Painting Contractor v. General Contractor over Direct Payment and Subcontractor Status
Synthèse Legislator
Généré par l'IAA painting and glazing contractor sued for the balance due after the general contractor, with whom it contracted for work on housing projects, was placed into judicial liquidation, the lower courts having ordered the contractor to return a direct payment received from the housing owner and denying its recourse against the owner and the supervising committee. The appellate court confirmed this decision, finding that the general contractor had contracted solely with the owner, that the supervising committee's involvement was administrative, and that the sub-contractor had submitted its bid to and dealt with the general contractor as the pilot contractor for the main works, despite the bid documents suggesting ambiguity regarding the contract structure. The Supreme Court quashed the appellate ruling because, while it acknowledged the main contracts, it failed to legally establish that the painting contractor agreed to be a subcontractor to the general contractor, noting instead that direct relations existed between the painting contractor, the owner, and the supervising committee, evidenced by direct payments the painting contractor received from the owner.
Regeste Legislator
Généré par l'IAARTICLE 1134 DU CODE CIVIL; Painting Contractor v. General Contractor over Direct Payment and Subcontractor Status: The appellate court confirmed this decision, finding that the general contractor had contracted solely with the owner, that the supervising committee's involvement was administrative, and that the sub-contractor had submitted its bid to and dealt with the general contractor as the pilot contractor for the main works, despite the bid documents suggesting ambiguity regarding the contract structure. The Supreme Court quashed the appellate ruling because, while it acknowledged the main contracts, it failed to legally establish that the painting contractor agreed to be a subcontractor to the general contractor, noting instead that direct relations existed between the painting contractor, the owner, and the supervising committee, evidenced by direct payments the painting contractor received from the owner.
Mots-clés
Généré par l'IADispositions légales citées
Généré par l'IADécisions connexes
Généré par l'IAQuestions juridiques clés extraites par Legislator
Généré par l'IAThis article, cited in the preliminary analysis, appears to be the basis for the Court of Cassation's finding that the lower court failed to establish the necessary contractual relationship (or lack thereof) required by law to support its decision.
This is the primary order of the final decision, resulting in the quashing of the lower court's ruling.
