the unauthorised foundation for

non-compliance pursuant to an enforcement notice issued by Kilkenny County Council.

9. If required, an injunction pursuant to Section 160 of the Planning and Development

Act 2000 requiring removal of the mobile phone mast at Kells, County Kilkenny purportedly

authorised by Board decision reference ABP-308931-200.

10. Further or other relief.

11. Costs.

12. Discovery for the purposes of grounding the reliefs set out above, including third

party discovery against:

12.1. Paul Hyde, c/o An Bord Pleanála, 64 Marlborough Street, Dublin 1

12.2. Sharon Hickey and Sean Hickey

12.3. Promontoria Ltd, c/o Mason Hayes and Curran, Solicitors, South Bank House,

Barrow Street, Dublin 4”

Grounds of challenge

52. The core grounds as set out in the second amended statement of grounds are as follows:

“1, The Board Decision is invalid because the Board was affected by bias or the appearance

of bias.

2, The Board Decision is invalid because the Board members involved in taking the decision

failed to comply with the provisions of the Code of Conduct, contrary to S150(1) of the 2000

Act.

3, The Board Decision is invalid because Paul Hyde entered into a composition or

arrangement with creditors as a result of which he was deemed pursuant to S106(13)(d) to

have ceased to be a member.

4, The Board Decision is invalid because the Board erred in law in its interpretation of

paragraph 9.4.2.1 of the 2014 Development Plan, and / or failed to have any or any adequate

regard to the Ministerial Guidelines in breach of Section 28 of the 2000 Act, and / or failed

to give any or any adequate reasons for its departure from Ministerial Guidelines and the

requirements of the 2014 Development Plan in breach of Section 34(10) of the 2000 Act.

5, There is good and sufficient reason to extend time for bringing of the application for leave

to apply for judicial review, and the circumstances of same were outside the control of the

Applicants, in accordance with Section 50(8) of the 2000 Act.

6, The Applicants are entitled to the protection against costs conferred by Section 50B of the

2000 Act and / or Sections 3 and 4 of the Environment (Miscellaneous Provisions) Act 2011.

7, The Court should stay the re-erection of the Development, and / or require removal of

the Development insofar as same may have been re-erected.”

The law in relation to extension of time

53. Leave was granted on the basis that time ought to be extended, but that of course was an

ex parte application and therefore, like any ex parte order, can be reconsidered on an inter partes

basis (Adam v. Minister for Justice [2001] IESC 38, [2001] 3 I.R. 53, [2001] 2 I.L.R.M. 452, [2001]

4 JIC 0506). The wording of the leave order made that clear in any event.

54. The test for extension of time is as set out in s. 50(8) of the 2000 Act:

“(8) The High Court may extend the period provided for in subsection (6) or (7) within which

an application for leave referred to in that subsection may be made but shall only do so if it

is satisfied that—

(a) there is good and sufficient reason for doing so, and

(b) the circumstances that resulted in the failure to make the application for leave

within the period so provided were outside the control of the applicant for the

extension.”

55. Thus there are two limbs to the test. The first limb is that the failure to bring the action

within the original 8 weeks is “outside the control” of the applicant. That applies only to the initial

period of 8 weeks, not the total period (see SC SYM Fotovoltaic Energy SRL v. Mayo County Council

(No 1) [2018] IEHC 20, [2018] 1 JIC 2404 (Unreported, High Court, Barniville J., 24th January,

2018) at §72(3)).

56. The second limb is that there is good and sufficient reason for the extension. The existence

of good and sufficient reason isn’t defeated by the existence of any period, however short, that is

not explained – that would be an impossible test because there is always a period here or there

which could have been dealt with more quickly. Say an applicant’s lawyers take 3 weeks to draft

and issue the proceedings – why wasn’t it two weeks? That nit-picking can go on indefinitely. But

the point is that regard must be had to the whole period – see SC SYM Fotovoltaic Energy SRL v

Mayo County Council (No 1) at §72(5), Sweetman v. An Bord Pleanála [2017] IEHC 46, [2017] 2

JIC 0205 (Unreported, High Court, Haughton J., 2nd February, 2017) at §6.5 et seq. and Reidy v.

An Bord Pleanala [2020] IEHC 423, [2020] 7 JIC 3110 (Unreported, High Court, Barr J., 31st July,

2020) at §43 – not that every second of every minute must be accounted for with a free-standing

good and sufficient reason. If the latter was the test, it could never be satisfied.

