Administrative court dismissed water damage claim as statute of limitations expired due to canal construction.
Legislator summary
AI generatedThe Administrative Court dismissed the plaintiff's claim for damages and remedial actions regarding water pollution caused by a canal construction. The plaintiff argued that the pollution resulted from unforeseen sediment collapse, but the court found the claim time-barred. Since the harmful effects occurred less than ten years before the claim was filed, the court ruled the claim did not meet the statutory limitation period requirements.
Legislator headnote
AI generatedVesiL 2 luku 27 § 2 mom; A claim for damages or remedial measures is time-barred if the harmful effects occurred more than ten years before the claim is filed.
Keywords
AI generatedCited Legislation
AI generatedRelated Decisions
AI generatedFull text
VYO katsoi, että Kimolanlahden mataloituminen ja lahden pohjakasvillisuuden
nopeutunut rehevöityminen olivat asiassa esitetyn
selvityksen mukaan johtuneet kanavan rakenteiden ja läjitysalueelle
kootun pohjalietteen ennalta arvaamattomasta sortumisesta.
Kun vahingolliset seuraukset olivat syntyneet vähemmän
kuin 10 vuotta ennen vaatimuksen kohdistamista luvansaajaan,
vahingonkärsijän korvaus- ja toimenpidevaatimukset
eivät vesilain 2 luvun 27 §:n 2 momentin viimeisen virkkeen
mukaan olleet vanhentuneet.
VesiL 2 luku 27 § 2 mom
Lainvoimainen