Developer v. Construction Company and Public Body Regarding Sewer Line Faults and Warranty Waiver

Numéro de cause 69-11351
Autorité / Tribunal
Juridiction France (FR)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

A property developer sued several parties, including a construction company and the public administrative body responsible for supervising the sewer line design and installation, after significant building damage resulted from pipeline leaks caused by faulty design and execution. The appellate court ruled that the judicial courts lacked jurisdiction over the claim against the state representative because the contract involving the public works supervision possessed an "exorbitant" clause waiving the ten-year structural warranty, thereby establishing an administrative contract, and it also deferred ruling on the liability of the construction company whose responsibility might overlap with that of the public service. The High Court upheld the ruling, affirming that the waiver of the ten-year warranty established the administrative nature of the contract, justifying the declination of jurisdiction by the judicial order, and that the deferral of the ruling against the private contractor was a proper exercise of the court's discretionary power for the sound administration of justice.

Regeste Legislator

Généré par l'IA

ARTICLES 1792 ET 2270 DU CODE CIVIL, LOI DU 29 SEPTEMBRE 1948, ARRETE INTERMINISTERIEL DU 7 MARS 1949; Developer v. Construction Company and Public Body Regarding Sewer Line Faults and Warranty Waiver: The appellate court ruled that the judicial courts lacked jurisdiction over the claim against the state representative because the contract involving the public works supervision possessed an "exorbitant" clause waiving the ten-year structural warranty, thereby establishing an administrative contract, and it also deferred ruling on the liability of the construction company whose responsibility might overlap with that of the public service. The High Court upheld the ruling, affirming that the waiver of the ten-year warranty established the administrative nature of the contract, justifying the declination of jurisdiction by the judicial order, and that the deferral of the ruling against the private contractor was a proper exercise of the court's discretionary power for the sound administration of justice.

Mots-clés

Généré par l'IA
contrat de droit administratif responsabilité de l'entrepreneur propriété immobilière travaux publics administration de la justice incompétence ratione materiae

Dispositions légales citées

Généré par l'IA
ARTICLES 1792 ET 2270 DU CODE CIVIL
These articles concerning the ten-year warranty are mentioned in the arguments against the appellate court's decision regarding the stipulation being exorbitant, but the final decision rests on the administrative nature of the contract, not on the application or rejection of this warranty.
LOI DU 29 SEPTEMBRE 1948
This law is cited in the context of the mandate given to the Ponts-et-Chaussées, but it is the finding of the administrative nature of the contract, established by the exorbitant clause, that ultimately justifies the ruling, not the direct application of this law in the operative part.
ARRETE INTERMINISTERIEL DU 7 MARS 1949
This decree is cited in the context of the mandate given to the Ponts-et-Chaussées, but it is the finding of the administrative nature of the contract, established by the exorbitant clause, that ultimately justifies the ruling, not the direct application of this decree in the operative part.
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
ARTICLES 1792 ET 2270 DU CODE CIVIL

These articles concerning the ten-year warranty are mentioned in the arguments against the appellate court's decision regarding the stipulation being exorbitant, but the final decision rests on the administrative nature of the contract, not on the application or rejection of this warranty.

LOI DU 29 SEPTEMBRE 1948

This law is cited in the context of the mandate given to the Ponts-et-Chaussées, but it is the finding of the administrative nature of the contract, established by the exorbitant clause, that ultimately justifies the ruling, not the direct application of this law in the operative part.

ARRETE INTERMINISTERIEL DU 7 MARS 1949

This decree is cited in the context of the mandate given to the Ponts-et-Chaussées, but it is the finding of the administrative nature of the contract, established by the exorbitant clause, that ultimately justifies the ruling, not the direct application of this decree in the operative part.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

SUR LE PREMIER MOYEN, PRIS EN SES TROIS BRANCHES : ATTENDU QU'IL RESULTE DES ENONCIATIONS DE L'ARRET ATTAQUE QUE LA SOCIETE IMMOBILIERE FAMILIALE DE CONSTRUCTION DE BOBIGNY <S I F C > A FAIT EDIFIER UN ENSEMBLE IMMOBILIER DE QUATORZE BATIMENTS D'HABITATION ;

