IEHC 154 ECLI:IE:HC:2023:154 AI generated

High Court dismisses judicial review applications against planning authority regarding land acquisition near Intel campus.

Case Number IEHC 154
Court / Authority
Jurisdiction Ireland (IE)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The High Court dismissed three judicial review applications filed by Thomas Reid against An Bord Pleanála concerning the planning authority's decision to allow Intel Ireland to acquire his adjacent farm. Reid argued that the planning authority failed to properly consider his long-standing family occupation of the land and the historical significance of his residence. The court rejected these claims, holding that the planning authority acted within its statutory powers and that Reid's arguments were either already addressed or raised too late for judicial review.

Legislator headnote

AI generated

Section 50 of the Planning and Development Act 2000; Section 50 of the Planning and Development Act 2000; A planning authority's decision to grant permission for development is not subject to judicial review where the decision was made in accordance with statutory requirements and the applicant's arguments were not reasonably available at the time of the decision.

Keywords

AI generated
judicial review dismissal planning and development act intel ireland limited an bord pleanala land acquisition dispute statutory powers procedural fairness

Cited Legislation

AI generated
Section 50 of the Planning and Development Act 2000, as amended
that the applicant will need to deal with is the proposition that s. 50B(2) of the 2000
Development Act 2000
IN THE MATTER OF SECTION 50 OF THE PLANNING AND DEVELOPMENT ACT 2000,

Cited Case Law

AI generated
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[2023] IEHC 154

THE HIGH COURT

JUDICIAL REVIEW

[2020 No. 54 JR]

IN THE MATTER OF SECTION 50 OF THE PLANNING AND DEVELOPMENT ACT 2000,

AS AMENDED

BETWEEN:

THOMAS REID

APPLICANT

AND

AN BORD PLEANÁLA

RESPONDENT

AND

INTEL IRELAND LIMITED

NOTICE PARTY

AND

THE HIGH COURT

JUDICIAL REVIEW

[2021 No. 61 JR]

IN A MATTER PURSUANT TO SECTION 50 OF THE PLANNING AND DEVELOPMENT

ACT 2000, AS AMENDED

BETWEEN

THOMAS REID

APPLICANT

AND

AN BORD PLEANÁLA,

IRELAND AND THE ATTORNEY GENERAL

RESPONDENTS

AND

INTEL IRELAND LIMITED

NOTICE PARTY

AND

THE HIGH COURT

JUDICIAL REVIEW

[2022 No. 1134 JR]

IN THE MATTER OF SECTION 50 OF THE PLANNING AND DEVELOPMENT ACT 2000,

AS AMENDED

BETWEEN

THOMAS REID

APPLICANT

AND

AN BORD PLEANÁLA

RESPONDENT

AND

INTEL IRELAND LIMITED

NOTICE PARTY

(No. 6)

JUDGMENT of Humphreys J. delivered on the 28th day of March, 2023

1. The applicant’s farm is located adjacent to the Intel campus in County Kildare. He

notes on affidavit that his residence, Hedsor House, was constructed around 1760.

His family have been in occupation of the lands since 1904. This is the ninth written

decision in relation to proceedings brought by the applicant either involving Intel or,

prior to that, a proposal to acquire the applicant’s lands. The present judgment deals

with applications in three judicial reviews brought by the applicant, which I shall

refer to as the 2020, 2021, and 2022 proceedings.

2. In Reid v. Industrial Development Agency [2013] IEHC 433, [2013] 6 JIC 1907

(Unreported, High Court, 19th June, 2013) Hedigan J. dismissed a challenge by the

applicant to the compulsory acquisition by the Industrial Development Agency (IDA)

of his house and lands. In Reid v. Industrial Development Agency [2015] IESC 82,

[2015] 4 I.R. 494, [2016] 1 I.L.R.M. 1, McKechnie J. for the Supreme Court, set

aside Hedigan J.’s decision and held that the IDA’s proposed acquisition was invalid.

3. On 5th October, 2017, the board granted the first permission relevant to the

proceedings for a development by Intel. The application in that case involved

environmental impact assessment (EIA).

