Case concerning accident insurance benefits and exhaustion of domestic remedies.
Legislator-Zusammenfassung
KI-generiertThis case concerned a procedure for obtaining accident insurance benefits, which became complex and lengthy. The court found the application inadmissible because the applicant had not exhausted domestic remedies. The court reasoned that Article 26 of the European Convention on Human Rights is satisfied if the delay in proceedings is caused by an appeal from the opposing party, and there is no avenue to complain about the length of the proceedings before the appellate body.
Legislator-Regeste
KI-generiertArt. 26 CEDH, Art. 26 EMRK, Art. 26 CEDU; Case concerning accident insurance benefits and exhaustion of domestic remedies: The court found the application inadmissible because the applicant had not exhausted domestic remedies. The court reasoned that Article 26 of the European Convention on Human Rights is satisfied if the delay in proceedings is caused by an appeal from the opposing party, and there is no avenue to complain about the length of the proceedings before the appellate body.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertZentrale Rechtsfragen, extrahiert von Legislator
KI-generiertUsed to declare the application inadmissible because the applicant had not exhausted domestic remedies.
Volltext
JAAC 62.123
Déc. rendue en anglais1 par la Comm. eur. DH le
10 septembre 1997 déclarant irrecevable la req. N° 26564/95, Hrvoje Grbavac c / Suisse
Procédure visant à l’obtention de prestations d’assurance de la Caisse nationale suisse d’assurance-accidents (CNA). Durée de la procédure dans un cas complexe. Art. 26 CEDH. Epuisement des voies de recours internes. Lorsqu’une requête a trait à la durée de la procédure, cette disposition est respectée si la longueur de la procédure est due au dépôt d’un recours par la partie adverse et qu’il n’existe pas de moyen de se plaindre de la durée de la procédure devant l’instance appelée à juger.
Verfahren betreffend Versicherungsleistungen der Schweizerischen Unfallversicherungsanstalt (SUVA). Dauer des Verfahrens in einem komplexen Fall. Art. 26 EMRK. Erschöpfung des innerstaatlichen Rechtszuges. Bei einer Beschwerde betreffend die Verfahrensdauer ist diese Bestimmung beachtet, wenn die Länge des Verfahrens auf die Einreichung einer Beschwerde durch die Gegenpartei zurückzuführen ist und vor der Rechtsmittelinstanz keine Möglichkeit bestanden hat, sich über die Dauer zu beschweren.
Procedura tendente all’ottenimento di prestazioni assicurative da parte dell’Istituto nazionale svizzero di assicurazione contro gli infortuni (INSAI). Durata della procedura in un caso complesso.
Art. 26 CEDU. Esaurimento delle vie di ricorso interne. Ove una domanda concerna la durata della procedura, tale disposizione è rispettata se il protrarsi della procedura è dovuto all’interposizione di un ricorso ad opera della controparte e non vi è modo di ricorrere contro la durata della procedura dinanzi all’istanza chiamata a statuire.
Schweizerisches Bundesarchiv, Digitale Amtsdruckschriften Archives fédérales suisses, Publications officielles numérisées Archivio federale svizzero, Pubblicazioni ufficiali digitali
JAAC 62.123 - Déc. rendue en anglais1 par la Comm. eur. DH le 10 septembre 1997 déclarant irrecevable la req. N° 26564/95, Hrvoje Grbavac c / Suisse
In Verwaltungspraxis der Bundesbehörden Dans Jurisprudence des autorités administratives de la Confédération In Giurisprudenza delle autorità amministrative della Confederazione
Jahr 1998 Année Anno
Band 62 Volume Volume
Seite --- Page Pagina
Ref. No 150 003 767
Das Dokument wurde durch das Schweizerische Bundesarchiv und die Bundeskanzlei konvertiert. Le document a été digitalisé par les Archives Fédérales Suisses et la Chancellerie fédérale. Il documento è stato convertito dall'Archivio federale svizzero e della Cancelleria federale.