Court dismisses prosecution for construction violation due to unclear deadline in administrative order.

Case Number Pp-2482/2023-4
Court / Authority
Jurisdiction Croatia (HR)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court acquitted the defendant of a construction violation charge stemming from an unclear administrative order. While the prosecution alleged failure to demolish a structure and level the land by March 17, 2023, the defendant argued the order was contradictory because the removal deadline was stated as July 27, 2023. The court ruled that without a clearly defined start date for the fifteen-day execution period, the order lacked the necessary legal certainty to constitute a violation.

Legislator headnote

AI generated

Article 71 of the State Inspectorate Act; Article 161, paragraph 6 of the Offences Act: An administrative order establishing a violation is invalid if it fails to clearly specify the commencement date of the execution period, rendering the deadline for compliance ambiguous and legally uncertain.

Keywords

AI generated
administrative order unclear deadline construction violation legal certainty State Inspectorate Act execution period acquittal

Cited Legislation

AI generated
Article 71 of the State Inspectorate Act
Article 127, paragraph 1, sub-paragraph 4 and sub-paragraph 4 of the State Inspectorate Act
Article 161, paragraph 6 of the Offences Act
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

REPUBLIKA HRVATSKA

OPĆINSKI SUD U PULI-POLA

Poslovni

Kranjčevićeva 8,52100 Pula-Pola

Poslovni broj: Pp -2482/2023-4

U I M E R E P U B L I K E H R V A T S K E

P R E S U D A

Općinski sud u Puli - Pola, po sucu Tatjani Japundžić Prović, uz sudjelovanje Željke Juričko kao zapisničara, u prekršajnom postupku protiv okrivljene OP, zastupane po Odvjetničkom društvu iz Zagreba, Horvat & Zebec & Bajsić Bogović j.t.d., po optužnom prijedlogu Državnog inspektorata, Područnog ureda Rijeka, Službe građevinske inspekcije, Ispostave u Pazinu, pod brojem: KLASA: UP/I -362-02/23- 02/336; URBROJ; 443-02-04-17-23-13 od 09.kolovoza 2023., zbog djela prekršaja iz članka 71. Zakona o Državnom inspektoratu, što je kažnjivo po članku 127.stavka 1. podstavka 4. i stavka 4. Zakona o Državnom inspektoratu ( „Narodne novine“ br. 115/19, 117/2021, 67/2023) 12.ožujka 2026. na temelju članka 161. stavka 6. Prekršajnog zakona ( Narodne novine, br. 107/07., 39/13., 157/13., 110/15., 70/17., 118/18., 114/22. )

p r e s u d i o j e

Okrivljena: OP, OIB: [osobni identifikacijski broj], nastanjena u Zagrebu, Ulica Đuke Begovića 17, fizička osoba,

oslobađa se od optužbe

I. - da u periodu od dana izvršnosti rješenja o uklanjanju 28.srpnja 2023. do dana kontrole izvršenja rješenja 03.kolovoza 2023. nije uklonila građevinu gotove konstrukcije tlocrtnih dimenzija 3,0x 8,0 m povezanu s tlom betonskim blokovima, sa ispustom za otpadne vode u septičku jamu ( upojni bunar ), prema jugu dograđena drvenom konstrukcijom na stupovima ( tipa sojenice ) ukupnih dimenzija 4,0 x 8,0m, od kojeg je zapadna polovina tlocrta 4,0 x 4,0 m zatvoreni dio s jednostrešnim krovom, ugrađene stolarije, a istočna polovina otvorena povišena terasa veličine 4,0 m x 4,0 m, izgrađenu na zemljištu k. č. [katastarska čestica] k. o. [katastarska općina], bez izvršne građevinske dozvole, te da nakon uklanjanja izvrši poravnavanje terena, a što da je bila dužna učiniti najkasnije do 17.travnja 2023. na temelju naredbe iz Rješenja građevinskog inspektora Državnog inspektorata, Područnog ureda Rijeka Službe građevinske inspekcije, Ispostave u Pazinu br. KLASA: UP/I-362-02/23-02/336; URBROJ: 443-02-04-17-23-1 od 28.ožujka 2023. što da je utvrđeno 03.kolovoza 2023. o čemu je sastavljen Zapisnik br. KLASA: UP/I-362-02/23-02/336; URBROJ: 443-02-04-17-23-11,

II. - čime da bi počinila prekršaj iz članka 71. Zakona o Državnom inspektoratu, što je kažnjivo po članku 127.stavku 1. podstavku 4. i stavku 4. Zakona o Državnom inspektoratu.