4. A second relevant application for development was made on 1 st February, 2019

through normal planning procedures. Permission was granted by Kildare County

Council and the applicant appealed on 13th June, 2019 and made a request for an

oral hearing.

5. On 5th September, 2019, the board decided to refuse an oral hearing, and the

applicant was so notified on 6th September, 2019.

6. On 21st November, 2019, the board granted permission for the development. This

was challenged in the 2020 proceedings [2020 No. 54 JR].

7. In those proceedings, Chris Clarke, on behalf of the board, swore an affidavit on 5th

August, 2020, exhibiting the file, and swore a further affidavit on 4 th December, 2020

(an unsworn version having previously been served on 29th October, 2020) exhibiting

the minutes of the meeting that took the decision not to hold an oral hearing. The

minutes are an important document for an understanding of the matter because they

establish that the decision was taken by a board composed of two rather than three

members. As explained below, the quorum is normally three but there were

exceptions at the relevant time.

8. The board granted a third relevant permission on 30 th November, 2020 which was

for a modification to the 2017 and 2019 permissions. This third permission is

challenged in the 2021 proceedings [2021 No. 61 JR].

9. In Reid v. An Bord Pleanála (No. 1) [2021] IEHC 230, [2021] 4 JIC 1204,

(Unreported, High Court, 12th April, 2021), I excluded certain evidence prior to the

hearing of the 2020 proceedings.

10. In Reid v. An Bord Pleanála (No. 2) [2021] IEHC 362, [2021] 5 JIC 2705,

(Unreported, High Court, 27th May, 2021), (see Kieran Lynch (2021) 3 I.P.E.L.J,

138), I dismissed the 2020 proceedings.

11. In Reid v. An Bord Pleanála (No. 3) [2021] IEHC 593, [2021] 10 JIC 0606,

(Unreported, High Court, 6th October, 2021), I refused leave to appeal and made no

order as to costs.

12. In Reid v. An Bord Pleanála (No. 4) [2021] IEHC 678, [2021] 11 JIC 0202,

(Unreported, High Court, 2nd November, 2021), I confirmed the costs order after the

applicant sought to reopen it for the purpose of making additional arguments.

13. In Reid v. An Bord Pleanála [2022] IESCDET 39, the Supreme Court refused Leapfrog

leave to appeal.

14. In Reid v. An Bord Pleanála (No. 5) [2022] IEHC 687, [2022] 12 JIC 0902,

(Unreported, High Court, 9th December, 2022), I granted leave in the 2021

proceedings challenging the third relevant permission, on certain grounds.

15. The applicant says that in December, 2022 he became aware of the difficulty

regarding the absence of a quorum. On 21 st December, 2022, he brought a fresh

set of proceedings seeking to challenge the 2019 permission, the 2022 proceedings

[2022 No. 1134 JR]. He subsequently brought a motion to reopen the judgment in

the 2020 proceedings, which is essentially seeking the same relief from a different

and more appropriate vantage point.

The requirement for a quorum of three

16. Prior to a statutory amendment made in 2022, the board was required to sit with a

quorum of three members save where determined by resolution to the contrary.

Section 108 of the Planning and Development Act 2000 provided as follows at the

relevant time:

“108.— (1) Subject to subsection (1A) (inserted by section 41) a quorum for a

meeting of the Board shall be 3.

(1A) The Board may determine by resolution, if so requested by the chairperson (or

the deputy chairperson if the chairperson is not available or where the office of

chairperson is vacant) where he or she is of the opinion that it is necessary to ensure

the efficient discharge of the business of the Board, that the quorum for a meeting

of the Board, or, notwithstanding section 112(2), a division of the Board referred to

in section 112, should be 2.

(1B) The resolution referred to in subsection (1A) shall specify the functions of the

Board or division of the Board which may be performed in a meeting with a quorum

of 2 and the period of time during which the specified functions may be performed.

