High Court grants interim stay of foreshore licence pending full judicial review application.

Case Number IEHC 263
Court / Authority
Jurisdiction Ireland (IE)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The High Court granted an interim order staying the effect of a foreshore licence pending the grant of leave for judicial review. The applicant sought this relief before the full challenge was heard, while notice parties were absent and procedural steps were slightly irregular. The court exercised its inherent jurisdiction to prevent irreparable harm and ensure the substantive proceedings could be heard effectively.

Legislator headnote

AI generated

Sections 21B and 3 of the Foreshore Act 1933; Section 50B of the Planning and Development Act 2000: The High Court has the inherent jurisdiction to grant an interim stay of administrative action pending judicial review to prevent irreparable harm and ensure the efficacy of the proceedings.

Keywords

AI generated
interim stay order judicial review procedure foreshore licence inherent jurisdiction irreparable harm planning and development interlocutory relief

Cited Legislation

AI generated

Cited Case Law

AI generated
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[2023] IEHC 263

THE HIGH COURT

JUDICIAL REVIEW

[2023 No. 407 JR]

IN THE MATTER OF SECTIONS 21B AND 3 OF THE FORESHORE ACT 1933, AS AMENDED

AND

IN THE MATTER OF SECTION 50B OF THE PLANNING AND DEVELOPMENT ACT 2000, AS

AMENDED

BETWEEN

IVAN TOOLE AND GOLDEN VENTURE FISHING LIMITED

APPLICANTS

AND

THE MINISTER FOR HOUSING, LOCAL GOVERNMENT AND HERITAGE AND THE MINISTER

OF STATE FOR THE DEPARTMENT OF HOUSING, LOCAL GOVERNMENT AND HERITAGE

WITH SPECIAL RESPONSIBILITY FOR PLANNING AND LOCAL GOVERNMENT

RESPONDENTS

AND

RWE RENEWABLES IRELAND LIMITED AND THE MINISTER FOR AGRICULTURE, FOOD

AND THE MARINE

NOTICE PARTIES

JUDGMENT of Humphreys J. delivered on the 22nd day of May, 2023

1. In this application, an interim order was sought staying the effect of a foreshore licence prior

to the grant of leave to seek judicial review to challenge that licence.

2. I heard the application and announced the order on 8th May, 2023 and gave reasons ex

tempore on 9th May, 2023, although I did emphasise that the written version would be the definitive

one. I am now giving that written version of the reasons, which, while restructuring the arrangement

and wording somewhat (as is virtually inevitable), is intended to reflect the essential substance of

the points already made.

3. The application involved submissions from the applicant and first named notice party. The

State parties were notified that the matter would be listed on 8th May, 2023, albeit they might not

have understood that that was in the context of a stay application specifically, but given that they

had notice of the date and that they indicated they would not be attending (referencing inter alia a

lack of papers), I didn’t see their absence as a reason not to deal with the matter. Admittedly, the

applicant served the Minister concerned directly rather than via the CSSO, which is what more

properly should have happened, but the Department did pass on the letter which also expressly and

prudently says that contact can be made with the List Registrar to seek access to ShareFile. In that

regard it was not totally clear at that point anyway, in the absence of hearing from the State, as to

why there was a difficulty accessing papers.

4. What I propose to do is to address the facts insofar as they appear to the court at this stage,

the jurisdiction to grant a stay at this point in the procedure, the law in relation to the grant of such

a stay and the application of that law to the facts here. For the avoidance of doubt, dealing with a

matter such as this in an interim way is very much without prejudice to any particular conclusion

being revisited at the interlocutory stage with the benefit of other factual material and legal

submission as appropriate.

Facts

5. In 2017, the applicants’ fishing business, Golden Venture, was established.

6. In 2019, the Rockabill to Dalkey Island Special Area of Conservation was defined by the

European Union Habitats (Rockabill to Dalkey Island Special Area Of Conservation 003000)

Regulations 2019 (S.I. No. 98 of 2019). This specified the qualifying interests of the special area of

conservation (SAC) as follows:

Natural Habitat Type

Natura 2000 Code Description

1351 Reefs

Animal and Plant Species

Natura 2000 Code Common Name Scientific Name

1351 Harbour Porpoise Phocoena phocoena

7. The Natura Impact Statement (NIS) here appears to be prepared on the basis of the

Geogenic reefs to which it relates being a qualifying interest falling within the reefs defined by the

SAC order. Reference is made to a lack of mapping.