57. If there is good and sufficient reason for an extension on one ground, that is not defeated

by the inclusion in the pleadings of another separate ground where such reason does not exist. One

only has to consider the alternative to see why that should be. If an applicant is disqualified from

seeking an extension of time because she includes one ground in a proposed statement of grounds

which could have been raised originally, that would penalise applicants on a purely technical basis

by discriminating against those who (erroneously) include such a ground and have the extension of

time refused outright on that basis, as compared with an applicant who limits themselves to grounds

for which an extension should be granted. It would be unfair to reject the first applicant outright on

all grounds (including those for which an extension is warranted) merely for erroneously including a

stale ground. To adopt the creative but totally artificial and legalistic submission to the contrary

that was made by a notice party in the proceedings heard with the present case would have a

disproportionate and unfair impact and would penalise human error in a way that does not serve the

interests of justice.

58. The basic rule in relation to good and sufficient reason is that the court has to be reasonably

strict, in a commercial context as opposed to a purely human rights context, with the time limit for

initiation of the proceedings in the first place (see per Murray J. in Arthropharm (Europe) Ltd v. The

Health Products Regulatory Authority [2022] IECA 109, [2022] 5 JIC 1003 (Unreported, Court of

Appeal, 10th May, 2022)). The court can and should be more flexible with amendments to

proceedings that were actually brought within time, for reasons explained elsewhere (e.g., by

allowing points that were simply overlooked by counsel initially – Keegan v. Garda Síochána

Ombudsman Commission [2012] IESC 29, [2012] 2 I.R. 570, [2012] 5 JIC 0103). However, a late

initiation of the proceedings in the first place is a more serious matter because it changes the status

of the decision from unchallenged to challenged thereby creating fundamental uncertainty as to its

status. Mere refinement or rewording of grounds has much less impact on such policy

considerations.

59. As pointed out by Simons J. in Arthropharm (Europe) Ltd v. The Health Products Regulatory

Authority [2020] IEHC 16, [2020] 1 JIC 1402 (Unreported, High Court, 14th January, 2020) at paras.

79-82, an applicant is generally not entitled to hold off on bringing proceedings while awaiting the

assembly of all relevant materials, citing Talbotgrange Homes Ltd. v. Laois County Council and

Others [2009] IEHC 535, [2009] 12 JIC 0203 (Unreported, High Court, McCarthy J., 2nd December,

2009) at para. 66, Irish Skydiving Club Ltd. v. An Bord Pleanála [2016] IEHC 448, 2016 WJSC-HC

11483, [2016] 7 JIC 2907 (Unreported, High Court, Baker J., 29th July, 2016) at para. 41, SC SYM

Fotovoltaic Energy SRL v. Mayo County Council (No. 1), at para. 100 and A Foster Mother v. Child

and Family Agency [2018] IEHC 762, [2018] 12 JIC 2102 (Unreported, High Court, Simons J., 21st

December, 2018) at para. 121. The principle outlined in McBain v McDonald [1991] 1 I.R. 284,

[1991] I.L.R.M. 764, 1991 WJSC-HC 912, [1991] 1 JIC 2102 applies by analogy. There, Morris P.

noted that a plaintiff, within the limitation period, had access to evidence which “was already

available to the plaintiff upon which she could rely in an attempt to persuade the court that on the

balance of probabilities the defendant was responsible”. The fact that further information became

available later “which she believes will copper fasten the matter in her favour” was not a basis to

extend the limitation period.

60. Jerry Beades Construction Ltd v. The Right Honourable Lord Mayor Alderman and Burgesses

of the City of Dublin and Others [2005] IEHC 406, [2005] 9 JIC 0701 (Unreported, High Court,

McKechnie J., 7th December, 2005) does not run contrary to this principle because in that case there

was no third party being adversely affected by any delay and because the information initially

available to the applicant wasn’t sufficient to enable it to make the point. There is no analogy here.

61. The current law is that the time (8 weeks in the case of a planning decision) runs from the

date of the decision (see Irish Skydiving v An Bord Pleanála (at §37) and Heaney v. An Bord Pleanála

[2022] IECA 123, [2022] 5 JIC 3123 (Unreported, Court of Appeal, Donnelly J., 31st May, 2022) at

§34, reflected in O. 84 r. 21(2) RSC), but that is less harsh than it seems because the court will

generally (although maybe strictly speaking this has yet to be declared to be an absolute matter of

right) allow the full period from the date the applicant knew about the problem, or if earlier, on

which a reasonably diligent applicant would have known about the problem (see SITA UK Limited v.

