High Court awards defendants costs from offer date, deducts hypothetical engineer fees for alternative rent claim.

Case Number IEHC 228
Court / Authority
Jurisdiction Ireland (IE)
Decision Date
Outcome Partially Allowed

Legislator summary

AI generated

The High Court ruled on costs following a principal judgment ordering specific performance of a building agreement. Plaintiffs claimed damages for repairs and alternative rent, while defendants offered to settle the rent issue on February 18, 2016. The court awarded defendants costs from that date but deducted a hypothetical sum for the plaintiffs' engineer to account for the offer.

Legislator headnote

AI generated

O 99, r 1 A (1) of the Rules of the Superior Courts; where a party makes a settlement offer, costs are generally awarded from the date of the offer, subject to deductions for hypothetical costs incurred by the offeree in response to that offer.

Keywords

AI generated
costs of proceedings settlement offer specific performance alternative accommodation hypothetical costs engineer fees High Court Ireland

Cited Legislation

AI generated
O 99, r 1 A (1) of the Rules of the Superior Courts
All of this is recognised by O 99, r 1 A (1) of the Rules of the Superior Courts.

Cited Case Law

AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[2018] IEHC 228

THE HIGH COURT

[RECORD NO. 2011 7987 P]

BETWEEN

SHANE AND ANTOINETTE O’REILLY

PLAINTIFFS

AND

SEAMUS NEVILLE, LIAM NEVILLE, COLM NEVILLE, ANTHONY NEVILLE, BRENDAN NEVILLE AND WILLIAM NEVIN AND SONS

CONSTRUCTION, TRADING AS THE NEVILLE DEVELOPMENT PARTNERSHIP

DEFENDANTS

COSTS RULING of Mr Justice Donald Binchy delivered on the 18th day of January, 2018

1. On 31st July, 2017, I handed down judgment (the “principal judgment”) in these proceedings. In summary, I made an order for

specific performance, in favour of the plaintiffs of a building agreement entered into between the parties on 30th March, 2005 (the

“building agreement”), and I also ordered that the defendants pay the plaintiffs the cost of renting alternative accommodation since

they vacated, in August, 2010, the dwellinghouse constructed for them by the defendants pursuant to the building agreement. I left

over the issue of costs pending submissions from the parties which I heard on 13th December, 2017.

2. In the proceedings, the plaintiffs claimed rescission of the building agreement, together with an order for repayment to the

plaintiffs of the contract price provided for therein and paid to the defendants by the plaintiffs. In the alternative, the plaintiffs

claimed damages for breach of contract, negligence and breach of duty. At the conclusion of the hearing, the plaintiffs abandoned

their claim for rescission of contract and instead sought damages for breach of contract comprising special damages of €97,000, being

the estimated cost of repairs required to be undertaken to the dwellinghouse, special damages in respect of the cost of renting

alternative accommodation (which at the conclusion of the trial amounted to of the order of €75,000) and general damages in respect

of the adverse impact upon the lives of the plaintiffs caused by the defects in the dwellinghouse. By reference to the decision of this

court in the case of Mitchell and Anor v. Mulvey Developments Ltd & Ors [2014] IEHC 37, counsel for the plaintiffs invited the Court

to measure general damages at the rate of €10,000 for each year since the plaintiffs were required to leave the dwellinghouse. In the

event, I acceded to submissions made on behalf of the defendants that the appropriate order should be one of specific performance,

thereby eliminating the amount claimed for cost of repairs. I made no order in respect of the general damages claimed. And, as

mentioned above, I did make an order requiring the defendants to discharge all of the costs incurred by the plaintiffs, since they left

the dwellinghouse, in renting alternative accommodation, pending the carrying out works of repairs by the defendants in the manner

directed in the principal judgment.

3. As regards the costs of the proceedings, it is submitted on behalf of the plaintiffs that in obtaining an order for specific

performance of the building agreement, they have succeeded in the “event” in the proceedings and that, accordingly, they are

entitled to an order for the costs incurred by them in obtaining this order in accordance with the general principle that costs follow

the event. It is submitted that there is no reason to depart from the general rule. Counsel for the plaintiffs relies upon the decision of

the Supreme Court in Dunne v. Minister for the Environment [2007] IESC 60. Counsel for the plaintiffs further submitted that this is

not a case in which the Court should depart from the general rule that costs follow the event for reasons such as those articulated

by Clarke J. in Veolia Water UK PLC v. Fingal County Council (No 2) [2006] IEHC 240. It was further submitted by counsel for the

plaintiffs that the issues that gave rise to the court departing from the general rule in Veolia were complex issues dealt with at

interlocutory hearings that added substantially to the costs of those proceedings, and that no such issues arise in this case.