8. On 25th January, 2021, a previous licence was granted in favour of the first named notice

party (reference FS 007029), and on foot of that the first named notice party carried out what is

referred to in the papers as a “2020 site investigation campaign”, although that appears to have

happened in 2021.

9. The licence now under challenge was sought under s. 3 of the Foreshore Act 1933 on 1st

October, 2021, to undertake geotechnical and geophysical site investigations and ecological, wind,

wave and current monitoring to provide further data to refine wind farm design, cable routing,

landfall design and associated installation methodologies for the proposed Dublin Array offshore wind

farm off the coast of counties Dublin and Wicklow.

10. That was advertised on 17th November, 2021 and thereafter and 17 submissions were made

during the public consultation process as well as 8 submissions by prescribed bodies. An appropriate

assessment (AA) screening was carried out dated May, 2022 which accepted that likely significant

effects could not be discounted. A marine advisory environmental screening stage report of 20th

June, 2022 concluded that environmental impact assessment (EIA) was not required although

reference was made to obligations to conduct an examination by the Department itself. The

preliminary examination prepared by the marine advisor also dated 20th June, 2022 concluded that

there was no real likelihood of significant effects on the environment and a screening determination

regarding appropriate assessment was signed by the Minister on the same date.

11. That resulted in a public consultation procedure in relation to stage 2 AA which ultimately

culminated in a conclusion that the proposed activity would not adversely affect the integrity of any

European site having regard to mitigation measures. A conclusion statement was signed by the

Minister on 23rd November, 2022.

12. As of December, 2022, in advance of the licence, the first named notice party appears to

have chartered at least one of the boats required for the site investigation.

13. The impugned five-year foreshore licence itself was executed by licence agreement on 13th

January, 2023. Condition 31.9 of the licence was particularly emphasised by the applicants and

provides as follows:

“The licensee shall ensure that the intertidal and subtidal geotechnical sampling locations

will be selected after review of the geophysical and environmental data obtained from

surveys completed under licence FS 007029 has been reviewed for the presence of potential

ecological features such as Geogenic reef.”

14. Notice of the licence was published in Iris Oifigiúil on 27th January, 2023 pursuant to s. 21A

of the 1933 Act. The first named notice party then proceeded to notify interested parties that

borehole drilling would commence in April, 2023. On 20th April, 2023, the applicants gave notice of

an intention to bring proceedings and to seek a “stay or similar relief” (exhibit IT3). The first named

applicant received a notice that, weather permitting, the array borehole element of the survey was

intended to commence on 23rd April, 2023.

15. There then followed an alleged incident where one of the boats chartered by the first named

notice party allegedly collided with static fishing gear belonging to the second named applicant.

Procedural history

16. On 26th April, 2023, proceedings issued and were mentioned to Holland J. Strictly speaking,

the proceedings were out of time on the basis of time running from the date of the decision, but

given that one can reasonably assume that the applicants were not made aware of the decision until

its publication in Iris Oifigiúil, they should be entitled to the full period of three months in this

instance running from the date of that notification, particularly having regard to the EU law elements

of the case (see caselaw discussed in Marshall v. ESB [2023] IEHC 73, [2023] 2 JIC 1705

(Unreported, High Court, 17th February, 2023)).

17. In Casey v. Minister for Housing Planning and Local Government & Ors [2021] IESC 42,

[2021] 7 JIC 1601 (Unreported, Supreme Court, 16th July, 2021) Baker J. held that failure to publish

a licence did not make it invalid but “a person who wishes to challenge by judicial review the making

of a licence may be able to rely on the absence of publication to seek an extension of time to bring

judicial review should that be required” (para. 134). That is consistent with the concept that

technically an extension of time is appropriate here. It may well be that due to Casey, the notice of

the licence implies that the period for challenge is to run from the date of publication, but nonetheless

in strictly technical legal terms a formal extension of time is still required if the challenge is brought

outside a period of three months as measured from the date of the decision itself.

18. On the day the application was issued, the applicants contacted the first named notice party

to complain further in relation to the alleged collision already mentioned.

