Challenge Against Planning Authority Decision on Traffic Building Lines Upheld

Geschäftsnummer VB.2015.00711
Gericht / Behörde
Rechtsordnung Schweiz · Kanton Zürich (CH-ZH)
Entscheiddatum
Ausgang Abgewiesen (Dismissed)

Legislator-Zusammenfassung

KI-generiert

The administrative court confirmed the dismissal of a challenge against a planning authority's decision regarding traffic building lines, which followed a prior annulment decision by the construction appeals court, deeming the latter appealable due to the planner's narrow scope of discretion. The court reasoned that the appeals court correctly considered all affected properties, not just those of the challengers, when assessing the legality and expediency of the lines. Furthermore, the court found that the authority's attempt to impose lines based on a uniform, schematic concept, ignoring site-specific factors like topography and traffic, constituted a failure to exercise planning discretion, rendering the decision unlawful because the affected building lines lacked a reasonable prospect of realization within a foreseeable planning horizon.

Legislator-Regeste

Amtlich

Baulinien | Verkehrsbaulinien. Aufgrund der klaren Anweisung im Rückweisungsentscheid des Baurekursgerichts besteht für den Beschwerdeführer nur noch ein geringer Planungsspielraum. Der Rekursentscheid ist daher beschwerdefähig (E. 3). Rechtsgrundlagen und Rechtsprechung zu Baulinien (E. 6). Das Baurekursgericht hat die Überprüfung der Recht- und Zweckmässigkeit der Baulinien zu Recht nicht auf die Grundstücke der drei Anfechtenden beschränkt, sondern in seine Erwägungen alle von diesem Sondernutzungsplan Betroffenen, namentlich auch die Grundstücke auf der gegenüberliegenden Strassenseite, einbezogen (E. 8.2). Das mit RRB Nr. 39/2010 beschlossene Konzept der Aufarbeitung und Bewirtschaftung von bestehenden Baulinien entbindet die Planungsbehörde nicht von der sorgfältigen Prüfung jedes Einzelfalls. Soweit Baulinien ein Gebäude tangieren, werden die Grundeigentümer im Fall einer anstehenden Sanierung stets prüfen, ob sie unter Inanspruchnahme der Bestandesgarantie den Altbau erhalten oder mit einem Neubau auf die rückversetzte Baulinie zurückweichen und so möglicherweise ein kleineres Bauvolumen in Kauf nehmen wollen. Die Erfahrung zeigt, dass einzelne Gebäude erst nach sehr langer Zeit überhaupt baulich verändert werden. Unter diesen Umständen ist dem Baurekursgericht darin beizupflichten, dass den streitbetroffenen Baulinien die Realisierungswahrscheinlichkeit innerhalb eines vernünftigen Planungshorizonts abzusprechen ist (E. 8.3). Indem der Beschwerdeführer nach einem einheitlichen und weitgehend schematischen Konzept kantonsweit Baulinien festzusetzen gedenkt, hat er vorliegend sein Planungsermessen nicht ausgeübt und die sich aufgrund der Topografie und Verkehrssitution aufdrängende differenzierte Betrachtung nicht vorgenommen. Dieses Vorgehen ist nicht nur unzweckmässig, sondern auch rechtsverletzend (E. 8.5). Abweisung.

Schlagwörter

KI-generiert
Baulinie Planungsermessen Anfechtung von Verwaltungsverfügungen Strassenverkehrsrecht städtebauliche Vorschrift Legitimation gegen Baubewilligung

Zitierte Gesetzesbestimmungen

KI-generiert
Art. 93 Abs. I BGG
This provision is implicitly referenced as the decision likely falls under the general scope of federal supreme court review when mentioned alongside the reasoning for the final judgment, although the primary ground for the decision is found in the cantonal law cited below.
Art. 36 BV
This provision (Federal Constitution) is cited as a general legal basis relevant to the matter, likely concerning property rights affected by the planning decision.
§ 96 Abs. I PBG
This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).
§ 96 Abs. II PBG
This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).
§ 98 PBG
This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).
§ 99 Abs. I PBG
This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).
§ 265 Abs. I PBG
This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).
§ 338c PBG
This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).
KI-generiert

Zentrale Rechtsfragen, extrahiert von Legislator

KI-generiert
Art. 93 Abs. I BGG

This provision is implicitly referenced as the decision likely falls under the general scope of federal supreme court review when mentioned alongside the reasoning for the final judgment, although the primary ground for the decision is found in the cantonal law cited below.

