Généré par l'IAThe Court of Cassation upheld the lower court's decision to reject an appeal regarding the revaluation of fees, which was contractually conditioned upon a work delay exceeding twelve months relative to the general schedule. The appellate court correctly determined that the condition for revaluation was not met because, although a delay occurred, there was no interruption in the work for the specified period, a finding of fact that the high court found was properly based on the evidence and adequately addressed the appellant's arguments.
Regeste Legislator
Généré par l'IAContractual Fee Revaluation Condition Not Met Due to Work Delay Qualification: The appellate court correctly determined that the condition for revaluation was not met because, although a delay occurred, there was no interruption in the work for the specified period, a finding of fact that the high court found was properly based on the evidence and adequately addressed the appellant's arguments.
Mots-clés
Généré par l'IADécisions connexes
Généré par l'IATexte complet
Sur le moyen unique ci-après annexé :
Attendu qu'ayant constaté que la convention stipulait l'actualisation des honoraires au cas où un retard de plus de douze mois se produirait dans la réalisation des travaux par rapport aux prévisions du "planning général" et relevé l'absence d'interruption des travaux pendant un tel délai la Cour d'appel, qui a répondu aux conclusions, a souverainement retenu que la condition mise à la réévaluation des honoraires n'était pas remplie ;
D'où il suit que le moyen n'est pas fondé ;
PAR CES MOTIFS :
REJETTE le pourvoi