19. On 28th April, 2023, the applicants emailed the Minister of State enclosing a motion to admit

the proceedings to the Commercial Planning and Environmental List pursuant to Practice Direction

HC119, although, as mentioned, it would have been preferable if the CSSO had been served on

behalf of the Minister. On the same date, the motion was served on the solicitors for the first named

notice party.

20. At the initial mention date, the matter was adjourned to 8th May, 2023. In fact, that was

the immediately next following sitting Monday list in the Commercial Planning and Environmental

List given the fact that Monday 1st May, 2023 was a public holiday (whether one wishes to celebrate

it as International Workers’ Day as proclaimed by the Second International in 1889, or the Celtic

festival of Bealtaine, or for good measure the Roman festival of Flora, can be left to individual taste

and judgement). But for that fact, the matter would have come back to the court rather sooner, so

I am not sure that the applicants can really be massively faulted for any lapse of time in that regard

specifically.

21. The first named notice party in any event, notwithstanding the proceedings, continued to

implement the licence and was doing so by carrying out boring as of the date of the hearing of the

application for interim relief. The first named notice party had chartered two boats, a tug boat, the

Dutch Pearl, and a drill rig which was not self-propelling and was essentially floating infrastructure

called Excalibur. There is reference on the papers to two other boats, a lookout boat, the Rós Áine,

and a Voe Vanguard vessel which is currently in Pembroke although it was not totally clear to me

what the relevance of these boats is.

Procedure to challenge a foreshore licence

22. The procedure for judicial review of a foreshore licence is set out in s. 21B of the 1933 Act

as follows:

“Contents of notice under s. 21A

21B. (a) A notice published under section 21A shall state that a person may question the

validity of any such determination by the Minister by way of an application for judicial review,

under Order 84 of the Rules of the Superior Courts (S.I. No. 15 of 1986).

(b) The notice shall identify where practical information on the review mechanism can be

found.

(c) A person shall not question the validity of a decision made or act done or purported to

be done by the Minister in relation to a relevant application otherwise than by way of an

application for judicial review under Order 84 of the Rules of the Superior Courts (S.I. No.

15 of 1986).

(d) The High Court shall not grant leave for judicial review under this section unless it is

satisfied that—

(i) the applicant has a sufficient interest in the matter which is the subject of the

application, or

(ii) the applicant—

(I) is a body or organisation other than a State authority, a public authority

or governmental body or agency the aims or objectives of which relate to

the promotion of environmental protection, and

(II) has, during the period of 12 months preceding the date of the

application, pursued those aims or objectives.

(e) A sufficient interest for the purposes of subparagraph (i) of paragraph (d) is not limited

to an interest in land or other financial interest.

(f) The Court, in determining either an application for leave for judicial review under this

section, or an application for judicial review on foot of such leave under this section, shall

act as expeditiously as possible consistent with the administration of justice.

(g) In paragraph (d), ‘State authority, a public authority or governmental body or agency’

means—

(i) a Minister of the Government;

(ii) the Commissioners of Public Works in Ireland;

(iii) a harbour authority within the meaning of the Harbours Act 1946;

(iv) a local authority within the meaning of the Local Government Act 2001;

(v) the Health Service Executive;

(vi) a person established—

(I) by or under any enactment (other than the Companies Acts),

(II) by any scheme administered by the Government, or

(III) under the Companies Acts, in pursuance of powers conferred by or

under another enactment, and financed wholly or partly, whether directly or

indirectly, by means of moneys provided, or loans made or guaranteed, by

a Minister of the Government or by subscription for shares held by or on

behalf of a Minister of the Government;

(viii) a company (within the meaning of the Companies Acts), a majority of the

shares in which are held by or on behalf of a Minister of the Government.”

23. The marginal or shoulder note to this section, “[c]ontents of notice under s. 21A”, is

alarmingly obscure and, while perhaps technically not part of the Act (s. 18(g) of the Interpretation

Act 2005), is the sort of misleading reference that parliamentary counsel rarely allow through.

Where such things happen they normally occur, as here, due to subsequent amendment rather than

original design. This type of note is best avoided and certainly somebody looking at the arrangement

of sections would not understand that the substantive judicial review procedure is to be found in a

section about the contents of a notice.

24. While the judicial review provisions of the 1933 Act appear to be somewhat inspired by those

for planning law generally, there are some differences, the rationale for which is not immediately

obvious. Two obvious immediate differences are that the test is arguable grounds rather than

substantial grounds and that there is no restriction on the right of appeal.