§ 96 Abs. I PBG

This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).

§ 96 Abs. II PBG

This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).

§ 98 PBG

This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).

§ 99 Abs. I PBG

This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).

§ 265 Abs. I PBG

This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).

§ 338c PBG

This provision is cited in the list of applicable legal norms, suggesting it formed part of the legal basis for the decision regarding building lines (Baulinien).

Art. 36 BV

This provision (Federal Constitution) is cited as a general legal basis relevant to the matter, likely concerning property rights affected by the planning decision.

§ 14 StrassG

This provision (Roads Act) is cited in the list of applicable legal norms, suggesting it formed part of the legal basis concerning road planning aspects relevant to the Baulinien.

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

Verwaltungsgericht des Kantons Zürich: VB.2015.00711

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

Druckansicht

--- · --- · --- · Geschäftsnummer: · VB.2015.00711 · Entscheidart und -datum: · Endentscheid vom 13.07.2016 · Spruchkörper: · 3. Abteilung/3. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Raumplanungs-, Bau- und Umweltrecht · Betreff: · Baulinien · Verkehrsbaulinien. Aufgrund der klaren Anweisung im Rückweisungsentscheid des Baurekursgerichts besteht für den Beschwerdeführer nur noch ein geringer Planungsspielraum. Der Rekursentscheid ist daher beschwerdefähig (E. 3). Rechtsgrundlagen und Rechtsprechung zu Baulinien (E. 6).

Das Baurekursgericht hat die Überprüfung der Recht- und Zweckmässigkeit der Baulinien zu Recht nicht auf die Grundstücke der drei Anfechtenden beschränkt, sondern in seine Erwägungen alle von diesem Sondernutzungsplan Betroffenen, namentlich auch die Grundstücke auf der gegenüberliegenden Strassenseite, einbezogen (E. 8.2). Das mit RRB Nr. 39/2010 beschlossene Konzept der Aufarbeitung und Bewirtschaftung von bestehenden Baulinien entbindet die Planungsbehörde nicht von der sorgfältigen Prüfung jedes Einzelfalls. Soweit Baulinien ein Gebäude tangieren, werden die Grundeigentümer im Fall einer anstehenden Sanierung stets prüfen, ob sie unter Inanspruchnahme der Bestandesgarantie den Altbau erhalten oder mit einem Neubau auf die rückversetzte Baulinie zurückweichen und so möglicherweise ein kleineres Bauvolumen in Kauf nehmen wollen.

Die Erfahrung zeigt, dass einzelne Gebäude erst nach sehr langer Zeit überhaupt baulich verändert werden. Unter diesen Umständen ist dem Baurekursgericht darin beizupflichten, dass den streitbetroffenen Baulinien die Realisierungswahrscheinlichkeit innerhalb eines vernünftigen Planungshorizonts abzusprechen ist (E. 8.3). Indem der Beschwerdeführer nach einem einheitlichen und weitgehend schematischen Konzept kantonsweit Baulinien festzusetzen gedenkt, hat er vorliegend sein Planungsermessen nicht ausgeübt und die sich aufgrund der Topografie und Verkehrssitution aufdrängende differenzierte Betrachtung nicht vorgenommen.

Dieses Vorgehen ist nicht nur unzweckmässig, sondern auch rechtsverletzend (E. 8.5). Abweisung. · --- · Stichworte: · BAULINIEN BAULINIENREVISION BAUPROJEKT EIGENTUMSBESCHRÄNKUNG KERNZONE ÖFFENTLICHES INTERESSE PLANUNGSERMESSEN PLANUNGSHORIZONT RÜCKWEISUNGSENTSCHEID SONDERNUTZUNGSPLÄNE STAATSSTRASSE STRASSENABSTAND TROTTOIR VERKEHRSBAULINIEN · Rechtsnormen: · Art. 93 Abs. I BGG Art. 36 BV § 96 Abs. I PBG § 96 Abs. II PBG § 98 PBG § 99 Abs. I PBG § 265 Abs. I PBG § 338c PBG § 14 StrassG · Publikationen: · - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3