4. On behalf of the defendants, it is submitted that this was a complex case, that it is necessary for the court to analyse the “event”

and in particular that it is necessary for the court to take into account the various opportunities afforded to the plaintiffs, by the

defendants, to resolve the dispute. In this regard, counsel refers to the following: -

(1) An offer made in writing by Mr Seamus Neville, on 13th July, 2010, to address the issues raised by the plaintiffs. The

defendants suggested starting remedial works in August 2010, but at this point the plaintiffs decided to instruct a new

consulting engineer to advise them, their previous engineer having advised them that further investigations into the state

of the dwellinghouse were required . So they did not respond to the defendants’ offer, and instead instructed Mr Declan

Gibbons, Consulting Engineer to prepare a report on the state of the dwellinghouse. Mr Gibbons presented his report to

the defendants in late 2010.

(2) The defendants then obtained a report from a consulting engineer of their own, a Mr Paul Forde, following which the

defendants made an offer to carry out the works identified by Mr Forde as being necessary to remedy the defects in the

dwellinghouse. This was in April, 2011. Mr Forde’s report did not specifically address the problem of mould in the attic

which was a key issue for the plaintiffs, and their consulting engineer. There was no response to this offer.

(3) An offer made in writing on 5th April, 2012, by the solicitors for the defendants to the solicitors for the plaintiff. I

quoted an extract from this letter in the principal judgment which bears repeating here:-

“…we confirm that our clients are prepared without admission of liability to carry out all of the works recommended

to be carried out in the report of DBFL Consulting Engineers together with such other works which your clients may

reasonably require to have carried out. Our clients have made many attempts to carry out repair works over the

last few years but your clients have failed, refused or neglected to make facilities available for this purpose. Should

your clients again refuse facilities to our clients to carry out the works, this letter will be used during the course of

the hearing of the proceedings as part of our clients’ defence and with a view to fixing your clients’ with the costs

of proceedings….

We will be obliged if you will be kind enough to confirm that facilities will now be made available to our clients to

carry out the recommended works. Following this your clients will be fully entitled, if they consider it necessary, to

pursue their proceedings with our clients in relation to any other issues in respect of which they consider our clients

have a liability.”

An open response was not delivered to this offer on behalf of the plaintiffs until 23rd March, 2015, possibly because of

settlement discussions in the intervening period. In any case, the offer was rejected.

(4) The offer made in the preceding paragraph was repeated defendants in their defence delivered on 25th October,

2012. There was no reply delivered to the defence and no correspondence in relation to this offer.

(5) An offer from the defendants’ solicitors to the plaintiff’s solicitors by letter dated 18th February, 2016, and rejected

by the solicitors for the defendants on 2nd March, 2016. This letter, which is quoted almost in full in the principal

judgment, set out a comprehensive mechanism for the objective identification of defects in the dwellinghouse as well as

the measures required to address those defects, and also merits repetition here : “As a perfectly reasonable manner in

which to progress the case between now and November, 2016, our clients hereby offer the following:-

(1) Our clients’ architect (Mr. Pat Halley) will liaise with your clients’ engineer (Mr. Declan Gibbons) to discuss and, if

possible, agree on the condition in which the plaintiffs’ house should be (to include position of vents, damp proofing,

fire proofing etc).

(2) If no agreement can be reached, both Mr. Halley and Mr. Gibbons will provide their respective views as to an

independent expert, acting as expert and not arbitrator or adjudicator, who will decide on what the condition should

be, and whose decision will be final.

(3) When there is agreement or determination on the final condition, Mr. Halley and Mr. Gibbons will liaise and if

possible, agree a specification for the works required to meet the agreed or determined condition.

(4) If no agreement can be reached, both Mr. Halley and Mr. Gibbons will provide their respective views to an

independent expert, acting as expert and not arbitrator or adjudicator, who will decide on what the specification

should be, and whose decision will be final.

(5) Our clients will carry out the required works, according to the agreed or determined specification.

