Administrative court annuls environmental permit for startup emissions as they require separate production operation permit.
Legislator summary
AI generatedThe Administrative Court annulled the city's environmental authority's decision regarding the startup of a new production line. The authority had approved the company's noise and steam emission notification, but the court ruled these activities were integral to the main production process. Consequently, such emissions can only be permitted within a separate production operation permit, not a general startup notification.
Legislator headnote
AI generatedYmpäristönsuojelulaki 60 §; 64 §: Startup emissions integral to production require separate production operation permit under environmental protection law.
Keywords
AI generatedCited Legislation
AI generatedRelated Decisions
AI generatedFull text
Kaupungin ympäristönsuojeluviranomainen oli valituksenalaisella päätöksellään hyväksynyt yhtiön meluilmoituksen, joka koski mm. tehtaan uuden tuotantolinjan käynnistykseen liittyviä soihdutuksia ja höyryn ulospuhalluksia.
Hallinto-oikeus kumosi päätöksen siltä osin kuin se koski em. uuden tuotantolinjan käynnistykseen liittyviä toimenpiteitä, koska toimenpiteet olivat sellaisia, jotka liittyivät tehtaan varsinaiseen tuotantoon siinä määrin, että ne voitiin sallia vasta toimintaa koskevan ympäristöluvan yhteydessä.
Ympäristönsuojelulaki 60 § ja 64 §