Greater Manchester Waste Disposal Authority [2011] EWCA Civ 56). Indeed the court is required to

allow such a period in cases with an EU law dimension, of which this is one because of the need to

consider the EIA and habitats directives in the planning context: see Case C-456/08 European

Commission v. Ireland (Court of Justice of the European Union, 28th January, 2010,

ECLI:EU:C:2010:46), Case C-406/08 Uniplex (UK) Ltd v. NHS Business Services Authority (Court of

Justice of the European Union, 28th January, 2010, ECLI:EU:C:2010:45), and caselaw discussed in

Marshall v. Kildare County Council [2023] IEHC 73, [2023] 2 JIC 1705 (Unreported, High Court, 17th

February, 2023) (under appeal by the applicants, but this was a point decided in favour of the

applicants).

62. The court in deciding whether there is good and sufficient reason should take a holistic view

of all of the circumstances: Heaney v. An Bord Pleanála. However in doing so, considerations arising

from any prejudice to third party beneficiaries of permissions will loom large. Other matters (for

example that not all information was to hand, other processes were ongoing, inquiries were in hand,

the decision-maker wasn’t particularly helping matters, or the law in relation to costs was uncertain)

are unlikely to outweigh those major considerations unless they had the effect that an applicant was

significantly inhibited from instituting proceedings within time. Not having all of the detail and all of

the evidence does not constitute a significant inhibition for this purpose.

Whether leave should be set aside here

63. Whether leave here should be set aside depends on whether time should have been

extended, which can be looked at on a ground-by-ground basis (core grounds 5, 6 and 7 do not

relate to substantive relief).

64. As regards the question of whether failure to make the point in the first place was outside

the control of the applicants, I agree that it was, apart from in relation to the core ground 4 (which

deals with points evident on the papers originally). Insofar as the applicants complain that the board

erred in law in its interpretation of paragraph 9.4.2.1 of the 2014 Development Plan, and/or failed

to have any or any adequate regard to the ministerial guidelines in breach of s. 28 of the 2000 Act,

and/or failed to give any or any adequate reasons for its departure from Ministerial Guidelines and

the requirements of the Development Plan in breach of s. 34(10) of the 2000 Act, that is a non-

starter as a basis to extend time. Those points were evident in the decision from the outset, and

failure to bring the proceedings in time was not outside the control of the applicants.

65. Core grounds 1-3 deal with points that would not have been obvious initially to a reasonably

diligent applicant, so the “outside the control” test is satisfied. This brings us to the question of

good and sufficient reason, which in turn depends on when the applicant knew about the issues

sought to be raised, or, if earlier, when a reasonably diligent applicant ought to have known about

them. The position in relation to the allegations made in core grounds 1-3 is as follows:

(i) Alleged bias or objective bias on the part of the board related to lack of

random allocation and excessive granting rate. The applicants knew of the

statistical anomalies in mast-related decision-making by February, 2022, although I

do appreciate the point that some further information was required in order to allow

that anomaly to mature into the sort of legal ground advanced here. Any concerns

about non-random allocation can be said to arise not just from that, but once the

identity of the decision-makers is known, even if further details are awaited such as

whether the board’s official stance was whether there was randomisation or not. The

applicants learned of how to access board minutes on 12th May, 2022. A reasonably

diligent applicant could have got that information within a couple of weeks from that

date. Even allowing for that further period, the applicants failed to bring the

challenge within 8 weeks from then. The fact that they got further detail

subsequently doesn’t mean that they didn’t have an obligation to move within 8

weeks from knowing enough to bring the challenge. The applicants seem to have

been labouring under the fundamental misapprehension that they could wait for the

results of investigations and inquiries, whether by the board, Mr Farrell S.C., or

somebody else, but that is a totally and indeed fairly self-evidently flawed approach.

An applicant isn’t entitled to wait for a respondent to admit wrongdoing, or to wait

for further evidence once the material meets the minimum level necessary to launch

a challenge. She must act independently of such admission or such additional

material, and must litigate within the specified period (normally 3 months, but 8

weeks in planning) from the date on which a reasonably diligent person would have

had enough information to institute proceedings. There is somewhat more latitude

if we are talking about amending a challenge that has already been brought, but we

are not dealing with an amendment here.

(ii) Failure to comply with the provisions of the Code of Conduct, contrary to s.

150(1) of the 2000 Act. This is primarily a reformulation of the first core ground,

as illustrated by the first sub-ground – “Paragraphs 1.1 to 1.11 above are repeated

as if set out herein”. The applicants had enough to go on to make this point as of

mid-2022.

