Construction Lien Deadline with Successive Contracts and Final Component Delivery
Legislator-Zusammenfassung
KI-generiertThe court considered the deadline for registering a construction lien under Article 839 Para. 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.
Legislator-Regeste
KI-generiertArt. 839 Abs. 2 ZGB, Art. 839 ZGB; Construction Lien Deadline with Successive Contracts and Final Component Delivery: 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertZitierte Rechtsprechung
KI-generiertVerwandte Entscheide
KI-generiertZentrale Rechtsfragen, extrahiert von Legislator
KI-generiertThis provision governs the deadline for registering a construction lien, which was the central issue decided by the court.
Volltext
Rechtsprechung Luzern
Instanz: · Obergericht
Abteilung: · I. Kammer
Rechtsgebiet: · Sachenrecht
Entscheiddatum: · 05.12.2002
Fallnummer: · 11 02 72
LGVE: · 2002 I Nr. 22
Leitsatz: · Art. 839 Abs. 2 ZGB. Beginn der Dreimonatsfrist für die Eintragung eines Bauhandwerkerpfandrechts bei mehreren Werkverträgen.
Rechtskraft: · Diese Entscheidung ist rechtskräftig.