Jurisdiction to seek injunctive relief prior to the grant of leave to seek judicial review

25. While the applicants initially relied on O. 84, r. 20(8) RSC, that does not apply because it

relates to situations where the court is granting or has already granted leave to seek judicial review.

26. However, the question of whether the court can grant injunctive relief prior to the grant of

leave for judicial review has been clearly answered by the, if I may respectfully say so, clear and

convincing judgment of Kelly J. in Harding v. Cork County Council [2006] IEHC 80, [2006] 1 I.R.

294, [2006] 2 I.L.R.M. 392, [2006] 2 JIC 2802, particularly at paras. 14 to 16, 20 and 21. That

strong assertion of the entitlement to the court to provide an effective remedy even at the very

initial interim stage has the implication that jurisdiction to grant an injunction or stay prior to the

grant of leave can now be found (in the current renumbering of the rules) at O. 84, r. 26(1) RSC

and in the inherent jurisdiction of the court.

27. Harding is yet another illustration of the utter centrality of the right to an effective remedy

(traditionally referred to in Irish jurisprudence as the right of access to a court). The court must

have whatever jurisdiction is necessary to ensure that a proper remedy is available if any given

complaint is upheld, and that also implies a jurisdiction to arrange matters in the interim pending

determination of the merits so that the risk of injustice is minimised and the possibility of such a

remedy is preserved where possible. That applies anyway, doubly so under art. 13 of the ECHR, but

in the EU law context it is further reinforced by the right to an effective remedy under Article 47 of

the Charter and as reflected in numerous environmental and other directives. Paragraphs 170 to

173 of the Commission Notice on access to justice in environmental matters (2017/C 275/01) explain

the position:

“170. Interim measures – referred to as ‘injunctive relief’ in Article 9(4) of the Aarhus

Convention – allow a court to order that a contested decision or act not be

implemented or that some positive measure be taken before the court delivers its

final judgment. The aim is to avoid harm arising from a decision or act that might

ultimately turn out to be unlawful.

171. In Križan [Case C-416/10 Križan (Court of Justice of the European Union, 15th

January, 2013, ECLI:EU:C:2013:8, see in particular para. 109], which concerned a

permit for a landfill, the CJEU was asked whether the access to justice provisions of

what is now the Industrial Emissions Directive, 2010/75/EU, allowed for interim

measures (despite not specifically mentioning them). It stated that ‘the exercise of

the right to bring an action provided for by Article 15a of [the then] Directive

96/61/EC would not make possible effective prevention of that pollution if it were

impossible to prevent an installation which may have benefited from a permit

awarded in infringement of that directive from continuing to function pending a

definitive decision on the lawfulness of that permit. It follows that the guarantee of

effectiveness of the right to bring an action provided for in that Article 15a requires

that the members of the public concerned should have the right to ask the court or

competent independent and impartial body to order interim measures such as to

prevent that pollution, including, where necessary, by the temporary suspension of

the disputed permit’.

172. In Križan, the CJEU also recalled that the possibility of interim measures is a

general requirement of the EU legal order. In the absence of EU rules, and in line

with the principle of procedural autonomy, it is up to Member States to lay down the

detailed conditions for granting interim measures.

173. The CJEU itself has defined criteria for deciding on applications for interim

measures where it has jurisdiction itself. Orders it has made, including in the field

of EU environmental law, refer to the need for the CJEU to be presented with a prima

facie case, the urgency of the matter and the balance of interests.”

Test for a stay

28. In Okunade v. Minister for Justice & Ors [2012] IESC 49, [2012] 3 I.R. 152, [2013] 1 I.L.R.M.

1, [2012] 10 JIC 1602, at p. 193, Clarke J. set out the broad approach to the grant of stays in the

context of judicial review:

“[104] As to the overall test I am of the view, therefore, that in considering whether to grant

a stay or an interlocutory injunction in the context of judicial review proceedings the court

should apply the following considerations:-

(a) The court should first determine whether the applicant has established an

arguable case; if not the application must be refused, but if so then;

(b) The court should consider where the greatest risk of injustice would lie. But in

doing so the court should:-

(i) Give all appropriate weight to the orderly implementation of measures

which are prima facie valid;

(ii) Give such weight as may be appropriate (if any) to any public interest in

the orderly operation of the particular scheme in which the measure under

challenge was made; and

(iii) Give appropriate weight (if any) to any additional factors arising on the

facts of the individual case which would heighten the risk to the public

interest of the specific measure under challenge not being implemented

pending resolution of the proceedings;

but also

(iv) Give all due weight to the consequences for the applicant of being

required to comply with the measure under challenge in circumstances

where that measure may be found to be unlawful.

