Construction permit extension denied due to minor procedural defect in notice delivery.
Legislator summary
AI generatedThe Administrative Court dismissed the municipality's appeal regarding the denial of a construction permit extension. The municipality argued that the extension request was a minor matter under the Water Act, noting the short original deadline and project complexities, while the Water Authority refused to serve the notice. The court upheld the Authority's decision, ruling that the procedural defect was not significant enough to warrant changing the outcome.
Legislator headnote
AI generatedVesiL 2 luku 12 §; VesiL 16 luku 9 § 2 mom: A procedural defect in serving a notice for a minor extension request does not justify altering the decision if the original deadline was short and extension was warranted.
Keywords
AI generatedCited Legislation
AI generatedRelated Decisions
AI generatedFull text
Vesioikeuden kunnalle myöntämän rakentamisluvan mukaan tienpenkereen
ja sillan rakennustyö oli tehtävä 5 vuoden kuluessa
päätöksen lainvoimaiseksi tulosta. Kun tiehankkeen toteuttamiseen
liittyvistä muiden viranomaisten päätöksistä oli tehty
valituksia, joiden käsittelyyn eri viranomaisissa oli kulunut
aikaa, ei kunta ollut ryhtynyt määräajassa toteuttamaan hanketta.
Ennen rakennustyön määräajan umpeenkulumista kunta oli
hakenut luvan voimassaoloajan jatkamista. VEO oli myöntänyt
rakennustyötä varten jatkoajan hakemuksesta tiedoksiantoa toimittamatta.
VYO: rakennustyön määräajan jatkaminen oli vesilain 16 luvun 9
§:n 2 momentissa tarkoitetulla tavalla merkitykseltään vähäinen
asia. Tiedoksianto ei myöskään asian laatu huomioon ottaen
ollut ollut tarpeen. Huomioon ottaen aikaisemmin asetettu suhteellisen
lyhyt määräaika ja hankkeen toteuttamiseen liittyvät
vaiheet, määräajan pidentämiselle oli erityistä syytä. VEO:n
päätöksen lopputulosta ei muutettu.
VesiL 2 luku 12 §
VesiL 16 luku 9 § 2 mom
Lainvoimainen