The former manager and initial syndicate of a property development company was sued by the company after his resignation for the settlement of various sums and payment of damages, specifically concerning additional construction work beyond the scope of the original approved contract. The court rejected the appeal challenging the conviction to reimburse the company for potential payments related to unapproved supplementary work, reasoning that the finding that the manager could not engage the associates for work outside the initial market justified the conditional condemnation without being purely hypothetical. Furthermore, the court upheld the decision ordering the former manager to repay a sum of money received via a check made out to the company which he had endorsed after his managerial term ended, finding that this implicitly answered his argument regarding the company's standing to sue for restitution.

Regeste Legislator

Généré par l'IA

Property Developer Sues Former Manager Over Unapproved Construction Work and Misappropriated Funds: The court rejected the appeal challenging the conviction to reimburse the company for potential payments related to unapproved supplementary work, reasoning that the finding that the manager could not engage the associates for work outside the initial market justified the conditional condemnation without being purely hypothetical. Furthermore, the court upheld the decision ordering the former manager to repay a sum of money received via a check made out to the company which he had endorsed after his managerial term ended, finding that this implicitly answered his argument regarding the company's standing to sue for restitution.

Mots-clés

Généré par l'IA
promotion immobilière entreprises de construction restitution de la propriété responsabilité du chef de projet expulsion de locataire commercial contrat de gérance d'immeubles
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
REJETTE LE POURVOI FORME CONTRE L'ARRET RENDU LE 16 FEVRIER 1970 PAR LA COUR D'APPEL DE PARIS

This is the operative part of the final order, dismissing the appeal.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

SUR LE PREMIER MOYEN : ATTENDU QU'IL RESULTE DES ENONCIATIONS DE L'ARRET ATTAQUE QUE LA SOCIETE CIVILE IMMOBILIERE BELGRAND PY A FAIT EDIFIER UN IMMEUBLE COLLECTIF A USAGE D'HABITATION, QUE X... A ETE A L'ORIGINE GERANT DE LA SOCIETE ET SYNDIC DE L'IMMEUBLE ET QU'IL A DEMISSIONNE DE SES FONCTIONS DE GERANT EN 1962 ;

QUE LA SOCIETE L'A ALORS ASSIGNE EN REGLEMENT DE DIVERSES SOMMES ET EN PAIEMENT DE DOMMAGES INTERETS ;

ATTENDU QUE X... FAIT GRIEF A L'ARRET D'AVOIR DECIDE QU'AU CAS OU IL AURAIT COMMANDE D'AUTRES TRAVAUX QUE CEUX QUI FAISAIENT L'OBJET DU MARCHE ORIGINAIRE DU 31 AOUT 1959 S'ELEVANT A 1793940,85 FRANCS, IL DEVRAIT ETRE CONDAMNE A REMBOURSER A LA SOCIETE BELGRAND PY LE MONTANT DES SOMMES QU'ELLE MEME POURRAIT ETRE CONDAMNEE A PAYER AU TITRE DE CES TRAVAUX SUPPLEMENTAIRES, ALORS, SELON LE POURVOI, QUE LES JUGES NE POUVAIENT PRONONCER UNE CONDAMNATION DE X... SUR LA SIMPLE HYPOTHESE QUE CELUI CI AURAIT COMMANDE D'AUTRES TRAVAUX QUE CEUX FAISANT L'OBJET DU MARCHE DU 31 AOUT 1959, SANS VERIFIER AUCUNEMENT LA REALITE DE CES PRETENDUES COMMANDES SUPPLEMENTAIRES, UNE TELLE CONDAMNATION ETANT DEPOURVUE DE BASE LEGALE ;

MAIS ATTENDU QUE, PAR MOTIFS ADOPTES, LA COUR D'APPEL DECLARE QUE PARMI LES DOCUMENTS REMIS AUX ASSOCIES ACTUELS FIGURAIT LEDIT MARCHE (LE MARCHE ORIGINAIRE) A L'EXCLUSION DE TOUT AUTRE ACTE MODIFICATIF ET DE TOUT AVENANT, QUE, DANS CES CONDITIONS, X... NE POUVAIT ENGAGER LES ASSOCIES A EFFECTUER D'AUTRES TRAVAUX QUE CEUX PREVUS AU MARCHE APPROUVE PAR L'ASSEMBLEE DU 5 JUILLET 1959, QU'IL ECHET DES LORS DE DIRE QUE X... NE POUVAIT COMMANDER D'AUTRES TRAVAUX QUE CEUX FAISANT L'OBJET DU MARCHE DU 31 AOUT 1959, S'ELEVANT A 1793940,25 FRANCS ET DE DIRE QU'AU CAS OU IL EN AURAIT COMMANDE IL DEVRAIT ETRE CONDAMNE A REMBOURSER A LA SOCIETE BELGRAND PY LE MONTANT DES SOMMES QU'ELLE MEME POURRAIT ETRE CONDAMNEE A PAYER AU TITRE DES TRAVAUX SUPPLEMENTAIRES ;

QUE CES MOTIFS, QUI N'ONT PAS LE CARACTERE HYPOTHETIQUE, JUSTIFIENT LA CONDAMNATION PRONONCEE POUR LE CAS OU DES TRAVAUX SUPPLEMENTAIRES AURAIENT ETE COMMANDES ;

D'OU IL SUIT QUE LE MOYEN DOIT ETRE REJETE ;

SUR LE SECOND MOYEN : ATTENDU QU'IL EST ENCORE REPROCHE A L'ARRET D'AVOIR CONDAMNE X... A PAYER A LA SOCIETE BELGRAND PY, LA SOMME DE 2000 FRANCS A TITRE DE RESTITUTION, AU MOTIF QU'IL AVAIT RECU CETTE SOMME D'UN CESSIONNAIRE DE PARTS SOCIALES A L'EPOQUE OU, N'ETANT PLUS GERANT DE LA SOCIETE, IL N'AVAIT AUCUNE QUALITE POUR AGIR, ALORS, SELON LE MOYEN, QUE LA SOCIETE BELGRAND PY N'AVAIT AUCUNE QUALITE POUR AGIR EN RESTITUTION, LE CEDANT DES PARTS, LAGRANGE, ETANT LE SEUL A POUVOIR SE PREVALOIR D'UNE QUELCONQUE IRREGULARITE, AINSI QUE L'AVAIT FAIT VALOIR X... DANS SES CONCLUSIONS D'APPEL DEMEUREES SANS REPONSE ;

MAIS ATTENDU QUE LA COUR D'APPEL CONSTATE QU'A L'OCCASION DE CETTE CESSION UN CHEQUE DE 2000 FRANCS A ETE EMIS LE 24 OCTOBRE 1962 A L'ORDRE DE LA SOCIETE BELGRAND PY ET QUE X... L'A ENDOSSE EN INDIQUANT PAYER ORDRE CABINET X..., LE GERANT DE LA SOCIETE CIVILE IMMOBILIERE BELGRAND PY ;

QU'ELLE AJOUTE QU'A L'EPOQUE X... N'ETAIT PLUS GERANT DE LA SOCIETE ET N'AVAIT DONC PAS QUALITE POUR ENDOSSER LE CHEQUE ;

QU'ELLE A AINSI REPONDU IMPLICITEMENT MAIS NECESSAIREMENT AUX CONCLUSIONS QUI LUI ETAIENT SOUMISES ;

QUE LE SECOND MOYEN NE PEUT ETRE ACCUEILLI ;

PAR CES MOTIFS : REJETTE LE POURVOI FORME CONTRE L'ARRET RENDU LE 16 FEVRIER 1970 PAR LA COUR D'APPEL DE PARIS ;