Statutory limitation period for transport contract claims calculated under general rules, not special provisions.
Legislator summary
AI generatedThe court dismissed the insurance company's request to reject the claim as time-barred. The insured delivered goods on July 7, 1981, and the insurer filed a lawsuit on July 7, 1982, within the one-year period specified in the Transport Contract Act. The court ruled that this specific limitation period must be calculated according to the general rules of the Limitation Act rather than as a special provision, thereby validating the claim.
Legislator headnote
AI generatedTiekuljetussopimuslain 41 §:n 1 momentin 1 kohta; MääräaikaL 3 §: The one-year limitation period for claims under the Transport Contract Act is calculated according to the general rules of the Limitation Act, not as a special provision.
Keywords
AI generatedCited Legislation
AI generatedRelated Decisions
AI generatedFull text
Tiekuljetussopimuslain 41 §:n 1 momentin 1 kohdassa säädetty määräaika on laskettava niin kuin MääräaikaL 3 §:ssä sanotaan.
Vakuutusosakeyhtiölle oli VakL 25 §:n 1 momentin nojalla siirtynyt oikeus tiekuljetussopimuslain 41 §:n 1 momentin 1 kohdan mukaan vuoden kuluessa vireille pantavalla kanteella vaatia kuljetusvahinkoon perustuvaa korvausta. Vahingoittunut tavara oli luovutettu 7.7.1981 ja vakuutusyhtiö oli pannut kanteen vireille 7.7.1982 tiedoksi annetulla haasteella.
Tiekuljetussopimuslain 41 §:n 1 momentin 1 kohdassa säädettyä aikamääräystä kanteen vireille panoa varten ei ollut pidettävä MääräaikaL 1 §:ssä tarkoitettuna erikoismääräyksenä, vaan määräaika oli laskettava viimeksi mainitun lain 3 §:stä ilmenevällä tavalla. Vaatimus kanteen hylkäämisestä vanhentuneena hylättiin.
Läsnä: Isaksson, C. Kuhlefelt ja Korhonen (apuj.) Esittelijä: Bygglin
Lainvoimainen