(c) In addition the court should, in those limited cases where it may be relevant,

have regard to whether damages are available and would be an adequate remedy

and also whether damages could be an adequate remedy arising from an

undertaking as to damages.

(d) In addition, and subject to the issues arising on the judicial review not involving

detailed investigation of fact or complex questions of law, the court can place all due

weight on the strength or weakness of the applicant's case.”

29. The discussion in Okunade takes place within the broader and well-established basic

framework for injunctive relief as set out in caselaw stemming from American Cyanamid v. Ethicon

Ltd. [1975] A.C. 396 (an approach followed in Campus Oil v. Minister for Industry (No. 2) [1983]

I.R. 88, [1984] I.L.R.M. 45), which while variously expressed, involves consideration of three main

issues, whether there is an arguable case to an appropriate standard, the adequacy of damages,

and the balance of convenience, as well as any other appropriate factors.

30. What Okunade particularly adds to this basic mix is a prominent acknowledgement, as a

factor to be considered, of the public interest in giving effect to decisions that are prima facie valid,

and a framing of the balance of “convenience” in a way that clearly brings out that it is not a

discretionary and subjective exercise but rather an endeavour to minimise the risk of injustice.

31. As regards prejudice to the beneficiary of or the maker of a decision challenged, it is

important to note that the degree of prejudice depends in a substantial way, although this is not the

only factor, on when the legality of a decision is first questioned. When a decision is made, it is of

course presumed to be lawful and valid from the moment it is adopted, but nonetheless in practical

terms it is subject to a zone of provisionality because the right to an effective remedy must in any

case allow a reasonable period, however defined, which may vary from legal context to legal context,

for that decision to be challenged. Only when the period so defined expires without a challenge does

a higher level of prejudice start to accrue to any given decision-maker or beneficiary of a decision.

That doesn’t of course mean that there can’t be at least some prejudice in at least some

circumstances if a stay is applied for in the context of a challenge brought within time. Some

processes are inherently urgent and the decision-making and judicial procedures need to take that

into account along with any other relevant factors.

32. Another issue relevant to balancing the weight of the factors to be considered under Okunade

is the possibility of damaging (and a fortiori irreversible) effects on the environment generally and

protected habitats in particular. At least in the latter context, the risk of damage may be inferred

as a possibility from any situation where there is a lack of scientific information or a prima facia

argument that there is such an absence (see Case C-441/17R European Commission v. Republic of

Poland (Court of Justice of the European Union, 20th November, 2017, ECLI:EU:C: 2017:877) at

para. 61):

“Consequently, given the prima facie lack of scientific information excluding beyond all

reasonable doubt that the active forest management operations at issue have damaging and

irreversible effects on the protected habitats of the Natura 2000 Puszcza Białowieska site

referred to in the Commission’s action, it must be held that the urgency of the interim

measures requested by the Commission has been established.”

33. As regards the question of an undertaking as to damages, as a question of pure domestic

law a court has a discretion in that regard: see Jennings v. An Bord Pleanála [2022] IEHC 16, [2022]

2 JIC 0701 (Unreported, High Court, 7th February, 2022), which dealt with the undertaking as a

matter of domestic law only and where Holland J. exercised the discretion not to require such an

undertaking without the necessity of considering EU law.

34. The position in European law would seem (on the basis of the consideration that can be

given to it at this preliminary stage) to be somewhat stronger having regard in particular to the

requirement of access to justice under the EIA and habitats directives and the Aarhus Convention

as incorporated into European law (see also Coll v. Donegal County Council [2007] IEHC 110, [2008]

1 I.L.R.M. 58, [2007] 3 JIC 2301 per Dunne J.). In any event, the first named notice party did not

at least at this stage of the proceedings strongly dispute that issue.