(6) Mr. Halley and Mr. Gibbons will have equal rights to supervise and inspect work as it is ongoing and, in the event

of an issue arising, the person who believes there to be an issue will liaise with the other and discuss, and if

possible agree, a solution.

(7) If no agreed solution to a perceived problem arising during the course of the works can be found or reached,

both Mr. Halley and Mr. Gibbons will provide their respective views to an independent expert, acting as expert and

not as arbitrator or adjudicator, who will decide on what the solution should be, and whose decision will be final.

(8) When the works are claimed to be complete, Mr. Halley and Mr. Gibbons will be invited to inspect the works, and

when both are satisfied that it is appropriate, the independent expert will be invited to inspect and certify the

works as complete and satisfying the specification, and his certificate shall be final.

(9) If at completion stage there is a difference of opinion between Mr. Halley and Mr. Gibbons, the subject matter of

such difference will be referred to the independent expert for his expert opinion, which shall be final.

By agreeing to this proposal, your clients can be assured that all works will be independently approved and their house

restored to the condition in which it should be.

When the works are complete, there may be other issues remaining in the case which can be litigated over a much

shorter timeframe.”

5. Counsel for the defendants argues that throughout this litigation, the defendants showed a willingness to engage with the plaintiffs

to resolve the matters in dispute, but this was not reciprocated by the plaintiffs. No reasonable person could disagree with this

submission, While in the principal decision I was critical of the workmanship of the defendants that gave rise to the defects in the

dwellinghouse, the defendants cannot be criticised for the manner in which they addressed the plaintiffs’ complaints before the issue

of proceedings, or for the manner in which they addressed the proceedings once issued. On the contrary, the open offers made by

the defendants to the plaintiffs with a view to resolving these proceedings were exemplary. But whatever may have been going on

behind the scenes by way of settlement discussions, the open offers of the defendants were repeatedly rejected by the plaintiffs.

Counsel for the defendants submits that O.99, r.1A(1)(c) requires the Court to take such offers into account in determining the issue

of costs. That order provides:-

“The High Court, in considering the awarding of the costs of any action (other than an action in respect of a claim

or counterclaim concerning which a lodgment or tender offer in lieu of lodgment may be made in accordance with

Order 22) or any application in such an action, may, where it considers it just, have regard to the terms of any

offer in writing sent by any party to any other party or parties offering to satisfy the whole or part of that other

party’s (or those other parties’) claim, counterclaim or application.”

6. Counsel for the defendants argues that the order for specific performance which the plaintiffs obtained was no more than they

would have achieved had they accepted either the offer made by the defendants in the letter of April, 2012 or the letter of 18th

February, 2016. Counsel for the defendants argues that there is really very little difference between these letters of offer, and in this

regard, argues that the letter of April 2012 contemplated the kind of independent supervision specified in the February, 2016 letter.

He submits that had the plaintiffs accepted either of these offers, the only issue that would have remained to be determined as

between the parties would have been the responsibility for the cost of alternative accommodation pending the carrying out of works

of remediation.

7. This is certainly so as regards the offer made in February, 2016, which was made some nine months before the matter came to

trial. As can be seen from its text, that offer set out a step by step procedure for identification and remedying of defects, with

provision for the intervention of an independent expert to resolve any disputes that might arise along the way. As I mentioned in the

principal judgment, the plaintiffs’ own engineer, Mr Declan Gibbons, confirmed that he could see no reason why that offer was not

accepted. He said he did not know why it was not accepted by the plaintiffs. It appears from the evidence of the second named

plaintiff that they were reluctant to permit the defendants to carry out remediation works, having lost faith in the defendants.

However, Mr Gibbons in his evidence confirmed that any such concerns were adequately addressed in the offer through the

involvement at all stages in the proposal of the plaintiffs’ own engineer, as well as the provision for resolution of disputes by an

independent expert.

8. Mr Gibbons however did not agree that the letter of April, 2012 was a sufficient proposal to resolve matters, or that it should have

been accepted by the plaintiffs. He said that that letter did not put forward a specific proposal in relation to the eradication of mould

from the attic space, which was the main issue of concern to the plaintiffs.

9. It is submitted on behalf of the defendants that had either of these offers been accepted, the only matter that would have

proceeded to trial would have been the claim for the cost of renting alternative accommodation. This would have involved relatively

brief evidence and a short hearing, and would have resulted in very significant savings of costs. As it is, the trial ran for eleven days.