(1C) The chairperson or deputy chairperson shall not request a resolution of the

Board referred to in subsection (1A) for the purposes of any matter falling to be

determined by the Board or division of the Board under this Act in relation to—

(a) development that would materially contravene the relevant development

plan,

(b) strategic infrastructure development, or

(c) a development or class of development referred to in regulations made

under section 176.

(1D) If, in determining by vote a question at a meeting of the Board or a division of

the Board with a quorum of 2, the voting is equally divided, the matter that is the

subject of the vote shall be referred to a meeting of the Board with a quorum of 3

and section 111(4) shall apply in relation to the determination of the question.”

17. A resolution of 26th July, 2019 was made pursuant to sub-s. (1A). This was not

published, although the board says it would have been available on request. This

provided that the necessary quorum in respect of certain functions of the board

should be two, including a case where the board was dealing with “(p) Decision as

to whether or not an oral hearing shall be held (in the case of normal planning

appeals but not in the case of any matter relating to Strategic Infrastructure

Development, Local Authority projects or Compulsory Acquisition or where an

Environmental Impact Statement or a Natura Impact Statement has been submitted

with the case)”.

18. The applicant did not actually get sight of the resolution until quite recently, but the

board rightly calls this a “canard”, because (even leaving aside the fact that he didn’t

go looking for it) the applicant was on notice from the terms of sub-s. (1C)(c) that

a planning application subject to EIA (and therefore to which s. 176 of the 2000 Act

applied) could not be made the subject of the lower quorum. The applicant was also

aware at all material times that the impugned second permission was one where an

EIA report had been submitted. Even though the board disputed that this was strictly

required, the fact that an EIA report was (to the applicant’s knowledge from the

outset, as illustrated by it being referred to in the 2020 proceedings when initiated)

part of the application, was sufficient to put the applicant on notice of, and on inquiry

regarding, a potential issue in relation to a quorum from the date when he had reason

to believe that the number of members attending the actual meeting in question was

less than three. I would not fault the applicant for not investigating the quorum

issue at a time when there was no reason to suspect that there was any problem –

a party to litigation can’t be expected to have almost perfect knowledge of every

unlikely thing that might have occurred or to have clairvoyance of what may emerge.

So the fact that the applicant could have gone looking for the minutes earlier doesn’t

matter because he had no reason to suspect they would show illegality and hence

had no particular need to seek them. But one has to act when one gets solid reason

to suspect something is amiss. Such reason was supplied on 29th October, 2020

when the applicant was given the minutes of the meeting in question. He did not

need a copy of the resolution on that date to be on sufficient notice of the point from

that date onwards because he, personally or through his advisers, had actual or

constructive knowledge of the terms of the legislation. Had the applicant sought to

amend his pleadings at that point, or within 8 weeks of that date, that application

would have been granted virtually as of right. Even after the 8 weeks, the applicant

would still have had at least a puncher’s chance of bringing the point in by way of

amendment as long as the proceedings were still live (basing himself, presumably,

on lawyers’ oversight). But we are dealing now with a very different situation – an

attempt to reopen the final outcome of decided litigation. Lawyers’ oversight carries

little or no weight in that context.

19. Following recent turbulence in the board, and in particular the revelation that the

quorum provision had apparently been breached on a number of occasions, the law

has been amended to provide for a minimum quorum of three at all times. The

present matter involved one of those apparent breaches, and the main question is

what, if anything, the court should do about that breach now.

Issues

20. Five basic issues were raised in the set of applications with which I am now dealing,

as follows:

(i) whether to reopen the order in the 2020 proceedings;

(ii) costs of the leave application in the 2021 proceedings;

(iii) leave to appeal in the 2021 proceedings;

(iv) the application to amend the 2021 proceedings; and

(v) leave on notice in the 2022 proceedings.

Application to reopen the order in the 2020 proceedings

21. By notice of motion filed on 16th February, 2023, the applicant sought orders

reopening the 2020 proceedings and permitting an amendment to the statement of

grounds to raise a new issue regarding the lack of a quorum when the board decided

to refuse an oral hearing.