Application of the law to the facts

35. As noted above, the basic Okunade formula is not especially ground-breaking and is a slightly

more elaborate version of well-established previous formulations ultimately driving from American

Cyanamid.

36. As regards an arguable case, sometimes put as a fair question to be tried, that must be

read as including a substantial case where that is appropriate including where that is the standard

for the grant of leave (although this isn’t such a situation). I was satisfied on the basis of what I

had as of the date of the decision on the interim stage that this element was satisfied (and indeed I

subsequently granted leave as noted below).

37. As regards placing all due weight on the strength or weaknesses of an applicant’s case as

referred to in Okunade, this is something which a court has to approach with a great deal of caution

in any case and certainly isn’t necessary here. The difficulty with a court going beyond an

assessment of an applicant’s case as merely arguable (or at most substantial) is that to proceed to

an assessment of its strengths and weaknesses can far too easily turn into something which is

functionally indistinguishable from giving a provisional view on the ultimate outcome of the case.

That is often an unsatisfactory procedure not least from the point of view of justice being seen to be

done. For example, suppose the court says that a party’s case is just about arguable but fairly weak

– one has to ask whether that party would reasonably feel that the court is going to approach the

substantive hearing with the necessary openness of mind. Absolute openness of mind is not

necessary or even possible because all courts come to all questions with a pre-existing exposure to

legal precedents, principles, concepts, philosophies and policies. But somewhere between the

impossibility of suggesting that a court should have absolutely no prima facie views on the general

issues involved in any given case, and the normally dubious procedure whereby a court would

comment on the strengths and weaknesses of the case based only on a preliminary examination,

lies a zone of reasonableness whereby it might be understood that the court has a broad

jurisprudential approach, formed primarily by reference to positive law and decided cases, but

remains open to that being challenged or to its application to particular facts being contested. Should

judges be neutral? Yes of course, as between persons. But not as between values and ideas. The

latter would be a serious misunderstanding of the idea of neutrality.

38. In terms of the adequacy of damages, which is related to consequences for the applicants,

it is not so much direct consequences to the applicants that are in issue, but an allegation of

significant risk to objective environmental interests protected by domestic and European legislation.

Damages are unlikely to be an adequate remedy in any case where there is risk of injury to the

environment. Relatedly, an undertaking as to damages is not something that I would propose to

require either in general in an environmental context without that being specifically asked for and

argued for, or more specifically in the present case at the present time having regard to the matters

set out in this judgment.

39. As regards the least risk of injustice, or the balance of convenience, the fact that the

decision was challenged within three months from the date of its publication in Iris Oifigiúil and that

the first named notice party decided to partially implement the decision while it was still within the

zone of provisionality to which I have referred, is relevant. One can reasonably say that while there

is undoubtedly going to be financial prejudice to the first named notice party, that is somewhat

diluted where there is an element of voluntary acceptance of risk by immediately acting on a public

law decision, albeit presumed valid, without waiting to see if it will be challenged.

40. In any event, financial damage to an individual private law actor would normally, and would

in this case, have to yield to the objective community and public interest in avoiding the risk of

environmental damage which transcends the interests of individual litigants, and which in this case

is set out on affidavit by or on behalf of the applicants, in particular in the affidavit of Marie Louise

Heffernan, director of Aster Environmental Consultants Ltd.

41. At the same time there are certain factors that lean in favour of the first named notice party.

One has to give all appropriate weight to the implementation of a prima facia valid public law decision

although that has to be reconciled with the fact that the applicants have also established arguable

grounds on a prima facie basis and in particular in relation to the argument that the condition of the

licence agreement suggests that not all information was before the Minister when the licence was

granted.

42. It is also true in favour of the first named notice party that the application for a stay was

not sought at the earliest opportunity, that the applicants initiated the proceedings on the last day

of the three-month period as running from the date of notification, and that having instituted

proceedings they didn’t seek to move a stay application until the next list, although that in itself is

understandable, especially in the circumstances as outlined above.

43. It also appears that when they sought a stay on the first substantive mention date, that was

without clear and specific notice in advance to the opposing parties of an intention to do so on that

day, which may possibly have contributed to the State not appearing on that occasion; and that the

application for the stay was not made until after the works had already commenced. In a case which

concerns a clash of purely private law interests, those factors might have somewhat greater weight,

but I don’t think that they are totally disqualifying here given the fact that the proceedings engage

objective environmental interests going beyond the private law concerns of the applicants. Again

for the avoidance of doubt, any assessment of the balance involved can be, and no doubt will be,

reconsidered and looked at afresh following full submissions and exchange of affidavits.