10. For all of these reasons, counsel for the defendants submitted that the court should fashion a costs order that reflects the offers

made by the defendants to resolve these proceedings well in advance of the trial, and he referred to the cases of Veolia, and also

McAleenan v. AIG (Europe) Limited 3 I.R. 202, as authority for the proposition that the Court should award any costs unnecessarily

incurred in proceedings against the party responsible for causing such costs, so, for example, in McAleenan, Finlay Geohegan J.

apportioned costs in the round; having awarded the plaintiff 40% of the costs and the defendant 60% of the costs, she made a net

award of 20% of the costs of the proceedings in favour of the defendants. She made similar orders in the case of Revenue

Commissioners v. Anthony J. Fitzpatrick [2017] IECA 115.

11. The letter of offer made on behalf of the defendants of April, 2012 was indeed a commendable offer. It is correct however to say

that it did not address the central issue of dispute between the parties i.e. the elimination of mould in the attic space, because this

was not addressed by Mr Forde in his report. Insofar as the defendants went on to offer to do such other works as the plaintiffs

might reasonably require, I think it is unlikely that that offer if accepted, would have resolved the proceedings because the

defendants were adamant that there was no necessity to replace the roof, the removal and replacement of which was included by me

as part of the order requiring specific performance of the building agreement. Nor was there any provision for independent resolution

of disputes in this letter and I do not think that such a proposal can be implied as submitted by counsel for the defendants. That said,

the plaintiffs must accept some criticism for not responding in any meaningful way to this letter.

12. But any shortcomings in the proposal advanced on April, 2012 were fully addressed by the offer made in February, 2016. That

offer should have been accepted, and by their failure to do so, the plaintiffs caused almost all of the costs that followed, with the

sole exception of those costs that are exclusively related to the recovery of rent paid by them for alternative accommodation.

13. Letters of the kind written on behalf of the defendants in February, 2016 would be deprived of much of their benefit and intended

effect if defendants are free to refuse such offers with impunity. Parties to proceedings are to be encouraged and not discouraged

from putting forward proposals which will lead to an early resolution of litigation with all attendant benefits, including significant

savings of costs and court time. All of this is recognised by O 99, r 1 A (1) of the Rules of the Superior Courts.

14. It follows from this that the defendants should be awarded all costs incurred by them in these proceedings from 18th February

2016 onwards, save only those costs that were incurred in connection with the claim of the plaintiffs for reimbursement of the cost of

renting alternative accommodation. The plaintiffs are entitled to an order for all other costs incurred by them in the proceedings i.e.

all costs incurred by them up to 18th February, 2016, together with such costs as may be deemed to relate only to recovering the

cost of renting alternative accommodation. I appreciate that separating this latter cost from all other costs is a somewhat difficult

exercise. To make this easier for the parties, and, if need be, for the Taxing Master, I propose to order that the plaintiffs shall be

entitled to be awarded the costs of one day in respect of this issue and on the basis that it would not have been necessary for the

plaintiffs to call any expert evidence in relation to the defects in the premises because responsibility for those defects was effectively

acknowledged by the letter of 18th February, 2016 and the necessary remediation works would have been identified and possibly

even completed by the time the trial of the issue concerning recovery of rent only came on for hearing. The brief fees in respect of

that one day shall be measured by reference to that issue alone.

15. However, had the plaintiffs accepted the offer of 18th February, 2016, they would have incurred a certain amount of additional

costs to their engineer in engaging with the defendants’ engineer and possibly also with an independent expert. The defendants would

have been liable to discharge those costs. The quantification of the same is obviously a hypothetical exercise, since we can never

know exactly how much work would have been required of the plaintiffs’ engineer in this scenario. However, some of his work would

already have been done and covered by the costs the plaintiffs are entitled to recover up to February, 2016 i.e. his initial inspection

and report, as well as work on specifications. We know also that the plaintiffs were placing a value of €97,000 on the cost of the

works, assuming they were undertaken by a third party. Having regard to these factors, I think that €7,500 would be a reasonable

allowance for whatever work might have been required of the plaintiffs’ engineer, and this amount (together with the VAT payable on

it) should be credited against the costs liability of the plaintiffs to the defendants arising out of the orders made above.