Texte complet
SUR LE PREMIER MOYEN, PRIS EN SES CINQ BRANCHES : VU L'ARTICLE 1134 DU CODE CIVIL ;
ATTENDU QUE, SELON LES ENONCIATIONS DE L'ARRET ATTAQUE, LA SOCIETE BAUDUIN, ENTREPRENEUR DE BATIMENTS, S'EST ENGAGEE PAR MARCHE DU 24 SEPTEMBRE 1963 A EXECUTER LES TRAVAUX DE CONSTRUCTION DU LOT UNIQUE TOUS CORPS D'ETAT DE HUIT LOGEMENTS, A HASPRES, POUR LE COMPTE DE LA SOCIETE HLM LE FOYER DU VALENCIENNOIS, SOUS LA SURVEILLANCE DU COMITE INTERPROFESSIONNEL DU LOGEMENT DE VALENCIENNES (CIL) ET QUE LE 24 OCTOBRE 1963, LE MEME ENTREPRENEUR S'EST ENGAGE DANS DES CONDITIONS SEMBLABLES, AVEC LA MEME SOCIETE HLM POUR LA CONSTRUCTION DE DOUZE LOGEMENTS A BELLAING ;
QUE X... AYANT EXECUTE LES TRAVAUX DE PEINTURE-VITRERIE A OBTENU DE LA SOCIETE HLM COURANT 1964 PAIEMENT DIRECT DE LA SOMME DE 4 864 FRANCS ET PRETENDU QU'UN SOLDE LUI RESTAIT DU AU DIRE DE SES TRAVAUX LORSQUE LE 15 DECEMBRE 1964 LE TRIBUNAL A PRONONCE LE REGLEMENT JUDICIAIRE DE LA SOCIETE BAUDUIN ET REPORTE AU 18 DECEMBRE 1963 LA DATE DE CESSATION DE SES PAIEMENTS ;
QUE LE JUGEMENT ENTREPRIS A CONDAMNE X... A RAPPORTER A LA MASE DU REGLEMENT JUDICIAIRE BAUDUIN LA SOMME DE 4 864 FRANCS, ET LA SOCIETE HLM A PAYER A LA SOCIETE BAUDUIN ET A SON ADMINISTRATEUR LE SOLDE RESTANT DU SUR LE PRIX DES TRAVAUX EXECUTES PAR X..., ET A DEBOUTE CELUI-CI DE SON RECOURS EN GARANTIE ET DE SON ACTION EN DOMMAGES ET INTERETS DIRIGES CONTRE LE CIL ET LA SOCIETE HLM ;
QU'A L'APPUI DE SON APPEL X... A FAIT VALOIR QU'IL N'A PAS EU CONNAISSANCE DESDITS MARCHES, QUE LE CIL LUI A ADRESSE LE 10 AVRIL 1963 SOUS LE TIMBRE DE LA SOCIETE HLM UN APPEL D'OFFRES SPECIFIANT QUE L'ENTREPRISE DE GROS OEUVRE DEVAIT ASSURER LE PILOTAGE DU CHANTIER, QUE CET APPEL D'OFFRES ETAIT ACCOMPAGNE D'UN CAHIER DES CHARGES PARTICULIERES DONT LE CHAPITRE DESIGNATION DU LOT DU TITRE A I AVAIT ETE LAISSE EN BLANC ET DONT LE TITRE B I INDIQUAIT QUE LES PAIEMENTS SERAIENT EFFECTUES A CHACUNE DES ENTREPRISES COPARTICIPANTES D'APRES LES SITUATIONS PRESENTEES PAR ELLES, QU'IL N'A JAMAIS ETE EN RELATION AVEC LA SOCIETE BAUDUIN MAIS UNIQUEMENT AVEC LE CIL ET QU'IL N'A EU DE LIEN DE DROIT QU'AVEC LA SOCIETE HLM ;
ATTENDU QUE, POUR CONFIRMER LA DECISION DES PREMIERS JUGES, L'ARRET ATTAQUE DECLARE QUE LA SOCIETE BAUDUIN A TRAITE SEULE LES MARCHES PRECITES AVEC LA SOCIETE HLM, QUE L'INTERVENTION DU CIL N'EST PAS SIGNIFICATIVE EN SOI PARCE QU'ELLE DERIVE DU STATUT PARTICULIER DES COOPERATIVES HLM AUPRES DESQUELLES LE CIL EXERCE LES FONCTIONS ET PREROGATIVES NORMALES DEVOLUES A L'ARCHITECTE ;