22. In submissions at the initial hearing of the motion on 8 th March, 2023, the applicant

complained about disclosure by the board and sought additional information which

essentially fell into three categories:

(i) the decision-making process generally;

(ii) the possibility that the board might have known of the quorum problem before

the 2020 proceedings were finalised; and

(iii) the possibility that the board was not aware of the problem until much later so

that it would be unrealistic to expect the applicant to have been so aware.

23. The first of these headings is an invitation to embark on an unfocused roving inquiry

into the whole process after the case has been dismissed. That is not normally an

appropriate procedure, and it is certainly not appropriate here.

24. I considered that the latter two points could be addressed by the board clarifying

when it knew of the problem, so I adjourned the matter to enable the board to deal

with that on affidavit and to allow the applicant to also file an affidavit.

25. I received further submissions in the light of the affidavits on 20th March, 2023 when

judgment was reserved.

26. There is no basis from the affidavits to suggest that the board was aware of the

problem during the hearing of the 2020 proceedings or prior to their finalisation. It

is clear that the issue came to light around July, 2022 following the receipt of a media

inquiry from Mr Roman Shortall of The Ditch website (www.ontheditch.com) on 29th

June, 2022.

Merits of the application to reopen

27. The applicant’s grounding affidavit in the 2022 proceedings also represents his

position on the application to reopen the 2020 proceedings. That position is as

follows:

“For reasons outside of my control, I was not aware until 16 December 2022 that

the Board, by allowing my application for an oral hearing to be determined by a 2

person board, had acted contrary to the law.”

28. The real problem with this submission is that it comes nowhere near reaching the

level of exceptional breach of constitutional rights envisaged in the caselaw in

order to enable a final order of the court to be reopened: see Greendale

Developments Ltd No. 3 [2000] 2 I.R. 514, [2001] 1 I.L.R.M 161, [2000] WJSC-SC

3223, [1999] 12 JIC 0902, Abbeydrive Developments Ltd. v. Kildare County

Council [2010] IESC 8, [2010] 2 I.R. 397, Student Transport Scheme Limited v.

Minister for Education and Skills [2021] IESC 35, [2021] 6 JIC 1401 (Unreported,

Supreme Court, 14th June, 2021), Lavery v. D.P.P. (No. 3) [2018] IEHC 185,

[2018] 3 JIC 1310 (Unreported, High Court, 13th March, 2018). There is no

evidence of improper withholding of information by the board. The evidence

implies internal failure of procedures and human error, but that by no means

equates to proof of the sort of intentional wrongdoing that would allow a court to

revisit a final order.

29. It is also not without relevance that the applicant himself was threatening litigation

as of June, 2022, according to an article by Mr Mick Clifford in the Irish Examiner,

which envisaged that the applicant would be seeking to reopen the 2020 proceedings

on foot of revelations concerning the board (“Farmer wants Intel permission revisited

after Paul Hyde allegations”, 11th June, 2022). While the applicant’s solicitor has

perfectly reasonably explained why nothing happened on foot of that threat at the

time, or at all, until December, 2022, it does not follow that the applicant should be

permitted to reopen a final order merely because he has not acted unreasonably.

An applicant has to do more than that bare minimum in order to obtain an

extraordinary order such as sought here. It seems to me that it cannot be said here

that the applicant’s constitutional rights have been fundamentally infringed in such

a way to make it unjust that the 2020 proceedings should remain dismissed.

Essentially all that has happened is that a technicality has come to light which didn’t

occur to the applicant or his advisers during the previous proceedings. The fact that

parties may miss out on making points that didn’t occur to them during proceedings

is just a consequence of the necessary balance inherent in the orderly process of

dispute resolution as between flexibility to raise points during proceedings with a

strong degree of finality thereafter.

30. As noted above, while oversight or omission is a legitimate basis for allowing an

amendment in the context of currently live proceedings, subject to arguability, lack

of irremediable prejudice and the interests of justice (that is what happened in

Keegan v. Garda Síochána Ombudsman Commission [2012] IESC 29, [2012] 2 IR

570, [2012] 5 JIC 0103), it is, on its own, certainly nowhere near enough to allow

the re-opening of a final order of the court.