44. Issues such as the orderly operation of the public law scheme concerned and factors

heightening the risk to the public interest are largely covered by the points already mentioned,

although the fact that the project concerned is one of major renewable energy-generating

infrastructure is an important factor which no doubt can be considered further when affidavit

evidence on behalf of the first named notice party is delivered. But nonetheless, even in the context

of green energy projects, there are still objective environmental requirements under the EIA and

habitats directives that must be complied with.

45. Overall, an assessment of all relevant factors favours the grant of an interim stay here, with

the risk to the environment in particular (even leaving aside other factors favouring the applicants)

outweighing such features of the case as tend to militate against a stay, as of the date of the order

for interim relief and on the basis of the material before the court at that time.

Terms of any stay

46. I did give consideration to the question of whether the stay could be nuanced in some way

or limited to works in the SAC, but having regard to the applicant’s expert evidence on affidavit I

didn’t think that is something that could realistically be done, at least on the basis of the material I

had as of the hearing.

47. The first named notice party requested a brief run-off period, and it seemed to me that that

was appropriate in this situation, so I allowed the first named notice party a 24-hour period until

16:00 on 9th May, 2023 to wind down the existing works and carry out any health and safety

measures, but not to carry out any new steps under the licence. There has to be some balance

between absolute principle on the one hand and practicality on the other, given the fact that an

application for a stay is being made mid-stream, which means that there must be some possibility

in an appropriate case (and this is such a case) of allowing the orderly boxing-off of some specific

works which are in hand at the precise time when the application for a stay is sought. The first

named notice party had intended to drill seven boreholes during the month of May and as of the

hearing was drilling number three, so insofar as that could be wound down within the 24-hour period

allowed it seemed to me that that was a reasonable balance between principle and practicality in

the circumstances. Perhaps I could be allowed to add that, while there are of course some situations

which call for an immediate downing of tools the moment an injunction is granted (for example,

when a deportee or extraditee is in a plane on the runway or in a car speeding towards the border),

some provision for a winding-down period that does not significantly damage any objective interests

also serves the practical function of minimising unnecessary satellite arguments created by brief

delays in communicating or actioning any order.

Order

48. For the foregoing reasons, the order made on 8th May, 2023 was that:

(i) there was a stay in terms of relief 3 in the statement of grounds but made under O.

84, r. 26(1) RSC and/or the inherent jurisdiction of the court;

(ii) the first named notice party would have until 16:00 on 9th May, 2023 to wind down

existing works and carry out any health and safety measures but not to carry out

any new steps under the licence;

(iii) an undertaking as to damages was not required at that stage;

(iv) the applicant was to issue a motion for an interlocutory stay by 16.00 on 9th May,

2023 and to furnish papers in draft form to the opposing parties by 14.00 on that

date as well as an order for short service;

(v) the matter was adjourned to Friday 12th May, 2023 at 11.00 to hear the motion to

admit the proceedings to the list on notice and the leave application ex parte and at

a minimum for mention of the interlocutory stay motion which was to be for hearing

if the parties agree that or the court considered that appropriate;

(vi) the applicants were to write to the CSSO immediately to inform them of the order;

and

(vii) costs were reserved.

49. I can also record that on 12th May, 2023, after a further listing attended by all parties,

additional orders were made as follows:

(i) the proceedings were admitted to the Commercial Planning & Environmental List

without objection, costs being reserved and certifying for two counsel;

(ii) time was extended if and insofar as that was legally necessary, without prejudice to

any objection that might be made in due course by the opposing parties;

(iii) leave was granted on standard terms, including costs being reserved, and certifying

for two counsel, on the basis of a proposed amended statement of grounds to be

filed (rectifying paragraph numbers of sub-grounds to make them continuous and

particularising to the extent possible the national and EU legal provisions specifically

relied on in core ground 9);

(iv) the return date for the substantive notice of motion was fixed for 19th June, 2023;

and

(v) the interlocutory stay was fixed for hearing on 23rd May, 2023 with the matter for

mention in the meantime on 17th May, 2023.