QUE L'APPEL D'OFFRES DU 10 AVRIL 1963 PRECISAIT LES ENTREPRENEURS DE LOTS SECONDAIRES ADRESSERONT LEUR SOUMISSION A L'ENTREPRENEUR DE GROS OEUVRE PILOTE QUI LES JOINDRA A SA SOUMISSION, QU'IL RESULTE NOTAMMENT DES ANNEXES JOINTES AUX MARCHES QUE X... A, CONFORMEMENT AUX STIPULATIONS DE CET APPEL D'OFFRES, ADRESSE UNE SOUMISSION A LA SOCIETE BAUDUIN, ET QUE CETTE TRANSMISSION IMPLIQUE QUE X... SAVAIT DES L'ORIGINE QUE LA SOCIETE BAUDUIN SE CHARGEAIT DU GROS OEUVRE ET QU'IL DEVAIT EN CONSEQUENCE SE METTRE EN RAPPORT AVEC ELLE, QUE SI LE CAHIER DES CHARGES PARTICULIERES JOINT A L'APPEL D'OFFRES ETAIT SUSCEPTIBLE, EN L'ABSENCE DE TOUTE MENTION SOUS LA RUBRIQUE DESIGNATION DU LOT, DE S'APPLIQUER INDIFFEREMMENT A UN MARCHE UNIQUE D'ENTREPRISE GENERALE OU A UN GROUPEMENT D'ENTREPRISES REPRESENTE PAR UN MANDATAIRE COMMUN, LES DEUX MARCHES LIANT LA SOCIETE HLM A LA SOCIETE BAUDUIN AVAIENT ETE PASSES TOUS CORPS D'ETAT ET QUE CETTE DERNIERE SOCIETE N'Y FIGURAIT DONC PAS EN QUALITE DE MANDATAIRE COMMUN, QU'UNE AUTRE ENTREPRISE A RECONNU ETRE SOUS TRAITANTE ET SOLLICITE DE LA SOCIETE HLM DES REGLEMENTS DIRECTS EN RAISON DE LA SITUATION PEU BRILLANTE DE LA SOCIETE BAUDUIN, QUE CELLE-CI A ACCEPTE QUE LES SOUS-TRAITANTS SOIENT PAYES DIRECTEMENT, QUE CHACUN DE CES PAIEMENTS DIRECTS A DONNE LIEU A UN CERTIFICAT PORTANT LE CACHET ET LA SIGNATURE DE LA SOCIETE BAUDUIN, ET QUE, SI X... FAIT VALOIR QUE LE VISA DU MANDATAIRE COMMUN EN CAS D'ENTREPRISES GROUPEES ETAIT EGALEMENT PREVU AU CAHIER DES CHARGES PARTICULIERES QUI LUI FUT ADRESSE EN MEME TEMPS QUE L'APPEL D'OFFRES DU 10 AVRIL 1963, LA SOCIETE BAUDUIN N'A, NI A L'EPOQUE DES SOUMISSIONS, NI EN COURS D'EXECUTION DES MARCHES, LAISSE SUPPOSER A AUCUN DES ENTREPRENEURS DE LOTS SECONDAIRES QU'ELLE AGISSAIT EN QUALITE DE MANDATAIRE COMMUN ET QU'IL APPARTENAIT A X..., EN PRESENCE DE L'ALTERNATIVE APPARAISSANT AUDIT CAHIER DES CHARGES, DE SOLLICITER EN TEMPS VOULU TOUS ECLAIRCISSEMENTS UTILES POUR LE CAS OU IL N'AURAIT PAS COMPRIS LA PORTEE JURIDIQUE DE SES ENGAGEMENTS ;
ATTENDU QU'EN STATUANT PAR CES MOTIFS QUI, S'ILS RELEVENT L'EXISTENCE DES MARCHES PASSES EN SEPTEMBRE ET OCTOBRE 1963 PAR LA SOCIETE BAUDUIN AVEC LA SOCIETE HLM SOUS LA SURVEILLANCE DU CIL, N'ETABLISSENT PAS POUR REPONDRE AUX CONCLUSIONS DE X..., QUE CELUI-CI AIT CONTRACTE AVEC LA SOCIETE BAUDUIN ET ACCEPTE DE DEVENIR SON SOUS-TRAITANT, ET FONT AU CONTRAIRE RESSORTIR QUE DES LE 10 AVRIL 1963 LE CIL ET LA SOCIETE HLM ONT NOUE AVEC LUI DES RAPPORTS DIRECTS QUI SE SONT PROLONGES PAR LA SUITE AU POINT QUE X... A RECU DE LA SOCIETE HLM TOUS LES PAIEMENTS LITIGIEUX, LA COUR D'APPEL N'A PAS DONNE DE BASE LEGALE A SA DECISION ;
PAR CES MOTIFS, ET SANS QU'IL Y AIT LIEU DE STATUER SUR LE SECOND MOYEN : CASSE ET ANNULE EN SON ENTIER L'ARRET RENDU, LE 26 SEPTEMBRE 1969, ENTRE LES PARTIES, PAR LA COUR D'APPEL DE DOUAI ;
REMET, EN CONSEQUENCE, LA CAUSE ET LES PARTIES AU MEME ET SEMBLABLE ETAT OU ELLES ETAIENT AVANT LEDIT ARRET ET, POUR ETRE FAIT DROIT, LES RENVOIE DEVANT LA COUR D'APPEL DE REIMS.