III. Na temelju članka 140. Prekršajnog zakona nastali troškovi postupka imaju se nadoknaditi na teret proračunskih sredstava ovog Suda.

Obrazloženje

1. 09.kolovoza 2023. Državni inspektorat, Područni ured Rijeka, Služba građevinske inspekcije, Ispostava u Pazinu, svojim aktom pod uvodno navedenim brojem izdala je prekršajni nalog protiv okrivljenice zbog izvršenja prekršaja kako je činjenično opisan i pravno označen u izreci presude.

2. Na izdani prekršajni nalog okrivljenica je putem opunomoćenog branitelja podnijela pravodoban prigovor osnovom osporavanja prekršaja u kojem se, među drugim, navodi i da u izreci predmetnog prekršajnog naloga ovlašteni tužitelj navodi da je uklanjanje i poravnanje terena okrivljenica bila dužna učiniti najkasnije do 17.travnja 2023., dok se u obrazloženju istoga navodi da je rok za dobrovoljno uklanjanje i poravnanje terena iz rješenja o uklanjanju istekao 27.srpnja 2023., a što prekršajni nalog čini nerazumljivim, nejasnim i posljedično nezakonitim.

3. Analizom postavljenog optužnog akta slijedi da je okrivljenica bila dužna izvršiti rješenje najkasnije do 17.travnja 2023. na temelju naredbe iz Rješenja građevinskog inspektora Državnog inspektorata, Područnog ureda Rijeka Službe građevinske inspekcije, Ispostave u Pazinu br. KLASA: UP/I-362-02/23-02/336; URBROJ: 443-02- 04-17-23-1 od 28.ožujka 2023. dok iz istog činjeničnog identiteta slijedi i da okrivljenica u periodu od dana izvršnosti rješenja o uklanjanju 28. srpnja 2023. do dana kontrole izvršenja rješenja 03.kolovoza 2023. nije uklonila građevinu gotove konstrukcije tlocrtnih dimenzija 3,0x 8,0 m povezanu s tlom betonskim blokovima, sa ispustom za otpadne vode u septičku jamu ( upojni bunar ) prema jugu dograđena drvenom konstrukcijom na stupovima ( tipa sojenice ) ukupnih dimenzija 4,0 x 8,0m, od kojeg je zapadna polovina tlocrta 4,0 x 4,0 m zatvoreni dio s jednostrešnim krovom, ugrađene stolarije, a istočna polovina otvorena povišena terasa veličine 4,0 m x4,0 m, izgrađenu a zemljištu k. č. [katastarska čestica] k. o. [katastarska općina], bez izvršne građevinske dozvole, te da nakon uklanjanja izvrši poravnavanje terena, dakle radi se o dva različita roka ( 28.srpnja 2023. odnosno 17. travnja 2023. ). Nadalje, primjećuje se da ni u rješenju zbog čijeg se neizvršenja tereti okrivljenica nije navedeno od kojeg momenta počinje teći rok od petnaest dana. Kako je za utvrđenje prekršaja neizvršenja izvršnog rješenja nužno jasno navesti dan od kojeg rješenje postaje izvršno što je konstitutivni element za postojanje prekršaja, a što je u konkretnoj situaciji ostalo dvojbenim i nije ispravljeno ni naknadno od strane tužitelja ( nejasnoća u odnosu na rok izvršenja istaknuta i u prigovoru ), uvjerenje je suda da valja postupiti kao u izreci presude i pozivom na odredbu članka 161. stavka 6. Prekršajnog zakona.

U Puli –Pola, 12.ožujka 2026.

Zapisničar

Sudac

Željka Juričko

Tatjana Japundžić Prović