Costs of the leave hearing in the 2021 proceedings

31. While the applicant initially applied for the costs of the leave hearing in the 2021

proceedings as against both opposing parties, after some discussion the parties

agreed to an order reserving costs with liberty to apply for the costs, including prior

to the determination of proceedings, on foot of a written legal submission. If the

applicant decides to so apply, he needs to deal inter alia with the statutory

architecture, but the parties may add any other issues they wish. The hypothesis

that the applicant will need to deal with is the proposition that s. 50B(2) of the 2000

Act, namely the default no order as to costs, must apply to the costs of interlocutory

relief as well. It is notable that “relief” includes interlocutory relief, as appears from

sub-s. (1)(c). A default no order as to costs of interlocutory matters makes sense

because if the costs protection rule does not apply to interlocutory costs, then an

applicant could easily be saddled with prohibitive costs arising from interlocutory

matters alone, which would defeat the statutory purpose and contravene the Aarhus

Convention and EU law. On the other hand, a conforming interpretation is very much

available.

32. On such an interpretation, the literal effect of sub-s. (2A) would be that apart from

perhaps limited cases like stays where interlocutory relief was obtained directly as a

result of the acts or omissions of an opposing party, the costs of interlocutory

applications should be considered as an adjunct to the substantive relief and thus

should await the determination of whether an applicant is entitled to any final relief

before disposing of such costs. Generally, costs of interlocutory matters don’t arise

directly and as such from acts of the respondents and notice parties. Rather they

arise indirectly as a consequence of the need to litigate the underlying issue. Hence

the need to first establish whether the applicant gets any substantive relief that is

attributable to such acts, before returning to the (on this hypothesis, reserved) costs

of interlocutory matters which would follow as an adjunct. That is consistent with

the discretionary nature of sub-s. (2A): “the costs…may”. Exercise of such a

discretion requires the court to retain seisin of the costs of such interlocutory matters

as of the time at which it is determined whether the applicant is entitled to

substantive relief.

33. There could be a wide range of potential situations calling for interlocutory

determination, including in no particular order:

(i) setting aside leave;

(ii) leave on notice;

(iii) admission to the list;

(iv) remittal;

(v) leave to appeal;

(vi) reference to the CJEU;

(vii) costs issues;

(viii) issues regarding the form of orders;

(ix) costs protection;

(x) contested directions;

(xi) amendment of pleadings;

(xii) liberty to defend proceedings;

(xiii) stays;

(xiv) SLAPP-type satellite issues;

(xv) directions regarding disclosure or discovery;

(xvi) cross-examination;

(xvii) extension of time; or

(xviii) amendment of or reopening of orders.

34. Any rule as to the interaction between sub-ss. (1), (2), and (2A) would have to make

sense as applied to all the different contexts that could arise, and the general default

of reserving interim and interlocutory costs would at least be consistent even if it

might differ in certain respects from other litigation. But all that awaits argument

and decision at a later point or in another case.

Leave to appeal in the 2021 proceedings

35. The law on leave to appeal has recently been summarised by Barniville J. (as he then

was) in Cork Harbour Alliance for a Safe Environment v. An Bord Pleanála [2022]

IEHC 231, [2022] 4 JIC 2601 (Unreported, High Court, 26 th April, 2022) at para. 32

and by Holland J. in Monkstown Road Residents Association v. An Bord Pleanála

[2023] IEHC 9, [2023] 1 JIC 1907 (Unreported, High Court, 19 th January, 2023).

36. The applicant requests certification of the following question:

“If the Board’s Inspector (and the Board in adopting the Inspector’s report), in

carrying out screening for appropriate assessment are of the view that it would have

been ‘useful’ if more detail had been presented, and such information is not sought

by the Board,

(a) Has the screening assessment been conducted on the basis of best scientific

knowledge within the meaning of section 177U(1) PDA 2000?

