Court dismisses appeal; bridge not deemed new construction under Building Act requiring planning permission.
Legislator summary
AI generatedThe Administrative Court dismissed the appeal against the County Administrative Board's refusal to grant a building permit for a bridge. The Board determined the structure was not a new construction or a building under the Building Act, thus no permit was required. The court upheld this decision, finding the bridge did not fall within the statutory definitions necessitating planning approval.
Legislator headnote
AI generatedRakennuslaki 7 ja 9 luku; Rakennusasetus 121 ja 137 luku: A structure not meeting the legal definition of a new building or building under the Building Act does not require a building permit.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
Sorvaamorakennuksen päätyyn rakennettavaa neljä metriä korkeaa, seitsemän metriä leveää ja 10 metriä pitkää siltanosturia tukirakennelmineen ei pidetty uudisrakennuksena eikä RakA 121 §:ssä tarkoitettuna rakennelmana. Sen rakentamiseen ei siten tarvittu rakennuslupaa eikä rakennuslautakunnan lupaa. Rakennuslautakunnan ei tarvinnut tässä yhteydessä selvittää tarvittiinko nosturin rakentamiseen mahdollisesti terveydenhoitolain 26 §:ssä tarkoitettu lupa.
RakennusL 7 §
RakennusL 9 §
RakennusL 130 §
RakennusL 131 §
RakennusA 121 §
RakennusA 137 §
KHO:n päätös 13.2.1985 taltionumero 557. Ei muutosta.