Contractor Payment for Unwritten Extra Work Under Approximate Estimate Contract
Synthèse Legislator
Généré par l'IAIn a dispute where a contractor sought payment for supplementary renovation work, the lower court denied the claim, ruling that even if the initial agreement was not a fixed-price contract, the contractor still needed written proof for all claimed work, relying on the idea that written authorization is generally required for changes. The high court overturned this decision, reasoning that Article 1793 of the Civil Code only mandates written proof for modifications in a fixed-price contract, and since the initial agreement was an "approximate" estimate explicitly allowing for changes based on executed work justified by submitted statements, the appellate court failed to provide a legal basis for denying payment based on the lack of written proof for the extras.
Regeste Legislator
Généré par l'IAARTICLE 1793 DU CODE CIVIL; Contractor Payment for Unwritten Extra Work Under Approximate Estimate Contract: The high court overturned this decision, reasoning that Article 1793 of the Civil Code only mandates written proof for modifications in a fixed-price contract, and since the initial agreement was an "approximate" estimate explicitly allowing for changes based on executed work justified by submitted statements, the appellate court failed to provide a legal basis for denying payment based on the lack of written proof for the extras.
Mots-clés
Généré par l'IADispositions légales citées
Généré par l'IADécisions connexes
Généré par l'IAQuestions juridiques clés extraites par Legislator
Généré par l'IAThis article was the basis for the Court's decision to quash the ruling regarding the required written proof for modifications to a contract.
Texte complet
SUR LE MOYEN UNIQUE : VU L'ARTICLE 1793 DU CODE CIVIL ;
ATTENDU QUE LA PREUVE PAR ECRIT DE L'AUTORISATION, PAR LE MAITRE DE X... DES CHANGEMENTS OU AUGMENTATIONS PAR RAPPORT AU PLAN PREVU N'EST EXIGEE PAR CE TEXTE QU'AU CAS DE MARCHE A FORFAIT ;
ATTENDU QUE, POUR DEBOUTER GRASSET, CHARGE PAR ZOURDANI D'EFFECTUER DES TRAVAUX DE REMISE EN ETAT DE SON IMMEUBLE, DE SA DEMANDE EN PAIEMENT DU PRIX DES TRAVAUX SUPPLEMENTAIRES QU'IL AURAIT EFFECTUES, L'ARRET ATTAQUE ENONCE QUE "LA QUALIFICATION PARTIELLE A FORFAIT DES MARCHES DES 30 NOVEMBRE 1965 ET 11 JUILLET 1966" IMPORTAIT PEU DES LORS QUE GRASSET, QUI DEVAIT, "DE TOUTE MANIERE, PROUVER EN PRINCIPE PAR ECRIT" L'ACCORD DES PARTIES POUR L'INTEGRALITE DES TRAVAUX DONT IL RECLAME LE MONTANT, NE RAPPORTE PAS CETTE PREUVE ;
ATTENDU QU'EN STATUANT AINSI, ALORS QUE LE DEVIS "APPROXIMATIF" DU 30 NOVEMBRE 1965 PREVOYAIT EXPRESSEMENT "QU'IL POURRA ETRE MODIFIE SOIT EN PLUS SOIT EN MOINS SUIVANT LES TRAVAUX EXECUTES QUI SERONT JUSTIFIES PAR LA PRESENTATION DES MEMOIRES", LA COUR D'APPEL N'A PAS DONNE DE BASE LEGALE A SA DECISION ;
PAR CES MOTIFS : CASSE ET ANNULE L'ARRET RENDU LE 16 MARS 1970 ENTRE LES PARTIES, PAR LA COUR D'APPEL D'AMIENS ;
REMET, EN CONSEQUENCE, LA CAUSE ET LES PARTIES AU MEME ET SEMBLABLE ETAT OU ELLES ETAIENT AVANT LEDIT ARRET ET, POUR ETRE FAIT DROIT, LES RENVOIE DEVANT LA COUR D'APPEL DE REIMS.