(b) Where the information in question has been seen and reported on by the

Developer’s Consultants but not submitted as part of the planning

application, is such information to be regarded as ‘not reasonably available’

for the purposes of People Over Wind v. An Bord Pleanála [2015] IECA 272?

(c) Is the requirement that the risk of significant effects on a European site be

excluded on the basis of objective information satisfied?

(d) Does the fact that the Inspector expressed that view create a doubt as to

effects on a European site, or demonstrate that a reasonable expert in the

position of the board would have seen such a doubt on the face of the

materials, for the purposes of the test identified in Reid v. An Bord Pleanála

(No. 2) [2021] IEHC 362?”

37. The preamble establishes that the point is totally fact-specific. The question,

therefore, does not warrant further consideration, as it clearly cannot meet the

statutory test. It is also relevant that, during the process itself, the applicant did

not seek the further detail on which the whole question hinges. The applicant

characterises the procedure that was adopted here as involving the withholding of

material and injects a lot of drama into the question. This sounds most impressive,

but the case does not raise any such issues. There is no “practice of with-holding …

material” either as alleged in submissions or at all. All that happened was that in

this case it was not considered necessary to seek further detail from the developer

because the board was satisfied in any event that impacts on air quality would “likely

be minimal and confined to a very localised area around the site” (para. 7.4.3 of the

inspector’s report). The point is totally fact-specific.

38. The applicant submits that “ … the question of whether the evidential requirements

on an Applicant of the Reid No 1 test are met where an issue is raised by the Board’s

Inspector is of widespread importance for many judicial reviews”. But the premise

of that is totally incorrect. The board’s inspector did not “raise” any issue. On the

contrary, it was clearly considered that there was no issue which would have required

the furnishing of further information.

39. Even if the applicant had raised a question that properly arises on the facts, he falls

at the first stumbling block, because as put by the board, “[q]uestions related to the

application of existing principles to an individual case do not, in general, meet the

threshold for certification”.

Application to amend the 2021 proceedings

40. The applicant sought the following amendment to the 2021 proceedings:

“To amend Ground E24 by the addition of the words underlined so that it

reads as follows:

‘No EIA screening was conducted for the impugned development. The First

Respondent’s Inspector excluded the need for an EIA ‘at preliminary

examination’ without making an EIA screening determination. The Board

Decision and Order is silent on the issue of EIA even though the scale of the

development that is being extended is such that it meets the threshold for

more than one category in Schedule 5 Part 2 of the Planning and

Development Regulations 2001, as amended namely 6(d), Storage facilities

for petrochemical and chemical products, where such facilities are storage

to which the provisions of Articles 9, 11 and 13 of Council Directive

96/82/EC1 apply; 10(a) Industrial Estate Development and 10(b) Urban

Development, and requires screening pursuant to paragraphs 6(c), 10 and

13 of Annex II of the EIA Directive’.” [I note that the clause regarding

storage facilities should have been underlined in full]

41. The applicant has already been through a number of iterations of the statement of

grounds:

(i) the original statement was filed on 29th January, 2021;

(ii) I allowed an amendment on 24th March, 2022;

(iii) I allowed a further amendment on 10th October, 2022; and

(iv) the leave judgment of 9th December, 2022 permitted further amendments.

42. He now seeks to be allowed a fifth iteration.

43. The notice of motion seeks relief pursuant to O. 28, rr. 1 or 6 RSC, but in fact the

appropriate legal basis is O. 84, r. 23(2) RSC. I will treat the application as being

made under the latter provision.

44. Insofar as the opposing parties complain that the amendment is made “out of time”,

this is a complete misconception. The eight-week time limit for the institution of

planning judicial review (or the three-month limit for other judicial reviews) applies

to the bringing of the proceedings in the first place. It does not apply to

amendments. Indeed the rules would not make sense on such a basis because they

expressly authorise the amendment of proceedings at any time after the grant of

leave, and it is self-evident that with the possible exception of an amendment sought

when a judicial review application is before the court for the very first time, any

statutory period for the initiation of proceedings would have long expired by the time

any such later amendment fell to be considered.