(iii) Mr Hyde entered into a composition or arrangement with creditors as a

result of which he was deemed pursuant to s. 106(13)(d) of the 2000 Act

to have ceased to be a member. This illustrates an interesting point, which is

that if a person is invalidly appointed to public office, or if their appointment becomes

invalid (say for example a judge is purportedly appointed who is not properly

qualified for the office on the date of appointment (see The State (Walshe) v. Murphy

[1981] I.R. 275)), that appointment doesn’t become unchallengeable 3 months after

the person takes up their role. Such an appointment can be challenged from time

to time into the future as the person acts in new matters that affect new potential

applicants. Indeed that is itself a sub-set of the more general principle that the

interests of justice favour an approach that allows unlawful failures to act, continuing

wrongs, or measures of general application, to be challenged from time to time as

they affect new applicants, rather than being shielded from the rule of law by a time

limit that expires before an individual applicant is in a position to challenge the

problem. So the point is not ruled out merely because the alleged composition with

creditors (and hence the alleged invalidity of continuing in office) is of some vintage.

Instead, the applicants are ruled out because this was all in the public domain long

before the present proceedings were instituted. The problem was referred to in an

article on 6th April, 2022 in The Ditch, “Deputy chairperson of An Bord Pleanála was

pursued in High Court for defaulting on investment property loans”. It is also

addressed in Mr Farrell S.C.’s terms of reference of 12th May, 2022. The applicants

didn’t bring the proceedings within 8 weeks of the matter coming to light. I accept

that details of the alleged composition with creditors have never been released, but

you don’t need the details to get the basic point. Assuming that a reasonably diligent

applicant wouldn’t have known of the issue earlier, anyone who found out about Mr

Hyde’s alleged composition in May 2022 had 8 weeks to challenge a decision made

since the date of the composition. Virtually nobody did so, and certainly these

applicants didn’t. This isn’t hindsight – anyone involved in practical planning

litigation is very conscious of the time limits and should be aware of the severe risks

of sitting on any point for more than 8 weeks after becoming aware of a ground to

impugn a decision if no proceedings at all have been commenced. The further detail

isn’t necessary to do that, and anyway all of that detail could have been obtainable

in such hypothetical proceedings through discovery or disclosure. Enough was

known in mid-2022 to bring proceedings raising the point, even if subsequent steps

to obtain further evidence to advance the point would need to be taken.

66. Insofar as the court should consider holistically all other circumstances above and beyond

the critical issue as to when the applicant knew or ought to have known about the problem (Heaney

v. An Bord Pleanála per Donnelly J. at para. 74), I have done that and have borne in mind all points

raised by the applicants, but they don’t outweigh the substantial public interest in certainty in a

commercial context that is the object and purpose of the time limit (see inter alia Arthropharm,

K.S.K. Enterprises v. An Bord Pleanála and Anor [1994] 2 I.R. 128, [1994] 2 I.L.R.M. 1, 1994 WJSC-

SC 1176, [1994] 3 JIC 2403 per Finlay C.J. at 135, Reidy v. An Bord Pleanála per Barr J. at para.

39)). That important objective is not outweighed by the applicants’ complaints that this is a systemic

failure, that the board didn’t realise and rectify what was going on, or any of the other points made.

Of course life would be simpler if the board had got to the bottom of all problems much quicker, but

the fact that it didn’t do so doesn’t remove the unfairness to the developer that would be created by

re-opening the decision here. The fact that the applicants have sought directions under Reid v. An

Bord Pleanála (No. 2) [2021] IEHC 362, [2021] 5 JIC 2705 (Unreported, High Court, 27th May,

2021) para. 81 aimed at obtaining information regarding the procedure for file allocation, for

example, doesn’t get them any further because it doesn’t get around the problem that they had

enough information to sue at a much earlier time, albeit far from all information. The idea that it

was “reasonable” to wait for progress in ongoing inquiries was a profoundly mistaken strategy apart

altogether from being an obviously perilous one on its face. An applicant seeking to impugn a

decision subject to an expiring time limit for challenge has to do more than merely scrape above the

absolute bare minimum requirement of being “reasonable”. She has to act with great expedition by

moving before the end of the statutory timelines. That doesn’t mean there is an obligation to act

with expedition within the prescribed time limit – that definitely doesn’t arise at all in an EU case

and probably not even in a domestic law case, provided that the applicant does actually manage to

bring proceedings within the period as measured from the date a diligent applicant would have

known enough to litigate. A free-standing obligation to act promptly within the time limit would

fundamentally undermine legal certainty. The requirement is to act within the prescribed period

from the decision, or at the latest from when the applicant knew or ought to have known of it. But

the applicants here didn’t act with expedition in either sense.

