Legislator Case Law & Legislation
IEHC 141 ECLI:IE:HC:2019:141 AI generated

High Court awards costs to applicant where respondent's unilateral decision to withdraw contract renders proceedings moot.

Case Number IEHC 141
Court / Authority
Jurisdiction Ireland (IE)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The High Court awarded costs to the applicant because the respondent's unilateral decision to withdraw the contract rendered the proceedings moot. The respondent argued that the litigation caused a stay preventing contract award within the tender timeline, but the court found the withdrawal was a discretionary choice within the respondent's control. Consequently, the court held that the respondent should bear the costs of the now-moot proceedings.

Legislator headnote

AI generated

Regulations 2010; Order 84A: Where a respondent unilaterally withdraws a contract award following litigation, rendering proceedings moot, the respondent bears the applicant's costs as the withdrawal was a discretionary act within their control.

Keywords

AI generated
public procurement moot proceedings costs award unilateral withdrawal tender process contract award High Court

Cited Legislation

AI generated
European Communities (Public Authorities' Contracts) (Review Procedures) Regulations 2010
Order 84A of the Rules of the Superior Courts

Cited Case Law

AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[2019] IEHC 141

THE HIGH COURT

2018 No. 302 JR

IN THE MATTER OF THE REVIEW OF THE AWARD OF A PUBLIC CONTRACT PURSUANT TO THE EUROPEAN COMMUNITIES

(PUBLIC AUTHORITIES’ CONTRACTS) (REVIEW PROCEDURES) REGULATIONS 2010 (AS AMENDED) AND ORDER 84A OF THE

RULES OF THE SUPERIOR COURTS (AS AMENDED)

Between:

KPW BUSINESS FORMS LIMITED

T/A KPW PRINT MANAGEMENT

Applicant

– and –

STATE EXAMINATIONS COMMISSION

Respondent

JUDGMENT of Mr Justice Max Barrett delivered on 5th March, 2019.

1. This is an application for costs made in now moot proceedings concerning a competition for the award of a contract relating to the

operation of Ireland’s second-level examinations. Following the commencement of these proceedings, the SEC, consistent with the

RFT, took the decision not to award that contract. So the proceedings became moot because the SEC unilaterally decided not to

award the contract. As to the rationale for this last decision, SEC’s CEO has averred that “[T]hese Proceedings…brought an

automatic stay on the procurement process. That stay in place the Respondent was unable to award the…contract to the

successful bidder. That stay might have been challenged, but that…would have taken time, and…would not have allowed time

enough to implement the…[proposed] system in 2018….Moreover, there was no certainty that the stay would be lifted…or that [a]

…decision to lift… would go without appeal”.

2. In determining this application, the court brings to bear various of the precepts identified, by reference to applicable Supreme

Court case-law, in MKIA v. IPAT [2018] IEHC 134:

(1) Is there an event to which the general rule as to costs should be applied? Yes, being the SEC’s unilateral decision not

to award the contract, rendering these proceedings moot.

(2) Is the event caused by the applicant’s proceedings? Yes. Were it not for these proceedings the event would not have

occurred.

(3) Are the proceedings moot due to a factor outside the control of either party? (4) Are the proceedings moot due to a

factor which is within the control of one party but which has no causal nexus with the proceedings? No to both. The

proceedings are moot due to the unilateral decision of the SEC not to award the contract (a) in circumstances where it

could have arrived at an alternative decision (it could have come to court, albeit that it was free also to take the decision

that it did), and (b) in the context of a tendering process, the relatively constrained timeframe of which was entirely of

the SEC’s design.

(5) Are the proceedings moot due to a factor within the control of one party that does have a causal nexus with the

proceedings? Yes, for the reason offered in answer to (3) and (4).

3. Having regard to the foregoing, the court will make an order of costs in favour of KPW.