Construction Lien Deadline with Successive Contracts and Final Component Delivery

Geschäftsnummer 11 02 72
Gericht / Behörde
Rechtsordnung Schweiz · Kanton Luzern (CH-LU)
Entscheiddatum
Ausgang Gutgeheissen (Allowed)

Legislator-Zusammenfassung

KI-generiert

The court considered the deadline for registering a construction lien under Article 839 Para. 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.

Legislator-Regeste

KI-generiert

Art. 839 Abs. 2 ZGB, Art. 839 ZGB; Construction Lien Deadline with Successive Contracts and Final Component Delivery: 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.

Schlagwörter

KI-generiert
Bauwerkvertrag Einreichungsdatum gesetzliche Fristen Eintragung eines gesetzlichen Pfandrechts Zahlungsfrist Obligationenrecht

Zitierte Gesetzesbestimmungen

KI-generiert

Zitierte Rechtsprechung

KI-generiert
KI-generiert

Zentrale Rechtsfragen, extrahiert von Legislator

KI-generiert
Art. 839 Abs. 2 ZGB

This provision governs the deadline for registering a construction lien, which was the central issue decided by the court.

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

Rechtsprechung Luzern

Instanz: · Obergericht

Abteilung: · I. Kammer

Rechtsgebiet: · Sachenrecht

Entscheiddatum: · 05.12.2002

Fallnummer: · 11 02 72

LGVE: · 2002 I Nr. 22

Leitsatz: · Art. 839 Abs. 2 ZGB. Beginn der Dreimonatsfrist für die Eintragung eines Bauhandwerkerpfandrechts bei mehreren Werkverträgen.

Rechtskraft: · Diese Entscheidung ist rechtskräftig.