67. The effect of the foregoing is that I would probably have regarded mid-June (a few weeks

from 12th May, 2022 to allow for obtaining the minutes) as being the latest date on which the

applicants had (or a reasonably diligent applicant would have had) sufficient information to bring

proceedings. Eight weeks from then expired in mid-August, 2022. The applicants are out of time

and have not established that there is good and sufficient reason to extend time.

68. This case illustrates the general point that a court deciding a case is not a tribunal of inquiry.

Yes, reasonable people could conclude that the applicants have advanced the public interest by

ventilating their concerns with The Ditch and the Irish Examiner, and that those media organisations

performed their role effectively in following those matters up. Whatever happens with the present

application, the applicants can be happy with that. Yes, the applicants have in the proceedings

raised important matters that well surmount the substantial grounds threshold; and yes, most of

these matters relate to probity in public life and are issues of general concern. But it’s not the

court’s role to examine matters for the sole reason that they are important or concerning. The

importance of an issue is at most a factor (particularly relevant to applications to amend or strike

out, for example) but it is not in itself a basis for the court to get involved in the first place. Even

an error on the face of a decision doesn’t mean that an extension of time isn’t required: per Woulfe

J. in Krikke v Barranafaddock Sustainable Electricity Limited [2022] IESC 41, [2023] 1 I.L.R.M. 81,

[2022] 11 JIC 0303 at para. 80.

69. The court’s role at its most basic (and with a fair bit of over-simplification, and leaving aside

the obvious additional obligations such as arise under the Bangalore principles and their domestic

equivalents, or other legal duties such as the need to give reasons) is:

(i) to decide issues that properly arise in the proceedings, which in practice is normally

limited to the issues raised by one or more of the parties (albeit that occasionally a

party might only decide to raise such an issue after engagement with the court

during the normal course of debate and discussion at a hearing, which is not in itself

impermissible at the level of principle, and albeit that occasionally a court can do

something of its own motion, although those situations are normally fairly defined);

(ii) to decide such issues only if they fall within the pleadings, provided that the legal

procedure being invoked involves pleadings and that the issues are such that they

require to be pleaded;

(iii) to decide those issues only insofar as the parties disagree about them (with only

occasional exceptions, such as where parties are agreed on an order that the court

doesn’t have jurisdiction to make, or that impermissibly interferes with the rights of

a person not before the court);

(iv) even then to formally decide such issues only where relevant to the actual order or

other business at stake (which doesn’t preclude conditional findings, or other obiter

comments from time to time); and

(v) not to decide such issues other than in accordance with law and the Constitution.

70. The latter point is crucial here. The law, validly enacted by the Oireachtas (see In re Planning

and Development Bill 1999 [2000] IESC 20, [2000] 2 I.R. 321, [2001] 1 I.L.R.M. 81, [2000] 8 JIC

2802) provides for a time limit and for criteria for extending that. Those criteria are not met here.

The potential merits of the important points raised by the applicants are not sufficient to overcome

that. To extend time here would be unfair to the commercial interests involved. The developer is

entitled to rely on its permission unless there is a clear case for a belated challenge. The court also

has to bear in mind the various structural asymmetries in planning law in favour of applicants, and

to balance those with a reasonably strict approach to time in a commercial context.

71. Ultimately the problem for the applicants is very simple. As of May, 2022, they had concerns,

they had information, they even had solicitors. But instead of taking those concerns to the High

Court at that point, they went to the media. That is absolutely fine in itself, obviously, and

reasonable people might even say commendable to the extent that it served the interests of public

debate, active citizenship, and transparency. But failing to bring proceedings in such circumstances

means that when they changed their mind and came to court in November, 2022, they were a day

late and a dollar short.

Order

72. For the foregoing reasons, it is ordered that:

(i) the order granting an extension of time and granting leave to apply for judicial review

be set aside and in lieu thereof there be an order refusing the application for an

extension of time and refusing leave to apply for judicial review;

(ii) Eircom be released from their undertaking not to proceed with the development,

with effect from the perfection of the order; and

(iii) unless any party applies otherwise by written legal submission within 7 days, the

foregoing order be perfected forthwith thereafter on the basis of no order as to costs.