45. While there are of course virtuous exceptions, opposing parties generally tend

towards being incapable of allowing themselves to acknowledge a distinction

between the procedure applicable to bringing proceedings in the first place and that

applicable to seeking amendments. Unfortunately the present case is an example of

that.

46. As held in B.W. v. Refugee Appeals Tribunal [2017] IECA 296, [2018] 2 I.L.R.M. 56,

the three limbs of the Keegan test are arguability, explanation and the absence of

irremediable prejudice. These are viewed in the light of the overall test of the

interests of justice.

47. While it is true that in some of the caselaw, what is described as an “entirely new

case” may call for a higher degree of good and sufficient reason, it is important to

note that the concept of an “entirely new case” is not a technical term, but essentially

a rhetorical move, or perhaps more benignly, a way of saying that in the particular

circumstances the interests of justice do not favour an amendment without an

elevated level of good and sufficient reason. However, on any view there is no way

in which the addition of one further limb of EIA applicability to a case where two

other limbs of EIA applicability have been in the pleadings from the outset could be

described as even remotely approaching a new case. And to go further and call that

an “entirely” new case would be to drain language and logic of meaning, and to

substitute in their place an exercise in mere adversarial vigour. At worst, what is

proposed is the modest extension of a broad point (the point that EIA screening was

required) that was always in the pleadings.

48. It seems appropriate therefore to turn to the three limbs of the B.W. test.

Explanation

49. As regards explanation, it is true that the affidavit of the applicant of 21 st December,

2022 didn’t explain why the point was not included earlier, contrary to the direction

I gave when granting leave. However, a further affidavit has since been filed by the

applicant’s solicitor basically saying that the point did not occur to counsel originally.

While that seems stark, it is all the explanation that could ever be offered for an

oversight, and something similar was accepted in Keegan v. Garda Síochána

Ombudsman Commission [2012] IESC 29, [2012] 2 I.R. 570. Insofar as the

applicant is alleged not to have explained the delay in raising the issue, the same

point applies. By definition, error or oversight cannot normally be explained much

further. In a typical situation (which is what happened here), an applicant’s lawyers

overlook the point initially but seek to include it in the proceedings once they become

aware of it and while the proceedings are still live and an amendment can be made

without derailing matters. The issue is then normally focused on arguability,

prejudice and the interests of justice. But as far as explanations go, it seems to me

that, much as in Keegan, lawyers’ oversight does provide a sufficient explanation.

Substantial grounds

50. As regards arguability, or substantial grounds in the planning context, issue is joined

on whether there are adequate grounds for the amendment. The classification

adopted in Reid (No. 5) for this purpose was essentially as between:

(i) points that had already been clarified;

(ii) points that were capable of being clarified within the limited confines of a

leave application; and

(iii) all other points.

51. Having considered the submissions, this seems to me to be a category (iii) point.

The meaning of class 6(d) in Schedule 5, Part 2 of the Planning and Development Regulations

2001 has not been decided already, and is not readily clarifiable in the limited context of an

application to amend the pleadings. Thus, I consider it substantial for current purposes but

obviously that is without prejudice to any defence that may be maintained at the full hearing.

Irremediable prejudice

52. As far as irremediable prejudice is concerned, it is true that the applicant has already

amended the statement of grounds, but that is not disqualifying generally and

certainly not here (indeed the power to amend even includes adding back something

deleted by a previous amendment: per O’Donnell J. in O’Neill v. Applebe [2014] IESC

31, [2014] 4 JIC 1003 (Unreported, Supreme Court, 10th April, 2014) at para. 14).

Legally cognisable prejudice does not include having to deal with a potentially

winning point. Thus, merely because the amendment would “include a distinct new

legal ground”, the opposing parties are not, as submitted, irremediably or improperly

prejudiced. It is true that the additional affidavit evidence may be required, which

might be a problem if such a requirement would derail an existing hearing date that

had been fixed. That would be prejudice – but there is no such date fixed here as

we are not at that stage yet. Opposition papers generally have yet to be filed. That

is in a context where Intel did not particularly rush the proceedings along and did

not pursue a proposal to admit the case to the Commercial List until quite a long

time after first suggesting it (and after initially withdrawing that suggestion).