QU'UNE FACADE DU BATIMENT " K " PRESENTA D'IMPORTANTES CREVASSES RESULTANT D'UN TASSEMENT DU A DES FUITES ABONDANTES PROVENANT D'UNE CANALISATION D'EGOUT LONGEANT CE BATIMENT ;

QUE CES FUITES AVAIENT POUR CAUSE DES FAUTES DE CONCEPTION ET D'EXECUTION DANS LA POSE DE CETTE CANALISATION ;

QUE POUR REALISER LA CONSTRUCTION DE L'ENSEMBLE IMMOBILIER, LA S I F C AVAIT DONNE MANDAT AU BUREAU ADMINISTRATIF ET TECHNIQUE DE L'HABITATION <B A T H > DE PREPARER LES MARCHES, DE PROPOSER LE CHOIX DES ENTREPRISES ET D'ASSURER LE RESPECT DE LA CADENCE DE REALISATION DES TRAVAUX ;

QUE, SUR LA PROPOSITION DU B A T H , L'ETABLISSEMENT DES PLANS DES C CANALISATIONS, AINSI QUE LA SURVEILLANCE DES TRAVAUX CORRESPONDANTS, AVAIENT ETE CONFIES A L'ADMINISTRATION DES PONTS-ET-CHAUSSEES, AUTORISEE A PRETER SON CONCOURS DANS LES CONDITIONS PREVUES PAR LA LOI DU 29 SEPTEMBRE 1948 ET L'ARRETE INTERMINISTERIEL DU 7 MARS 1949 ;

QUE L'ENTREPRISE BIARNAIS AVAIT ETE CHARGEE DES TRAVAUX DE MISE EN PLACE DES CANALISATIONS ;

QU'EN VUE D'OBTENIR LA REPARATION DU PREJUDICE QU'ELLE AVAIT SUBI, LA S I F C ASSIGNA L'ENTREPRISE BIARNAIS ET SON ASSUREUR, LE B A T H ET SES ASSUREURS, AINSI QUE L'AGENT JUDICIAIRE DU TRESOR PUBLIC, EN QUALITE DE REPRESENTANT DU SERVICE DES PONTS-ET-CHAUSSEES ET DU MINISTRE DE L'EQUIPEMENT ;

QUE LA COUR D'APPEL MIT HORS DE CAUSE LE B A T H ET SES ASSUREURS, SE DECLARA INCOMPETENTE POUR CONNAITRE DE LA DEMANDE FORMEE CONTRE L'AGENT JUDICIAIRE DU TRESOR PUBLIC ET DECIDA DE SURSEOIR A STATUER SUR CELLE DIRIGEE CONTRE L'ENTREPRISE BIARNAIS ;

ATTENDU QUE LA S I F C REPROCHE A L'ARRET ATTAQUE D'AVOIR ESTIME QUE LES TRIBUNAUX DE L'ORDRE JUDICIAIRE N'ETAIENT PAS COMPETENTS POUR APPRECIER, EN L'ESPECE, LA RESPONSABILITE EVENTUELLE DE L'ADMINISTRATION, ALORS, SELON LE MOYEN, QUE, LORSQU'U UNE PERSONNE PUBLIQUE OU PRIVEE ET L'ETAT CONVIENNENT, EN APPLICATION DES TEXTES SUSVISES, DE CONFIER AU SERVICE DES PONTS-ET-CHAUSSEES DES TRAVAUX D'ETUDES, DE DIRECTION ET DE SURVEILLANCE DE PROJETS, LA CONVENTION AINSI CONCLUE EST UN CONTRAT DE LOUAGE D'OUVRAGE, DONT L'INEXECUTION OU LA MAUVAISE EXECUTION ENGAGERAIT, A MOINS DE STIPULATIONS EXPRESSES CONTRAIRES, LA RESPONSABILITE DE L'ETAT DEVANT LES JURIDICTIONS ADMINISTRATIVES OU JUDICIAIRES, SELON LES CAS QU'IL EST EGALEMENT PRETENDU QUE LA RENONCIATION A SE PREVALOIR DE LA GARANTIE DECENNALE ETABLIE PAR LES ARTICLES 1792 ET 2270 DU CODE CIVIL, RENONCIATION QUI NE SERAIT NI ILLEGALE, NI CONTRAIRE A L'ORDRE PUBLIC, NE CONSTITUERAIT, EN AUCUNE MANIERE, UNE CONDITION EXORBITANTE DU DROIT COMMUN ;

QU'IL EST ENFIN SOUTENU QUE " LES TRAVAUX ENTREPRIS PAR UNE SOCIETE IMMOBILIERE FAMILIALE DE CONSTRUCTION, AGISSANT POUR SON PROPRE COMPTE, ET NON POUR CELUI D'UNE PERSONNE DE DROIT PUBLIC, N'ONT PAS LA QUALITE DE TRAVAUX PUBLICS " ;

MAIS ATTENDU QUE LA COUR D'APPEL, APRES AVOIR RELEVE LES CIRCONSTANCES DESQUELLES ELLE A PU DEDUIRE " LE CARACTERE D'INTERET GENERAL DES TRAVAUX A REALISER ", ENONCE, A BON DROIT, QUE LA " LA RENONCIATION A TOUT RECOURS A LA RESPONSABILITE DECENNALE DES ARCHITECTES ET ENTREPRENEURS " CONSTITUE UNE STIPULATION " EXORBITANTE DU DROIT COMMUN " ;

QUE, PAR CES SEULS MOTIFS, L'ARRET ATTAQUE, QUI NE S'EST PAS PRONONCE SUR LA NATURE JURIDIQUE DES TRAVAUX AU REGARD DE LA NOTION DU TRAVAIL PUBLIC, A ETABLI LE CARACTERE ADMINISTRATIF DU CONTRAT INTERVENU ENTRE L'ADMINISTRATION ET LE BUREAU ADMINISTRATIF ET TECHNIQUE DE L'HABITATION, MANDATAIRE DU MAITRE DE X... ET A DES LORS, JUSTIFIE L'INCOMPETENCE DES TRIBUNAUX DE L'ORDRE JUDICIAIRE ;

QUE LE MOYEN NE PEUT DONC ETRE ACCUEILLI EN AUCUNE DE SES BRANCHES :

ET SUR LE SECOND MOYEN : ATTENDU QU'IL EST ENCORE REPROCHE A LA JURIDICTION DU SECOND DEGRE D'AVOIR SURSIS A STATUER SUR LA DEMANDE DIRIGEE CONTRE L'ENTREPRISE BIARNAIS, ALORS, SELON LE POURVOI, QUE LA COUR D'APPEL N'AURAIT PU PRENDRE UNE TELLE DECISION, SANS VIOLER LE PRINCIPE DE LA SEPARATION DES POUVOIRS, LA DETERMINATION DE LA PART DE RESPONSABILITE INCOMBANT A UN SERVICE PUBLIC NE DEPENDANT PAS DE L'APPRECIATION A LAQUELLE L'AUTORITE JUDICIAIRE A PU SE LIVER DES FAUTES RESPECTIVES DU SERVICE PUBLIC ET DES PARTIES PRIVEES, ET RECIPROQUEMENT ;

MAIS ATTENDU QUE LES JUGES D'APPEL ENONCENT " QU'EN L'E TAT ACTUEL DE LA PROCEDURE, LA COUR NE SAURAIT EXAMINER LA RESPONSABILITE EVENTUELLE DE L'ENTREPRISE BIARNAIS, EXECUTANTE DES PONTS-ET-CHAUSSEES, SOUS LEUR SURVEILLANCE ET LEURS INSTRUCTIONS, ET DONT LA RESPONSABILITE PROPRE DANS LES DOMMAGES SUBIS EST SUSCEPTIBLE DE CONCOURIR AVEC LA LEUR " ;

QU'EN SE DETERMINANT PAR UN TEL MOTIF, ILS N'ONT FAIT QU'USER DU POUVOIR SOUVERAIN QUI LEUR APPARTENAIT, DANS L'INTERET D'UNE BONNE ADMINISTRATION DE LA JUSTICE, D'APPRECIER L'OPPORTUNITE DE SURSEOIR A STATUER ;

QUE, DES LORS, LE MOYEN DOIT ETRE ECARTE ;

PAR CES MOTIFS : REJETTE LE POURVOI FORME CONTRE L'ARRET RENDU LE 13 DECEMBRE 1968, PAR LA COUR D'APPEL DE PARIS ;