Interests of justice

53. Considering all the circumstances here, it seems to me that it is in the interests of

justice to permit the proposed amendment. Doing so allows the applicant to make

his best case and does not impose any irremediable or unfair consequences on the

opposing parties. Indeed, refusing the amendment would simply confer on them a

windfall benefit arising from the applicant’s lawyers’ oversight at the stage of

initiating the proceedings. That would be a disproportionate response.

Leave on notice in the 2022 proceedings

54. As a general rule, where an applicant has already challenged a decision and had her

proceedings dismissed, she cannot simply ignore that and bring fresh proceedings

challenging the same decision. The correct procedure is to seek to reopen the earlier

order.

55. While the 2022 proceedings in form challenge the oral hearing decision as well as

the permission, in substance that is a mechanism to challenge the permission. In

substance and in reality, the 2022 proceedings cut across the order in the 2020 case,

so the appropriate way for an applicant to proceed in such circumstances would be

to seek to vacate the existing order in the earlier proceedings rather than to act as

if that order was not there.

56. Thus, leave in the 2022 proceedings must be refused in any case, even if the

applicant here had a point, which he doesn’t.

57. Even if hypothetically, I am incorrect about that and if a lesser test of extension of

time was applicable, rather than the Greendale test for reopening the order, it seems

to me that the applicant has not met that either. Especially in a commercial context

or where third party rights are at stake, or both (things can be a little more flexible

for a purely human rights case), it is appropriate that the court should be reasonably

strict with the question of extension of time. That said, one doesn’t have to act

within the initial 8 weeks if the information required to make the point isn’t

reasonably available initially. But as explained above, the point was available to the

applicant as of 29th October, 2020. Eight weeks from then expired in December,

2020. The notion of wandering into court in December, 2022 seeking leave on this

basis is a complete non-starter. It would be unfair to Intel to allow their permission

to be put in question at such a remove.

Order

58. The order made on 8th March, 2023 was:

(i) in the 2020 case, that:

(a) the board have liberty to file a further affidavit and

(b) the matter be listed for further submission on 13th March, 2023;

(ii) in the 2021 case, that:

(a) costs of the leave hearing be reserved with liberty to the applicant to

apply for such costs, including in advance of the determination of

the proceedings, on the basis of a written legal submission that

would inter alia address the statutory architecture in accordance

with the judgment of the court, and

(b) there be liberty to the applicant to file a further affidavit regarding

amendment of pleadings by 10th March, 2023; and

(iii) in the 2022 proceedings, that:

(a) additional affidavits in the 2020 proceedings may be relied on in the

2022 proceedings and

(b) the matter be further heard on 13th March, 2023.

59. The order now being made is as follows:

(i) in the 2020 proceedings, that:

(a) the applicant’s motion be dismissed; and

(b) unless submissions to the contrary are received within 7 days of this

judgment (exclusive of vacations), the foregoing order be perfected on

the basis of there being no order as to costs;

(ii) in the 2021 proceedings that:

(a) leave to appeal on foot of the leave judgment be refused;

(b) the applicant have liberty to file a further amended statement of

grounds incorporating the amendment sought, to be filed within 7

days of this judgment (exclusive of vacations);

(c) the matter be listed for mention on a date to be notified by the List

Registrar; and

(d) unless submissions to the contrary are received within 7 days of this

judgment (exclusive of vacations), the foregoing order be perfected

on the basis of costs of the amendment application being reserved and

there being no order as to costs of the leave to appeal application; and

(iii) in the 2022 proceedings, that:

(a) leave to seek judicial review be refused; and

(b) unless submissions to the contrary are received within 7 days of this

judgment (exclusive of vacations), the foregoing order be perfected on

the basis of there being no order as to costs.